The BOCC will begin using the overall goal on October 1 of the specified year, unless the BOCC has
received other instructions from DOT. If we establish a goal on a project basis, the BOCC will begin using
the goal by the time of the first solicitation for a DOT-assisted contract for the project. The BOCC’s goal will
remain effective for the duration of the three-year period established and approved by FTA.
Section 26.47 Goal Setting and Accountability
If the awards and commitments shown on the BOCC’s Uniform Report of Awards or Commitments and
Payments at the end of any fiscal year are less than the overall applicable to that fiscal year, we will:
1. Analyze in detail the reason for the difference between the overall goal and the actual
awards/commitments;
2. Establish specific steps and milestones to correct the problems identified in the analysis; and
3. Submit the plan to FTA within 90 days of the end of the affected fiscal year.
Section 26.49 Transit Vehicle Manufacturers Goals
The BOCC will require each transit vehicle manufacturer, as a condition of being authorized to bid or
propose on FTA-assisted transit vehicle procurements, to certify that it has complied with the requirements
of this section. Alternatively, The BOCC may, at its discretion and with FTA approval, establish project-
specific goals for DBE participation in the procurement of transit vehicles in lieu of the TVM complying with
this element of the program.
Section 26.51 Meeting Overall Goals/Contract Goals
The BOCC will meet the maximum feasible portion of its overall goal using race-neutral means of
facilitating DBE participation. DBE participation that is obtained on contracts that have no specific
DBE goal, or where prime contractors use a strictly competitive bidding process or do not
consider the DBE’s status as a DBE in awarding a subcontract shall be considered race-neutral
DBE participation. In addition, the BOCC will use the following measures as appropriate:
1. Configuring large contracts into smaller contracts when feasible, when to do so would
make contracts more accessible to small businesses, and would not impose significant
additional cost, delay or risk to the BOCC;
2. Identifying components of the work that have subcontracting opportunities and identifying
the availability of DBE subcontractors to participate in an equitable proportion to total
available subcontractors when it is infeasible to configure large contracts into smaller
separate contracts.
3. Assisting in overcoming limitations in bonding and financing by such means as
simplifying the bonding process, reducing bonding requirements, eliminating the impact
of surety costs from bids, and providing services to help DBEs, and other small
businesses, obtain bonding and financing;
4. Providing technical assistance and other services in orienting small businesses to public
contract procedures, and facilitating introductions to BOCC’s and other FTA recipients’
contracting activities;
5. Providing outreach and communications programs on contract procedures and specific
contract opportunities to ensure the inclusion of DBEs and other small businesses, on
BOCC mailing lists for bidders; ensuring the dissemination to potential prime bidders of lists
of potential DBE and small business subcontractors; and provision of information in
languages other than English, where appropriate;
6. Ensuring notification of the availability of the Florida UCP DBE Database to the widest
feasible universe of potential prime contractors; and
7. Providing business development assistance to help DBEs, and other small businesses,
improve long-term development, increase opportunities to participate in a variety of kinds
of work, handle increasingly significant projects, and achieve eventual self-sufficiency;
8. Arranging solicitations, times for the presentation of bids, quantities, specifications, and
delivery schedules in ways that facilitate DBE, and other small businesses, participation.
Prime Contractors will be encouraged to consider subcontractors for components of the
work that they might otherwise perform with their own forces, including DBEs,
subcontractors, in preparing their bids.
9. Ensuring notification of the availability of the Florida UCP DBE directory, to potential
prime contractors bidding BOCC projects:
10. Assisting DBEs, and other small businesses, to develop their capability to utilize
emerging technology and conduct business through electronic media
The BOCC will use contract goals to meet any portion of the overall goal BOCC does not project being able
to meet using race-neutral means. Contract goals are established so that, over the period to which the
overall goal applies, they will cumulatively result in meeting any portion of BOCC’s overall goal that is not
projected to be met through the use of race-neutral means. BOCC will establish contract goals only on
those DOT-assisted contracts that have subcontracting possibilities. BOCC need not establish a contract
goal on every such contract, and the size of contract goals will be reasonable and adapted to the
circumstances of each such contract (e.g., type and location of work, availability of DBEs to perform the
particular type of work.) BOCC will express a contract goal as a percentage of the total amount of a DOT-
assisted contract. BOCC is located within the jurisdiction of the U.S. Court of Appeals for the Ninth Circuit
and BOCC is subject to Western States Paving, Inc. v. Washington State Department of Transportation,
407 F.3d 983. BOCC will verify with DOT whether BOCC may use DBE contract goals and/or raceconscious
measures when implementing BOCC’s DBE program. Absent such approval from DOT,
BOCC will operate an entirely race-neutral DBE programs.
