READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — April 7, 2015 — TaskOrder06 HDR — reading text
Part 2 of 2. These parts divide the reading text for browsing; they are not the source document's page numbers.
TaskOrder06 HDR — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Stored Materials/Equipment Review (as required)
= Coordinate with Contractor to facilitate review of major items prior to
unloading and storage.
* Regularly review Contractor's storage areas to determine compliance
with the Contract Documents.
» Notify the Contractor of any damaged or improperly stored materials.
= Adjust payments properly for damaged or improperly stored
equipment.
1340 - Design Discipline Site Visitations
= Coordinate design discipline site and other visitations.
« Follow-up of any site deficiencies noted by design team members
= Inthe event of visitation by regulatory officials, follow up with
telephone contact to get their impressions and comments.
= For special visitations, arrange that proper persons representing the
various interested parties are present.
1345 - Project Photo and Video Documentation (as required)
* Develop and maintain a logging system to enable easy retrieval of
visual information.
* Video or photo document construction activites as deemed
appropriate.
1350 - Record Drawing Review
* Review monthly status of as-recorded drawings. Refer to Additional
Work Authorization and Request for Proposal Logs to identify areas
of construction revision.
= Notify Contractor in a timely fashion of noted deficiencies.
= Provide follow-up to verify Contractor brings as-recorded drawing
status up-to-date.
= Continually note items as they are noticed during regular field
observation duties for inclusion on monthly as-recorded updates,
= Report general status at Project meetings
1355 - Develop a Progressive List of tems Requiring Correction
= Manitor construction throughout the Project duration and identify
deficient items.
* Provide Contractor with an updated list at construction meetings.
= As deficiencies are corrected, revise the list by deleting corrected
items.
= Distribute the deficiencies list updates to authorized parties.
« Utilize list to aid in identifying retainage amounts near Project
completion.
1360 - OWNER Notification of Accident Damagefinjury
= Maintain communications with Contractor's superintendent
encourage prompt notification of accidents.
= Require lost-time accident reports at construction meetings.
to
= Upon cbservation or notification of an accident, take photographs
and/or videotape of accident scene, make written notes and notify
OWNER.
TASK SERIES 1400 - CONTRACT INTERPRETATIONS AND MODIFICATIONS
Objective:
CONSULTANT
Activities:
ADMINISTRATION
Provide timely reviews and responses to Contractor requests for
interpretations or information and proposed modifications identified by
the Contractors, OWNER or CONSULTANT design and construction
engineering and inspection team.
1405 - Coordinate Interpretations Review
= Receive, log and distribute Requests for information (RFI) to
appropriate design team members for response.
» Review and respond to RFI's.
* Receive design team responses, log and distribute to Contractor.
« Prepare and issue response letters, Change Orders (CO's) or
Change Proposal Requests (CPR's) as required.
1410 - Administration of Changed Worlk
* Evaluate Project on a continual basis to determine when changes
are required.
= Initiate necessary changes in the form of Requests for Proposals
(RFP's).
= Review costs presented on RFP's by Contractor.
= Review all RFP items and negotiated costs with OWNER for
OWNER's approval.
= Assemble approved RFP's periodically into Change Orders (CO's).
include justification documents with each CO.
* Track RFP's and CQO's through Contractor's acceptance, OWNER's
acceptance, Engineer's signature and OWNER executive action
= Maintain current status log of all RFP's and CO's.
* For minor changes involving no cost and no time changes, issue
FO's.
* Review as-recorded drawings to verify changes in work are reflected
as applicable.
* Review pay requests to verify CO items are broken out and that
payment is not made until work is complete.
1415 - Coordinate and Issue Interim Field Change Agreement (IFCA)
* Prepare technical description of the IFCA,
* Route IFCA through established clearinghouse for numbering,
logging and issuance to the Contractor.
= Obtain a copy, executed by the Contractor, and route copies to the
appropriate Project files.
1420 - Coordinate and issue Change Proposal Requests (RFP's)
* Collect technical information and evaluate proposed change.
Prepare technical description of the RFP using necessary graphic
details and specifications.
= Prepare Engineer's Opinion of Cost and evaluation of impact on
Contract Time.
* Route the RFP through established clearinghouse for numbering,
logging and issuance to the Contractor for pricing.
* Route copies to the appropriate Project files.
* Follow and report the status of RFP’s using logs that track the dates
of:
Return from the Contractor with pricing;
Engineer's review and recommendation of pricing; and,
OWNER's acceptance.
