AVCON, INC.
ENGINEERS & PLANNERS
320 Bayshore Drive, Suite A
Niceville, Florida 32578
Phone: (850) 678-0050
Fax: (850) 678-0040
www.aveonine.com
TASK ORDER SUMMARY
Professional Consulting Services
Okaloosa County Public Works
Task Order No.: 05
AVCON Project No.: 2014.125.04
Date: March 22, 2016
AVCON, INC.,, a Florida Corporation (hereinafter “CONSULTANT”) agrees to perform and complete
the following services (hereinafter “Services”) for Okaloosa County Public Works (hereinafter
“COUNTY?”), in accordance with the terms and conditions of the Agreement for Consulting Engineering
Services (Contract No.: C14-2077-PW), dated October 3, 2013, all of which terms and conditions are
incorporated herein by reference.
1. Task Location: Bluewater Bay MSBU, Okaloosa County, Florida
2. Task Name: Bluewater Bay Stormwater Hazard Mitigation Improvements
3. Task Description/Scope of Services: CONSULTANT shall perform the professional services
contained in Exhibit “A* dated March 22, 2016 and attached hereto.
4, Compensation: For all work performed in accordance with Section 3, the CONSULTANT shall
be compensated on a Lump Sum basis. The Lump Sum fee shall be Ninety-Eight
Thousand, Two Hundred Four and 00/100 dollars ($98,204.00 LS) derived as follows:
Bluewater Bay Stormwater Hazard Mitigation Improvements
TASK 1: Pond & Associated Conveyance System Inventory $ 6,500.00
TASK 2: Hydraulic Model of Stormwater System $ 13,600.00
TASK 3: Hydraulic Analysis Report $ 31,260.00
TASK 4: Phasing Plan & Budgets $ 9,880.00
TASK 5: Professional Design Phase Services: 0-90% $ 12,000.00
TASK 6: Professional Design Phase Services: 90-100% $ 5,000.00
TASK 7: Environmental & Stormwater Permitting $ 10,000.00
TASK 8: Grant Administration $ 10,000.00
Total Lump Sum Fee: $ 98,204.00 LS
CIVIL & STRUCTURAL ENGINEERING AIRPORT & AVIATION CONSULTING B TRANSPORTATION DESIGN & PLANNING
Direct expenses necessary to perform the scope of work, including related printing/plotting
and mail charges, shall be included in the Lump Sum fee. Progress payments shall be
made monthly and shall be by an estimate of the percent complete in accordance with the
project progress.
Sincerely,
AVCON, INC.
Virgil C. “Lee” Lewis, P.E.
Regional Manager
CIVIL & STRUCTURAL ENGINEERING B AJRPORT & AVIATION CONSULTING B TRANSPORTATION DESIGN & PLANNING
AVCON, INC. Attachment A: Scope of Services
Bluewater Bay MSBU Bluewater Bay Stormwater Hazard Mitigation Improvements
ATTACHMENT A: SCOPE OF SERVICES
AVCON, INC.
Bluewater Bay Stormwater Hazard Mitigation Improvements
March 22, 2016
l. PURPOSE
Localized flooding is occurring in certain residential areas associated with Curacao Way, Dominica Way,
Southwind Drive and Aruba Way in Niceville, Florida following high-intensity storm events. This scope of
services describes professional services to be performed by AVCON, INC. (“CONSULTANT”) to facilitate
an inventory and hydraulic study of the stormwater systems associated with a portion of the Bluewater
Bay drainage system spanning from the north end of Southwind Drive to the outfall at Grass Lake.
This project shall evaluate the drainage basin association with the areas of concern to identify
deficiencies in the individual components of the drainage system. The project shall identify upgrade
recommendations to address the flooding and analyze the impacts to the downstream ponds and
waterways flowing to Grass Lake. The results of these efforts will be utilized to develop construction
documents intended to improve drainage and to mitigate future hazards associated with the existing
drainage basin. The work shall include permitting for the proposed improvements.
The improvements, when completed, shall minimize or eliminate future structural damage and provide
protection to the surrounding properties in the area by minimizing recurring flooding and reducing
repetitive flood loss to properties. The completed project shall provide protection against a 25-year
storm event.
The work will be funded through the Hazard Mitigation Grant Program, DR-4177-06-R, as approved by
the Florida Division of Emergency Management and the Federal Emergency Management Agency
(Project 4177-06-R). The work shall include preliminary engineering designs and calculations and
permitting and shall be completed in accordance with all applicable federal, state, and local laws,
regulations, and codes. No construction activities shall be initiated during this project.
. PROJECT LIMITS
The limits of the drainage basin to be considered in the study are those contributing to the outfall
traversing Curacao Way as approximated in Attachment B.
Hi. SCOPE OF SERVICES
The following items describe the tasks comprising the scope of services for this project.
TASK 1: POND AND ASSOCIATED CONVEYANCE SYSTEM INVENTORY
Task 1 of this project shall include an inventory of the existing stormwater conveyance system
including stormwater pipes, inlets, contributing swales, and ponds. This task shall also include
analyzing the contributing drainage basins to determine the effects of the critical storm events on
the system.
PAGE 1 OF 7
AVCON, INC.
Attachment A: Scope of Services
Bluewater Bay MSBU Bluewater Bay Stormwater Hazavd Mitigation Improvements
1.1,
1.2,
1.3.
1.4.
1.5.
Coordinate Project Scope, Budget, Schedule, Design Issues: CONSULTANT shall
coordinate the project scope, budget, schedule, and related issues with representatives
of the County and MSBU as required.