Section 26.53 Good Faith Efforts Procedures
Award of Contracts with a DBE Contract Goal: 26.53(a)
In those instances where a contract-specific DBE goal is included in a procurement/solicitation, BOCC will
not award the contract to a bidder who does not either: (1) meet the contract goal with verified, countable
DBE participation; or (2) documents it has made adequate good faith efforts to meet the DBE contract goal,
even though it was unable to do so. It is the obligation of the bidder to demonstrate it has made sufficient
good faith efforts prior to submission of its bid.
Information to be Submitted: 26.53(b)
Each solicitation for which a contract goal has been established will require the bidders/offerors to
submit the following information:
1. The names and addresses of DBE firms that will participate in the contract;
2. A description of the work that each DBE will perform;
3. The dollar amount of the participation of each DBE firm participating;
4. Written and signed documentation of commitment to use a DBE subcontractor whose
participation it submits to meet a contract goal;
5. Written and signed confirmation from the DBE that it is participating in the contract as
provided in the prime contractors commitment and
6. If the contract goal is not met, evidence of good faith efforts will be required to be
submitted to BOCC within three business days of the due date of the bid or offer..
Evaluation of Good Faith Efforts: 26.53(a) & (c)
BOCC treats bidder/offers’ compliance with good faith efforts' requirements as a matter of responsiveness.
The BOCC DBELO, in collaboration with BOCC staff, is responsible for determining whether a bidder/offeror
who has not met the cont race goal has documented sufficient good faith efforts to be regarded as
responsive. BOCC’s evaluation of good faith efforts will be conducted in accordance with “Appendix A to
Part 26 - Guidance Concerning Good Faith Efforts” The processes used by BOCC to determine whether
good faith efforts have been made by a bidder are as follows:
If bidder or proposer does not meet the established DBE goal, and is required to submit documentation of
good faith effort, then a good faith efforts submission shall be provided within three business days from the
bid/proposal submittal date, which shall include a signed DBE Good Faith Efforts Checklist (form provided
by BOCC) and supporting documentation that the bidder/proposer made a good faith effort to meet the
goal. BOCC may allow a longer period based on submittal of a request demonstrating good cause for such
extension. Good faith efforts at a minimum include, without limitation, the following where applicable:
a. Attendance at the pre-bid meeting.
b. Advertisement in trade association newsletters and minority-focused media
within a reasonable time before bids are due for specific sub-bids that would be at least equal
to the percentage goal for DBE utilization specified for the project.
c. Notification in writing to minority contractor associations within a reasonable time
before bids are due of a solicitation for specific sub-bids.
d. Direct negotiation with DBEs for specific sub-bids.
e. A report with:
1. A detailed statement of the efforts made to negotiate with DBEs including
at a minimum (a) the names, addresses, and telephone numbers of
DBEs who were contacted; (b) a description of the information provided
to DBEs regarding the plans and specifications for portions of the work to
be performed; and (c) a detailed statement of the reasons why additional
prospective agreements with DBEs, if needed to meet the stated goal,
were not reached.
2. A detailed statement of the efforts made to select portions of the work
proposed to be performed by DBEs in order to increase the likelihood of
achieving the stated goal.
3. As to each DBE contacted which the bidder considers unqualified, a
detailed statement of the reasons for the bidder's conclusion.
4. As to each DBE contacted which the bidder considers to be unavailable,
an Unavailability Certificate signed by a DBE, or a statement from the
bidder that the DBE refused to give such written certification after
reasonable request, and a detailed statement from the bidder of the
reasons for the bidder's conclusion.
5. The name(s) of the certified DBEs whose bid(s) were rejected, the
description of the work, price quote(s), and an explanation why they were
rejected. Also provide the name(s), description of the work, and price
quote(s) of the non-DBE subcontractors whose bids were accepted.
BOCC will ensure that all information is complete and accurate and adequately
documents the bidder/offer’s good faith, efforts before BOCC commits to the
performance of the contract by the bidder/offeror.
Administrative Reconsideration: 26.53(d)
The BOCC's Bid Protest procedures will be available as administrative reconsideration to bidders/proposers
who are determined by the DBE Liaison Officer to be nonresponsive to the Good Faith Efforts requirements
of the Invitation for Bid or Request for Proposal. Within ten (10) days of being informed by BOCC that it is
not responsive because it has not documented sufficient good