Okaloosa County BOCC — July 30, 2015 — I. e. Colleen Marine contract — reading text
Part 17 of 19. These parts divide the reading text for browsing; they are not the source document's page numbers.
I. e. Colleen Marine contract — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Contractor will not
be reimbursed for any materials dropped or deployed outside of the proposed reef site(s) and shall be
responsible for any damages or costs (e.g., damage to private property or roadways) resulting from such
occurrences.
I. The Contractor shall complete and sign the FWC Artificial Reef Cargo Manifest and Pre-Deployment
Notification Form (included within the DOA permit authorization) for each offshore deployment and
submit the document(s) to the required regulatory agencies, the Owner, and Engineer a minimum of 14
days prior to offshore deployment. By signing the Pre-Deployment notification, the Contractor certifies
that all materials are free from asphalt, petroleum, other hydrocarbons and toxic residues. The Cargo
Manifest Form and copies of all regulatory authorizations shall be maintained onboard the vessel at all
times during transport of materials, pursuant to Chapter 370.25, Florida Statutes.
J. The Contractor shall estimate the tonnage of reef material on the barge for each deployment prior to
departing the waterside staging area. The Contractor shall document the method for calculating the
tonnage and perform the measurements and calculations (before and after barge draft calculations) in
the presence of the Owner or Engineer in accordance with the proposed measurement procedures
discussed in Section 10.
K. During the loading of barges with artificial reef materials, the barge shall be sufficiently moored in
protected waters approved for mooring/anchoring. The barges shall be made available to the Owner and
Engineer while moored in protected waters to record the pre- or post-deployment waterline of the barge
or inspect materials prior to deployment.
8.4 OFFSHORE TRANSPORT AND SUPPORT VESSELS
A. All offshore work vessels (e.g., tug and/or transport vessel, support vessel(s), etc.) shall meet all U.S.
Coast Guard certification and safety requirements, be ABS certified (if required), and be equipped with a
working Differential Global Positioning System (DGPS) unit accurate within 1 meter and other marine
electronics including a working VHF radio and depth sounder/fathometer accurate to within 1 ft. The
Page 28 of 37
GPS system shall be capable of producing location data in both geographic coordinates and State Plane
Coordinates, North American Datum of 1983 (NAD83), Adjustment of 2007 (NSRS2007), Florida North
Zone.
B. The Contractor shall provide a support vessel, captain and sufficient crew to assist in the reef
construction effort. The support vessel shall be used to place marker buoys at each artificial reef location
as a reference for reef material placement. The marker buoys shall be placed, at a minimum, at the four
corners and the centroid of the reef, unless approved otherwise by the Owner or Engineer. The support
vessel should be capable of accommodating its crew and three additional individuals — Owner
representatives, FWC staff, and/or project sponsors — and their dive gear. After assisting in the
construction effort, the support vessel and crew shall be made available to support a minimum of two
reef monitoring dives to be performed by FWC agents. FWC will be required to coordinate for these
dives with the Contractor prior to artificial reef deployment. The Owner’s representative designated as
an official observer shall remain on-site during the entire deployment phase of the operation to confirm
all deployment operations.
C. The support vessel shall be equipped with an electronic depth sounder accurate to within 1 ft. and a
real-time Differential Global Positioning System (DGPS) accurate within 1 meter and capable of
navigating to specific sites. The support vessel — accommodating the Owner representatives, FWC
staff, and/or project sponsors — shall verify the maximum vertical relief and footprint of the reefs
following construction as required by regulatory authorizations and these specifications. The verification
shall occur following each load or partial load of material placed.
8.5 PRE-DEPLOYMENT BOTTOM SURVEY
The USACE regulatory authorization requires a bottom survey within one year prior to artificial reef
material deployment. The County performed a bottom survey of the two permitted fish havens (Fish
Haven #13 and #14) on February 28, 2012; the report is included within Appendix E. The bottom survey
included fathometer transect surveys and visual (scuba diver) observations at the centroids of both
areas. The report concluded the bottom conditions within both Fish Haven #13 and #14 consisted of
sand substrate with no indication of potential hard bottom. To meet USACE permitting requirements, the
Contractor shall perform a second assessment of the bottom conditions prior to artificial reef
deployment. The assessment shall be accomplished by diver surveys, submersible video camera,
fathometer, depth/bottom sounder (e.g. “fish finder”), or side-scan sonar. The inspection may occur at
the time of deployment but no more than one year prior to deployment. The Contractor shall notify the
Owner and Engineer immediately if submerged natural resources (e.g. seagrass beds, hard bottom,
corals, etc.) are observed. The Contractor shall notify the Owner, Engineer, and USACE immediately if
evidence of cultural/archeological resources, such as sunken vessels or ballast, are found.