Request and Collect Existing Survey/As-Built Data: CONSULTANT shall request and
collect existing survey/as-built data from County Public Works survey staff to identify
drainage system information required for modeling the system. Survey information shall
address elevations associated with swales, stormwater pipes, non-permitted discharges,
existing inlets and associated stormwater structures contributing to the study limits. No
survey services are assumed in this scope; any required survey services shall be
considered additional services.
Review and Confirm Existing Survey/As-Built Data: CONSULTANT shall review survey
data to confirm adequacy of elevation and location information related to contributing
swales, stormwater pipes, non-permitted discharges, existing inlets and associated
stormwater structures. No survey services are assumed in this scope.
Perform Site Visit: CONSULTANT shall visit the project site to visually verify stormwater
system components and general conditions of the various components.
Prepare Base Map with Existing Survey Data: CONSULTANT shall prepare a base map
with the hydraulic basins identified and existing stormwater system components clearly
summarized. Map shall also highlight pipes that are damaged or sediment has been
visually identified.
TASK 2: HYDRAULIC STUDY OF STORMWATER SYSTEM
Task 2 shall include the preparation of a hydraulic model to enable evaluation of the drainage
system in various storm events. This evaluation shall result in the identification of system
deficiencies during the assumed storms.
2.1,
2.2,
2.3.
2.4.
Calculate Basin and Sub-Basin Areas: CONSULTANT shall review existing topographical
data and USGS maps to determine the contributing drainage area associated with the
drainage basin. Sub-basins shall also be identified within the basin to facilitate
identification of runoff characteristics.
Identify Runoff Characteristics: CONSULTANT shall determine water volumes from this
area and determine the critical storm with a range of frequencies up through the 100-
year frequency (i.e. 2, 5, 10, 25, and 100-year) and a range of durations through the 24-
hour duration {i.e. 1, 2, 4, 8 and 24-hour).
Prepare Hydraulic ICPR Model: CONSULTANT shall prepare a hydraulic model of the
stormwater piping system and ponds to evaluate system performance and impacts of
the critical storm events in the current condition. The model shall be developed using
ICPR software and shall account for critical tailwater conditions.
Test / Validate Model: CONSULTANT shall test the hydraulic AJICPR model to validate
the model generates observed localized flooding conditions.
PAGE2 OF 7
AVCON, INC. Attachment A: Scope of Services
Bluewater Bay MSBU Bluewater Bay Stormwater Hazard Mitigation Improvements
2.5. Perform Alternatives Analysis; Identify Deficiencies: CONSULTANT shall perform
modeling analysis to determine impacts of various high-intensity storm events. The
analysis shall include identification of system deficiencies under the storm event
assumptions. The analysis will also consider any tailwater impacts on the system
resulting from the water levels at the basin outfall, just south of Curacao Way.
TASK 3: HYDRAULIC ANALYSIS REPORT
Task 3 shall include the preparation report summarizing the hydraulic model evaluation, including
assumptions and results.
3.1 Prepare Hydraulic Study: CONSULTANT shall prepare a hydraulic analysis report
summarizing the findings from the inventory and hydraulic analysis for the pipes/culvert
systems and ponds with conveyance to Grass Lake. The report shall include
recommendations pertaining to the system capacity, illegal discharges, pipe
repair/replacement, and recommendations for pond/natural channel modifications that
may be required to address the runoff and flooding concerns.
If impacts to waters of the United States or wetlands are identified in the study,
coordination with USACE shall be required. Any conditions imposed by the USACE shall
be included in the final design plans, narrative and project implementation actions.
3.2 Coordinate with Bluewater Bay MSBU and Okaloosa County Public Works:
CONSULTANT shall coordinate with the Bluewater Bay MSBU and County staff to discuss
issues and other factors that may affect the overall performance of the system and the
project results in general. CONSULTANT shall also participate in a meeting with
Bluewater Bay MSBU to review the recommendations and any comments the board
may have.
TASK 4: PHASING PLAN & BUDGETS
Task 4 includes preparing budgets for stormwater hazard mitigation improvements and any phasing
recommendations that may apply.
4.1 Prepare Estimated Project Budgets: CONSULTANT shall provide an engineer’s opinion of
recommended budgets for the improvements required to improve the existing
stormwater system. Budgets shall detail the probable construction costs, professional
services costs, with recommended contingencies.
4.2 Provide Phasing Recommendations: CONSULTANT shall provide recommendations
assigning priorities on repairing or replacing stormwater pipes, outfall structures, and
other pond modifications to ensure the most effective implementation strategy based
on available funding.
TASK 5: PROFESSIONAL DESIGN PHASE SERVICES—0-90% DESIGN
Based on the recommendations from Task 3 and Task 4, Task 5 includes the development of 90%
design plans implementing the stormwater improvements recommended for the basin. It is
anticipated the FDOT Specifications for Road & Bridge Construction, latest edition, will serve as the
basis for technical specifications.
PAGE3 OF 7
AVCON, INC. Attachment A: Scope of Services
Bluewater Bay MSBU Bluewater Bay Stormwater Hazard Mitigation Improvements
5.1 Prepare 90% Construction Drawings: CONSULTANT shall prepare 90% design
development drawings for coordination with COUNTY staff:
- Cover Sheet - Erosion Control Plan
- Existing Conditions Plan - Grading & Drainage Plans
- General Notes & Quantities - Grading & Drainage Details
- Site Plan - Pavement Repair Details
5.2 Address/Incorporate Review Comments: Address 100% review comments from the
state review and from County Public Works staff.
5.3 Coordinate Anticipated Ground Disturbing Activities: Tribal Consultation shall be
required for proposed ground disturbing activities. Where applicable, the following
documents shall be required and submitted as part of deliverables:
a) Horizontal limits and vertical depths of ground disturbance in feet and square feet
(mapped)