Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 33 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
pipe, tack weld
a plate over the inlet/outlet pipe or place an expandable plug in the pipe.
Repair & Paint 009870 - 21
Countryview & Bluewater Tanks (2014) Job No. 41-459
c. Ifa plate is tack welded over the pipe, the plate shall completely cover the
pipe and shall not be removed until the interior and exterior painting is
complete. After the plate is removed the damaged areas of coating and weld
burrs shall be ground smooth and recoated in accordance with the applicable
paragraphs in these specifications.
d. Ifan expandable plug is inserted in the pipe, the plug shall be placed
approximately 18" down in the pipe to allow for proper coating of the
inlet/outlet pipe.
11. Air Dryer for Compressor
a. Use air dryers sufficient to remove 98% of the moisture from the compressed
air. Size the dryers based on total cfm using manufacturer supplied charts.
Upon request, supply charts to engineer for verification.
b. _ If the fan is not operable, cease all blasting until the dryer is replaced or
repaired.
c. Supply air dryer with an air draw-off valve to check air for dryness, oil
contamination and cleanliness on the outlet side of the air dryer.
d. For cleaning operations, draw clean air from the outlet side of the air dryer.
C. Preparation and Painting the Tank Wet Interior
1. Surfaces to be Cleaned and Painted:
All interior wet surfaces including the roof, manholes, roof vent flange access tube,
etc., shall be cleaned and painted in accordance with the requirements of this
section.
2. Cleaning Tank and Debris Removal
a. The OWNER will remove all water from the tank which will drain by gravity
through the drain line.
b. The CONTRACTOR shall remove all standing water, mud, and debris from
the tank prior to starting work
3. Surface Preparation
a. The interior surfaces mentioned above in Paragraph 3.05.B.1. shall be cleaned
to a degree of cleanliness equivalent to SSPC-SP10, Near-White Blast
Cleaning by a method approved by the ENGINEER and OWNER.
b. Before the formation of rust and after observation of the surface by the
ENGINEER, all cleaned surfaces shall be primed as specified. Prior to the
application of the finish coat, all seams, rough areas, deviations from smooth
surfaces, pits, bolt heads and nuts, remains of erection lugs and scars, and
comers shall be primed by brush (stripe coat at 2.0 - 4.0 mils) with the primer,
Repair & Paint 009870 - 22
Countryview & Bluewater Tanks (2014) Job No. 41-459
followed by the finish coat.
A sample area of minimum size 2’x 2’ will be cleaned to a degree of
cleanliness equivalent to SSPC-SP10, Near White Blast Cleaning as agreed by
the ENGINEER and CONTRACTOR. After agreement as to degree of
cleanliness, the sample area shall be clear coated and used as a template for
the remainder of the cleaning for this portion of the tank.
4. Seam Sealer
After cleaning, seam sealer is to be applied to the roof vent intersection, roof
manhole, tank manhole intersection, piping intersections, and the lap seams to
seal these intersections from moisture. It shall be applied in a workmanlike
manner, being beveled at approximately 45 degrees.
The cost of this seam sealing is to be included in the Base Bid.
At the CONTRACTOR'S option Filler (see section 2.05, above) and Surfacer
may be applied after the priming of the surface, providing no rust has formed
on any un-coated surfaces (such as crevices between plates).
5. Coating Application
a.
The approved coatings for the interior surfaces are intended to comply with
the requirements of AWWA D102-11 Inside Coating System No. 3 (ICS-3,
Modified) with the dry film thickness as specified in the coating schedule.
Acceptable manufacturers and products are shown in the coating schedule.
The CONTRACTOR must submit certifications indicating compliance with
the specifications.
Not later than eight hours and before the formation of rust, the cleaned
surfaces (SSPC-SP10) shall be primed with the specified primer applied at a
rate to achieve a 2.5 - 3.5 mils (min.) dry film thickness.
The primer coat shall be inspected and approved by the ENGINEER prior to
proceeding with the remaining coats.
After approval of the prime coat a finish coat shall be applied at a rate to
achieve 30.0 - 40.0 mils DFT. Roof beams, sharp edges and other difficult to
coat areas shall receive 40.0 — 50.0 mils DFT..
The total dry film thickness for the two (2) coat system shall be a minimum of
32.5 mils. All roof beams, sharp edges and other difficult to coat areas shall
have a minimum of 42.5 mils DFT.
Paint shall be applied strictly in accordance with the manufacturer's
recommendations.
6. Re-coat Cycle
a. The CONTRACTOR shall review the manufacturer's published product data
for maximum re-coat times for the interior coating system selected for use.
b. Ifthe maximum re-coat window is exceeded prior to application of the
Repair & Paint 009870 - 23
Countryview & Bluewater Tanks (2014) Job No. 41-459
succeeding coat, then the CONTRACTOR shall prepare the interior surfaces
in accordance with the manufacturer's published product data prior to the
application of the next coat.
The cost of this additional surface preparation shall be borne by the
CONTRACTOR with no additional cost to the OWNER.
The Contract Time shall not be increased as a result of this additional surface
preparation.
Curing
Each coat shall be properly cured before the application of any subsequent
coats.
The interior wet area coating shall be completely cured and the tank shall not
be filled with water until approved by the ENGINEER and OWNER.
The exterior dry coating on the opposite side of water bearing surfaces shall be
completely cured and the tank shall not be filled with water until approved by
the ENGINEER and OWNER.
Solvent rub tests, pencil hardness tests, or other industry recognized testing
procedures shall be used as recommended by the manufacturer.
