CHANGE ORDER FORM
Date: 06/24/2016 Contract No: C15-2310-AP Change Order No.:_01
Owner: __ OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS
Contractor: Lord & Son Construction, Inc.
Description of this summary change: Increase the amount of time needed to complete the project.
ISA requested changes to incorporate elements from the current Planning Guidelines and Design
Standards (PGDS) Version (V5.0) that was approved by TSA post-award of this construction contract.
In addition, TSA requested alterations to temporary bag screening location and configuration that
varied from the issued construction drawings. This iterative process required multiple levels of TSA
input/approvals. These items interrupted the development of shop drawings and the manufacturing
of the temporary and permanent systems as well as slowed construction work progress. Costs
associated with these changes are covered by existing Allowances within the Contract.
CHANGE TO CONTRACT PRICE
DESCRIPTION AMOUNT
Original Contract Price: $ 3,670,500.00
Net change by previously authorized Change Orders: $0.00
Present Contract Price: $ 3,670,500.00
This Change Order will (add/deduct): $0.00
New Contract Price: $ 3,670,500.00
CHANGE TO CONTRACT TIME
DESCRIPTION DATE or NUMBER OF DAYS
Original Contract Date: October 1, 2015
Original Substantial Completion Date: June 26, 2016
Net change by previously authorized Change Orders: None
This Change Order will (add/deduct): 77 days
Unchanged
New Contract Date:
New Substantial Completion Date: September 11, 2016
APPROVALS (SEE ATTACHED SHEET(S) FOR ADDITIONAL CHANGE ORDER APPROVAL SIGNATURES)
DATE: _ 7- /3/l
o pae_ 7/15/e
/ e ’/Lwedo%,\du) DATE: 7/2'///9
OWNER: DATE:
Grades W Laindes, 3¢, Oncrmarn
This Change Order is an amendment to the Contract / Agreement between Contractor and the
Owner, and all other contract provisions shall remain in full force and effect unless specifically
amended in writing, sighed by both parties.
REQUESTED BY:
PROJECT ENGINEER:
CONTRACTOR:
RECAPITULATION
Job: Airport Baggage Handling System ESTIMATE NO.: 1
Location: VPS Airport SHEET NO.:| 1.00
For: CBRA Area Layout Changes
Engineer: Michael Baker International DATE:|4/4/2016 (Revised 6/9/1
Prepared by: Lord & Son Construction, Inc. CHECKED BY:| RC
RFP # CP-04 CBRA PGDS 5.0 Revisions
DESCRIPTION QUANTITY ~UNIT SUB-CONTRACTS UNIT TOTALESTIMATED UNIT TOTAL ESTIMATED
B PRICE MATERIAL COST PRICE LABOR COST
#
1|tectum panels and furing 1940 sf 13,192
2|Electrical Revisions @ Baggage Inspection Tables 1 Is 800
3|Electrical Revisions @ Computer Network Rack 1 Is 1,680
4|Delete Epoxy Floor 1 Is -19,800
5{Add Dur A Flex Paint Floor 1 Is 16,500
6|walkway mats (630 sf) 1 Is 8,663
7|Exhaust Duct @ CMU wall (2 locations) 1 Is 3,500
Credit Reduced Data Cabling to Network Rack - (Wash
8|with Data to AOC) i Is 0
9|Data Revisions @ BHS Inspection Tables 1 Is -400
10|Credit BSDS (4 deleted) 1 Is -1,250
11|Credit BSDS Data Drops (4 deleted) 1 Is -800
12|Credit Floor Finishes @ Plumbing Line 1 Is -1,338
Additional Sawcut/Concrete Work @ Plumbing Line (70
13[If) (Deleted - can use existing drains) 1 Is 0
14|Added Bollards (31 ea) 1 Is 8,250
15|Delete Jersey Barriers (200 If) 1 Is -5,880
16 |Install Roller Bed Equipment @ Lobby 1 Is 5,528
Revised Power to Lobby vs "As Bid" (Add 480V
17 |Power/Deduct Data) 1 Is 3,860
18|Relocate Power for Temp MCP to Normal Power Panel 1 Is 750
19|Lobby Door Remove/Replace for EDS Machines 1 Is 6,999
20|CBRA HVAC Unit 1 Is 26,176
21|CBRA HVAC Unit Electrical 1 Is 4,323
CBRA HVAC Unit Controls & BAC NET - Owner Decided
22|to use built in controls/Tstat ($11,550) 1 Is 0
Drain Line Work Deletion - Use Existing Drains (sawcut,
concretework, sheetrock, ceiling tile work, plumbing &
23|balance of associated floor finishes) 1 Is -8,041
Replace Existing Conveyor TC02-04 - Damaged beyond
24 |repair due to missalignment of belt 1 Is 9,711
72,423 0 0
| Tax: 6% 0
Labor Burden: 40% 0
Total Subcontracts: 72,423
Total Materials: 0
Total Labor: 0
Sub Total: 72,423
Overhead (0%): 0
Sub Total: 72,423
Fee (0%): 0
Sub Total: 72,423
Total: 72,423
Page 1
Sewe, Transportation
{:’U&% ; !
',_% i il ecuril tY
\%gf,@ Administration
4
e"&;j
28D 2
OSC DEPLOYMENT
Change Request Approval Form (CRAF)
COTR John L. Reed OTA Number HSTS04-13-H-CT1161
Date 07/21/2016 Airport Code -CRAF # | VPS-1
PR Number |N/A Cost/Price: $0.00
Change Request Summary
Is this change an allowable cost? X | YES NO
Is this change within the scope of the project? X | YES NO
Is the additional cost within the ceiling of the OTA? X | YES NO
Has the Site Lead Reviewed and Concurred with this Change Form X | YES NO
Attachments/supporting 1. | Contract No. C15-2310-AP 3.
Documentation
2. 4.
Proposed Change Increase the amount of time needed on the airport’s prime construction
contract to complete the Recapitalization Project due to PGDS version 5.0
revisions, temporary lobby baggage screening EDS configurations
modifications and other construction anomalies. This change does not
impact the OTA period of performance.
Impact of change to
quality, quantity, or
delivery of project:
Change is necessary to meet aggressive project schedule milestones to
successfully compete the Recapitalization Project.
Consequence if change is
not made:
Recapitalization In-line CBIS Project will not be compliant with OTA
agreement established Planning Guide Lines & Design Standards (PGDS)
Available alternatives?
None
Approval:
Based on the above [ hereby approve of this proposed Change Form.
Name: John L. Reed
Digitally signed by JOHN L
E-Signature: JOHN L REED Eey016.0721 102
Date: July 21,2016