READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 8 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
If said Bid shall be rejected, or in the alternate,
(b) __ If said Bid shall be accepted and the Principal shall execute and deliver a contract in the
Form of Contract attached hereto (properly completed in accordance with said Bid) and
shall furnish a bond for his faithful performance of said contract, and for the payment of
all persons performing labor or furnishing materials in connection therewith, and shall in
all other respects perform the agreement created by the acceptance of said Bid, then this
obligation shall be void, otherwise the same shall remain in force and effect; it being
expressly understood and agreed that the liability of the Surety for any and all claims
hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.
The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and
its bond shall be in no way impaired or affected by an extension of the time within which the Owner may
accept such Bid; and said Surety does hereby waive notice of any such extension.
Repair & Paint
Countryview & Bluewater Tanks (2014) 004.10-1 Job No. 41-459
| IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals,
and such of them as are corporations have caused their corporate seals to be hereto affixed and these
J presents to be signed by the proper officer, the day and year first set forth above.
LS.
i Principal
Surety
BY:
SEAL:
i Repair & Paint
Countryview & Bluewater Tanks (2014) 00410-2 Job No. 41-459
SECTION 00500
EJCDC
STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
ON THE BASIS OF A STIPULATED PRICE
THIS AGREEMENT is by and between Board of County Commissioners, Okaloosa County, FL
(hereinafter called OWNER) and (hereinafter called
CONTRACTOR). OWNER and CONTRACTOR, in consideration of the mutual covenants
hereinafter set forth, agree as follows:
ARTICLE 1. WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
The Work is generally described as follows:
Repair and Paint Countryview and Bluewater Tanks (2014)
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a
part is generally described as follows:
Repair and Paint Countryview and Bluewater Tanks (2014)
ARTICLE 3 - ENGINEER
3.01 The Project has been designed by POLYENGINEERING, INC. who is hereinafter called
ENGINEER and whois to act as OWNER's representative, assume all duties and responsibilities and
have the rights and authority assigned to ENGINEER in the Contract Documents in connection with
completion of the Work in accordance with the Contract Documents.
ARTICLE 4- CONTRACT TIME
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and
readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Days to Achieve Substantial Completion and Final Payment
A. The Work will be substantially completed within 120 calendar days from the date
when the Contract Time commences to run as provided in paragraph 2.03 of the General
Repair & Paint
Countryview & Bluewater Tanks (2014) 00500-1 Job No. 41-459
Conditions, and completed and ready for final payment in accordance with paragraph 14.07.B of
the General Conditions within 180 calendar days from the date when the Contract Time
commences to run.
4.03 Liquidated Damages.
A. Amount: In case of failure on the part of the Contractor to complete the work within the
time(s) specified in paragraph 4.02 above, or within such additional time(s) as may be
granted by Okaloosa County in accordance with Article 12 of the General Conditions, the
County will suffer damage, the amount of which is difficult, if not impossible, to ascertain.
Therefore, the Contractor shall pay to the County, as liquidated damages, the amount
established in the schedule below for each calendar day of delay that actual completion
extends beyond the time limit specified until such reasonable time as may be required for
final completion of the work. In no way shall costs for liquidated damages be construed as
penalty on the contractor.
Original Contract Amount Daily Charge Per Calendar Day
$50,000 and under $311
Over $50,000 but less than $250,000 $972
$250,000 but less than $500,000 $1,584
$500,000 but less than $2,500,000 $1,924
$2,500,000 but less than $5,000,000 $2,694
$5,000,000 but less than $10,000,000 $3,902
$10,000,000 but less than $15,000,000 $6,102
$15,000,000 but less than $20,000,000 $7,022
$20,000,000 and over $7,022
plus 0.2% for any amount over $20 million
B. Determination of Number of Days of Default: For all contracts, regardless of whether the
contract time is stipulated in calendar days or working days, the default days shall be counted
in calendar days.
C. Conditions under which Liquidated Damages are imposed: Should the Contractor or, in
case of his default, the Surety, fail to complete the work within the time stipulated in
paragraph 4.02 above, or within such extra time as may have been granted by the County in
accordance with Article 12 of the General Conditions, the Contractor or, in case of his
default, the Surety, shall pay to the County, not as a penalty, but as liquidated damages, the
amount so due as determined by the Code requirements, as provided above.
D. Right of Collection: The County shall have the right to apply as payment on such liquidated
damages any money which is due to the Contractor by the County.
Repair & Paint
Countryview & Bluewater Tanks (2014) 00500-2 Job No. 41-459
E. Permitting Contractor to Finish Work: Permitting the Contractor to continue and to finish
the work, or any part of it, after the expiration of the contract time allowed, including
extensions of time granted to the Contractor, shall in no way act as a waiver on the part of
the County the liquidated damages due under the contract.