The CONTRACTOR shall monitor the torus bottom plate temperature during
the interior coating curing to verify that minimum steel temperature
requirements are satisfied.
Ventilation
Forced ventilation shall be supplied to the interior of the tank for a continuous
period of at least 48 hours after the final coat has been applied.
Adequate ventilation of the tank bottom and other low lying areas of the tank
shall be provided by the CONTRACTOR as required for solvent release and
coating cure. This ventilation shall, at a minimum, be in accordance with
AWWA D102-06.
The CONTRACTOR shall furnish, install and operate the equipment that is
necessary to provide forced ventilation to aid curing.
If supplementary heating or dehumidification is required to effect curing, the
CONTRACTOR shall furnish, install, and operate the equipment to perform
the supplementary heating or dehumidification required at no additional cost.
9. Testing
Repair & Paint
Countryview & Bluewater Tanks (2014)
All interior wet coatings, including those above the high water level, shall be
checked with a wet sponge low voltage holiday detector.
Testing shall be done in accordance with Section B.9.3 of AWWA D102-06 in
the presence of the ENGINEER.
Any voids indicated shall be repaired by applying more of the finish coat of
paint by brush or roller. The repaired areas shall be retested after the
009870 - 24
Job No. 41-459
appropriate drying time.
d. The coating system must pass the holiday test regardless of the mil thickness
applied to the tank.
D. Preparation and Painting the Tank Exterior
1. Surfaces to be Painted
All exterior surfaces of the tank, including the bowl, tower, rods, turnbuckle
threads, bolts, nuts, pins, brackets, seams, corners, base, pedestals/pillars or legs,
manhole neck of the roof vent, etc., shall be cleaned and painted in accordance
with the paragraphs in this section.
2. Irregular Surfaces
a. Any burns, weld splatter, rough welds, weld overlap, bolts, sharp edges, or
comers of any areas disturbed or installed by the CONTRACTOR'S
operations which would cause difficulty in achieving a defect-free coating
shall be chipped and/or ground smooth.
b. Any pinholes or voids in exterior welds shall be filled with an epoxy seam
sealer. It is not the intent to have these irregular surfaces chipped and/or
ground flush. The objective of the chipping, grinding and/or seam sealing is
to eliminate irregular surfaces to provide a surface that is sufficiently smooth
for the application of a uniform thickness coating without voids. This
chipping, grinding and/or seam sealing is considered incidental to the exterior
painting and is to be included in the Base Bid.
3. Cleaning Tank and Debris Removal
a. The surfaces described in paragraph 3.05.D.1 shall be cleaned to a degree of
cleanliness equivalent to SSPC-SP6, Commercial Blast Cleaning by a method
approved by the ENGINEER and OWNER.
b. A sample area of minimum size 2’x 2’ will be cleaned to a degree of
cleanliness equivalent to SSPC-SP 6, Commercial Blast Cleaning as agreed by
the ENGINEER and CONTRACTOR. After agreement as to degree of
cleanliness, the sample area shall be clear coated and used as a template for
the remainder of the cleaning for this portion of the tank.
4. Coating Application
a. The approved coatings for the exterior surfaces are intended to comply with
the requirements of AWWA D102-11 Outside Coating System No. 4 (OCS-4,
Modified). Acceptable manufacturers and products are shown in the coating
schedule. The CONTRACTOR must submit certifications indicating
compliance with the specifications.
Repair & Paint 009870 - 25
Countryview & Bluewater Tanks (2014) Job No. 41-459
Repair & Paint
Countryview & Bluewater Tanks (2014)
Not later than eight hours and before the formation of rust, the cleaned
surfaces (SSPC-SP6) shall be primed with the specified primer.
Should any area exist where the intersection of two (2) members does not
allow the complete cleaning of the intersection and the members cannot be
separated for cleaning (such as anchor bolt washers, clevises, turnbuckles,
etc.), these intersections shall be post-primed with an aluminum platelet
pigmented material suitable for marginally cleaned surfaces. The material
shall be Tnemec 1 Omnithane, or other material approved in writing by the
ENGINEER and recommended by the manufacturer of the exterior paint
system.
Following the prime coat application, the exterior surfaces shall receive two
intermediate coats and a finish coat of paint. The colors for the intermediate
coats shall be slightly darker than that chosen for the finish coat, being dark
enough and different enough from one another to visually assure application
and coverage of each subsequent coat, yet light enough to allow proper hiding
of the intermediate coats of paint.
Recoat Cycle
The CONTRACTOR shall review the manufacturer's published product data
for maximum recoat times for the interior coating system selected for use.
If the maximum recoat window is exceeded prior to application of the
succeeding coat, then the CONTRACTOR shall prepare the interior surfaces
in accordance with the manufacturer's published product data prior to the
application of the next coat.
The cost of this additional surface preparation shall be borne by the
CONTRACTOR with no additional cost to the OWNER.
The Contract Time shall not be increased as a result of this additional surface
preparation.
Curing
Each coat shall be properly cured before the application of any subsequent
coats.
The interior wet area coating shall be completely cured and the tank shall not
be filled with water until approved by the ENGINEER and OWNER.
The exterior dry coating on the opposite side of water bearing surfaces shall be
completely cured and the tank shall not be filled with water until approved by
the ENGINEER and OWNER.
Solvent rub tests, pencil hardness tests, or other industry recognized testing
procedures shall be used as recommended by the manufacturer.
The CONTRACTOR shall monitor the torus bottom plate temperature during
the