Okaloosa County BOCC — July 25, 2016 — Road Construction - PBB
Road Construction - PBB in the July 25, 2016 Okaloosa County BOCC meeting materials. Preserved county-portal original with machine-extracted reading text.
Preserved among the July 25, 2016 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1343). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used ; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Road Construction - PBB
Date
July 25, 2016
Publisher
Okaloosa County Board of County Commissioners
Where to find it
3
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
Road Construction - PBB — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
BOARD OF COUNTY COMMISSIONERS
OKALOOSA COUNTY, FLORIDA
SERVICE AREA: TRANSPORTATION
DEPARTMENT/PROGRAM: ROAD/BRIDGE CONSTRUCTION
PROGRAM DESCRIPTION: The Public Works Department provides to the public; road and storm-water
construction, enhancement, and replacement; resurfacing and open graded hot mix asphalt (formerly cold mix
base stabilization); bridge construction; and other major infrastructure construction services. Projects are
performed by in-house staff as well as contract services. The division also provides both rescue and recovery
operations during disasters and other emergencies which impact road and storm-water infrastructure.
REVENUE: Road and Bridge Construction is funded within the Road & Bridge Construction Fund. Supporting
revenue of the Road & Bridge Construction Fund are “non-discretionary” (local option gas tax (LOGT)) fuel
taxes, constitutional gas taxes (CGT), interest, other miscellaneous revenue and state grants.
MAJOR ACCOMPLISHMENTS LAST YEAR:
Robinson Road – began dirt to pave project – 1.9 miles
Kervin Road – began dirt to improvement project
Foxwood Subdivision Phase III – begin final phase of major storm-water rehabilitation
Mount Olive Road – Resurfacing
Lake Lorraine – Major storm-water rehabilitation
Old Ebenezer – overlay/preservation of cold mix
PJ Adams Emergency Overlay - two miles
Sheriff Office Parking Lot Extension-Site Clearing, Sub-base prep, gravel and pavement
Millings Conversion Roads
-William Gary Johnson Rd
Resurfacing/Road Preservation
17.67 miles of road resurfaced/chip sealed/micro-surfaced
Completed the dirt to pave project on Gilmore Road
Completed the Emergency Overlay of a portion of PJ Adams (night work) using in house staff
Completed pavement on Atoka Road
Completed drainage improvement on Troon Way
PROGRAM GOAL: The mission of the Okaloosa County Public Works Department is to provide transportation
and infrastructure services to residents and visitors of Okaloosa County. The goal is to accomplish this mission
through its six primary divisions: Engineering, Environmental Services, Traffic Operations, Roads, Resources,
and Administrative Services.
KEY OBJECTIVES:
1. To construct the roads, bridges, and associated infrastructure to support the transportation needs of
unincorporated Okaloosa County.
2. Complete the annual Overlay Program for Commissioner Districts 1 – 5.
3. Rehabilitate cold mix roads that are currently near or beyond their life expectancy
4. Oversee contracted construction projects.
5. Convert wooden bridges to concrete.
6. Oversee/Construct Emergency Watershed Projects.
7. Stabilize dirt roads with millings.
8. Antioch Road – Drainage improvements and resurface.
9. Okaloosa Lane – Dirt to pave & Bridge project
10. Kervin Road – Install drainage swales and stabilize road.
11. Robinson Road – Dirt to pave.
12. Build bridges- Old Antioch and Okaloosa Lane
13. Live Oak Church Road-Overlay
PERFORMANCE MEASURES:
Actual Estimate Proposed
Performance Measures
FY14/15 FY15/16 FY16/17
Output
Miles of roads resurfaced 17.67 19.65 18.5
Miles of roads restriped (focus was on School Zones) 8.4 21 20
Efficiency
Jurisdictional miles of roads maintained 946 948 950
Miles of cold mix stabilized roads rehabilitated 5.3
Only a preview is loaded on this record page. The linked reading pages contain the remaining text and work without JavaScript.
Citation & reuse
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — July 25, 2016 — Road Construction - PBB.” July 25, 2016. Road Construction - PBB. Crypt of Echoes evidence ID LED-2026-f7aecd577cf7494bae251ce2edc59872. http://127.0.0.1:58097/evidence/LED-2026-f7aecd577cf7494bae251ce2edc59872. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, Road Construction - PBB, meeting materials for July 25, 2016. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=4&ID=11885&MeetingID=1343
Preserved county public-record source. Third-party attachments may retain their original rights.