F, Completion of Work by County: In case of default of the contract and the completion of
the work by the County, the Contractor and his Surety shall be liable for the liquidated
damages under the contract, but no liquidated damages shall be chargeable for any delay in
the final completion of the work by the County due to any unreasonable action or delay on
the part of the County.
ARTICLE 5 - CONTRACT PRICE
5.01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the
Contract Documents an amount in current funds equal to the sum of the amounts determined
pursuant to paragraphs 5.01.A below:
A. For all Work, at the prices stated in CONTRACTOR’s Bid, attached hereto in Section 00300.
As provided in paragraph 11.03 of the General Conditions, estimated quantities are not
guaranteed, and determinations of actual quantities and classifications are to be made by
ENGINEER as provided in paragraph 9.08 of the General Conditions. Unit prices have been
computed as provided in paragraph 11.03 of the General Conditions.
Contract Amount of
ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14
of the General Conditions. Applications for Payment will be processed by ENGINEER as provided
in the General Conditions.
6.02 Progress Payments; Retainage
A. OWNER shall make progress payments on account of the Contract Price on the basis of
CONTRACTOR's Applications for Payment on or about the 10th day of each month during
performance of the work as provided in Paragraphs 6.02.A.1 and 6.02.A.2 below. All such
payments will be measured by the schedule of values established in paragraph 2.07.A of the General
Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the
event there is no schedule of values, as provided in the General Requirements.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to
the percentage indicated below, but, in each case, less the aggregate of payments previously made
Repair & Paint
Countryview & Bluewater Tanks (2014) 00500-3 Job No*41-459
and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance
with paragraph 14.02 of the General Conditions.
a. Ninety percent (90%) of Work completed (with the balance being retainage).
If Work has been fifty percent (50%) completed as determined by ENGINEER, and
if the character and progress of the Work have been satisfactory to OWNER and
ENGINEER, OWNER on recommendation of ENGINEER, may determine that as
long as the character and progress of the Work remain satisfactory to them, there will
be no retainage on account of Work subsequently completed, in which case the
remaining progress payments prior to Substantial Completion will be in an amount
equal to 100% of the Work completed less the aggregate of payments previously
made; and
b. Ninety percent (90%) of cost of materials and equipment not incorporated in
the Work (with the balance being retainage).
2. Upon Substantial Completion, OWNER shall pay an amount sufficient to increase total
payments to CONTRACTOR to ninety-five percent (95%) of the Work completed, less such
amounts as ENGINEER shall determine in accordance with paragraph 14.02.B.5 of the General
Conditions and less 100% of ENGINEER’s estimate of the value of Work to be completed or
corrected as shown on the tentative list of items to be completed or corrected attached to the
certificate of Substantial Completion.
6.03 Final Payment.
A. Upon final completion and acceptance of the Work in accordance with paragraph 14.07
of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended
by ENGINEER as provided in said paragraph 14.07.
ARTICLE 7 - INTEREST
7.01 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear
interest at the rate of 12% per annum.
ARTICLE 8 - CONTRACTOR'S REPRESENTATIONS
8.01 Inorder to induce OWNER to enter into this Agreement CONTRACTOR makes the following
representations:
A. CONTRACTOR has examined and carefully studied the Contract Documents and the
other related data identified in the Bidding Documents.
B. CONTRACTOR has visited the site and become familiar with and is satisfied as to the
general, local and site conditions that may affect cost, progress, performance of the Work.
C. CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws
and Regulations that may affect cost, progress, performance of the Work.
Repair & Paint ;
Countryview & Bluewater Tanks (2014) 00500-4 Job No. 41-459
D. CONTRACTOR has carefully studied all: (1) reports of explorations and tests of
subsurface conditions at or contiguous to the site and all drawings of physical conditions in or
relating to existing surface or subsurface structures at or contiguous to the site (except Underground
Facilities) which have been identified in the Supplementary Conditions as provided in paragraph
4.02 of the General Conditions and (2) reports and drawings of a Hazardous Environmental
Condition, if any, at the site which has been identified in the Supplementary Conditions as provided
in paragraph 4.06 of the General Conditions.
E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for
having done so) all additional or supplementary examinations, investigations, explorations, tests,
studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or
contiguous to the Site which may affect cost, progress, or performance of the Work or which relate
to any aspect of the means, methods, techniques, sequences, and procedures of construction to be
employed by CONTRACTOR, including applying the specific means, methods, techniques,
sequences, and procedures of construction, if any, expressly required by the Contract Documents to
be employed by CONTRACTOR, and safety precautions and programs incident