= Assist OWNER with negotiations of cost and time.
1425 - Work Change Directives (WCD's)
= Evaluate field activities to determine need for issuance of Work
Change Directive when necessary to expedite extra work on a time
and materials basis.
= Observe time and material work and reconcile costs with Contractor
on a daily basis.
= Finalize WCD's in an appropriate Change Order when associated
work is complete,
1430 - Change Orders {CO's)
= Identify with the OWNER's designated representative the combining
of CPR's strategy and the timing of Change Orders.
= Update CPR and Change Order Logs and provide status reports
tracking the execution of Change Orders.
» Monitor Contractor progress payment applications to allow payment
only for executed Change Orders.
TASK SERIES 1500 - MEASUREMENT AND PAYMENT ADMINISTRATION
Objective:
CONSULTANT
Activities:
Obtain a reasonably balanced distribution of costs to the various
elements of the total construction in the Contractor's Schedule of Values
(cost breakdown) to serve as a basis for progress payments and
determination of cost impact ofchanges.
1505 - Review and Process Progress Payments
= Review draft application for payment in comparison to measuredor
estimated quantities. Make notations of:
Deficient work not recommended for payment until corrected:;
Deletion of payment for stored materials andfor equipment which
do not have approved Shop Drawings and/or proper invoices;
and
Reduction of value for partially completed items claimed as
complete.
Return a copy of the reviewed draft to the Contractor.
= Conduct review of storage areas and verify existence of invoiced
materials/fequipment and proper storage.
» Meet with Contractor to reconcile discrepancies.
= Review revised application for payment and, if appropriate, advise
Contractor to submit the required number of copies.
= Execute completed application for payment indicating amount
recommended for payment and transmit to OWNER for processing
of payment.
« Distribute executed copies as established in preconstruction
conference minutes.
+ Monitor total payments to adjust retainage amounts as specifiedin
the Contract Documents,
* As Project nears completion, and at OWNER's direction, adjust
retainage from fixed percent to only enough retainage to providefor
work completion.
TASK SERIES 1600 - PROJECT CLOSEOUT
Objective:
CONSULTANT
Activities:
Conduct an orderly and properly decumented Projectcloseout.
1605 - Review Substantial Completion Submittal
* Receive and review Contractor's required substantial completion
submittal and determine if Project is ready for substantialcompletion
inspection.
= Develop substantial completion submittal checklist.
= Verify submittal of all required documents.
* Review Contractor Record Drawings.
= Perform review of Record Drawing revisions.
* Review other substantial completion submittal documentsfor
completeness and compliance with Contract provisions.
= Schedule substantial completion inspection.
1610 - Conduct Substantial Completioninspection
= Notify design team members of date or substantial completion
inspection.
Notify OWNER's designated representative of the date ofthe
substantial completion inspection.
Prepare and distribute the punch list format to the parties conducting
the inspection.
Compile the punch list, review with OWNER and transmit to the
Contractor.
Review progress of corrective action on punch list items and
periodically update and re-issue.
1615 - Issue Certificate of Substantial Completion and Punch List
Review the findings of the substantial completion inspection with
OWNER and jointly determine the status of the Work.
Address comments from either OWNER or the Contractor regarding
the tentative date of substantial completion or the punch list.
1625 - Document Project Warranties
Provide notification of the start of the warranty period to define for all
parties the ending date of the period for which the Contractor is
responsible for repairing deficient Project materials and equipment,
1630 - Review Final Completion Submittal
Receive and review the Contractor's required final completion
submittal,
Develop final completion submittal checklist.
Verify submittal of all required documents.
Review for completeness and compliance with Contract provisions.
Notify OWNER and Contractor of date of final inspection,
Determine if OWNER requires (or is required by State Statute) Lien
Waivers and Consent of Surety.
1635 - Conduct Final Completion Inspection
Schedule the final inspection date and notify the Contractor and
OWNER,
Assemble the various final completion submittal documents for the
final inspection meeting and review them with the various parties.
Conduct the final inspection.
1640 - Recommend Final Payment
Finalize all Project costs and determine the final adjusted amounts
for construction as well as reimbursements for engineering services
owed to OWNER by the Contractor.
Obtain Contractor's signature on any required Contractor's
Certification or Affidavits.
Process and sign Final Application for Payment.
Prepare transmittal letter indicating recommendation for Final
FPayment and stating whether or not Engineer is aware of any
outstanding issues that preclude issuance of Final Payment.