8.6 REGULATORY AUTHORIZATIONS AND CONDITIONS
The Contractor shall maintain copies of all regulatory authorizations, attachments, and cargo manifests
onboard the deployment vessel and support vessel(s) at all times. The Contractor shall comply with the
Sea Turtle and Smalltooth Sawfish Construction Conditions throughout transport and deployment
operations; these Construction Conditions shall also apply to the Gulf Sturgeon. The Contractor shall
comply with the Standard Manatee Conditions for in-water work throughout transport and deployment
operations. The Contractor shall comply with the Vessel Strike Avoidance Measures and Injured or
Dead Protected Species Reporting guidance for marine turtles and marine mammals throughout
transport and deployment operations. The Contractor shall be responsible for ensuring that all permit
conditions are met.
Page 29 of 37
8.7 ARTIFICIAL REEF DEPLOYMENT
A. The Contractor shall have on-site current NOAA nautical charts of the deployment area, with the overall
Fish Haven and individual deployment sites (#1 and #2) as well as any adjacent natural reef areas
indicated on the chart. The proposed artificial reef coordinates for Reef Sites #1 and #2 (centroid and
corner coordinates of the reef site) shall also be in possession of the Contractor when on site.
B. Effective and reliable communications shall exist at all times between Contractor personnel— including
all vessel captains, mates and crew members assisting in the deployment — and with the on-site Owner
observer. A marine radio channel shall be designated, used and monitored throughout the offshore
transport and deployment operations.
C. Deployment operations will only be initiated when sea height in the project area(s) is no greater than
three to four feet as forecast by the NOAA weather service supporting Destin area waters out 20
nautical miles. Both the Owner and the Engineer have the authority to suspend reef deployment
operations if positioning and other deployment objectives, including safety of personnel and equipment,
are not being met.
D. During the deployment of the reef material, the transport/deployment vessel shall be sufficiently moored
through double anchoring (minimum), be spudded down, or otherwise be held securely in place with
minimal movement (+/-10 feet) to ensure accurate placement of the reef materials on the bottom in the
designed configuration. In certain situations where spudding or anchoring is impossible due to depth or
current conditions, the materials barge may be held in position by the tug for the deployment operation.
In such cases, the Owner or Engineer will be in constant contact with the tug and the barge crew via
telephone and/or radio to verify the Contractor is meeting positioning requirements. The Owner or
Engineer may require the Contractor to stop offloading at any time to reposition the barge if reef
positioning requirements are not being met.
E. Winds and currents may change offshore conditions rapidly. The deployment of materials may be
stopped at any time, as often as required by the Owner or Engineer, to confirm correct placement of the
materials by means deemed suitable by the Owner under the prevailing conditions.
F. The Contractor shall program the exact latitude/longitude coordinates (provided in the Construction
Drawings) of each patch reef, as well as the overall artificial reef area, into the deployment vessel’s GPS
unit. GPS coordinate system for location data will be Geographic, National Geodetic Datum of 1983.
G. The Contractor’s Project Manager shall oversee the temporary marking of the reef deployment location
in advance of reef material deployment in order to ensure proper placement of the reef material. The
Contractor’s proposed plan for marking the reef sites, mooring the barge, and deploying the material
must receive Owner or Engineer approval prior to commencement of offshore transport. The Contractor
shall place 5 temporary marker buoys, one at each of the artificial reef site’s four corners (marking the
deployment area) and one at the centroid. The markers shall be buoys 16 inches in diameter minimum –
clearly visible to the transport vessel captain and sufficiently anchored to not drift during deployment
activities and maintain reef location accurately. Precise GPS placement of marker buoys that do not shift
position with time will also be required to ensure the reef is constructed as designed. The Owner’s
observer or Engineer may verify the location of these buoys prior to or throughout deployment
operations. The Contractor may elect to use additional buoys for location or deployment control;
however, any additional buoys shall be a separate color than the five required markers to easily
distinguish the four corners and centroid.
Page 30 of 37
H. Under no circumstances shall materials be placed in the water without the on-site Owner’s acceptance
of the barge’s final moored position. The Contractor shall receive a verbal authorization from the Owner
or Engineer prior to off-loading any materials and shall remain on-site until released by the Owner or
Engineer. Precise positioning of the barge is required in order to avoid any impacts from materials to
existing artificial or natural reef structures. Offloading of materials may be stopped at any time by the
Owner or Engineer in order to make an inspection dive to check placement of the materials or to require
repositioning of the barge due to other factors.
I. An approximately equal volume of material shall be placed at each artificial reef site. Each completed
artificial reef site and the project overall shall contain approximately 80% materials sourced from Eglin
AFB Range C-64ABC and approximately 20% materials sourced from the Okaloosa County