Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 32 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
grinding is considered incidental to the welding work and is to be included in
the Base Bid.
After grinding, these areas shall be cleaned to produce the profile recommended by
the manufacturer of the coating system.
Cleaning Areas To Be Welded
a. It shall be necessary to remove the coating prior to the welding of any new
items to the tank.
b. All areas that have been welded and/or ground smooth shall be cleaned prior
to painting to provide proper profile for the coating system.
c. Areas to be welded shall be welded prior to the final cleaning and painting of
surfaces within the heat-affected zone. The heat-affected zone includes the
opposite side of the plate or member being welded. Even if not specifically
009870 - 16
Job No. 41-459
mentioned as a part of the Work under this Agreement, those areas of paint or
coatings in the heat-affected zone of areas not specified to be painted shall be
cleaned and painted in accordance with the requirements listed in these
Detailed Technical Specifications.
C. Pit Filling
1. After an area of steel is abrasive blast cleaned, any pits, rough areas or seams
marked for pit filling or surfacing by the ENGINEER shall be filled with
solventless polyamide epoxy seam sealer of the type recommended by the supplier
of the interior paint system. The epoxy seam sealer shall be applied neatly and
smoothly to the steel surfaces and any rough areas of the seam sealer shall be
sanded smooth prior to the application of the coating system.
2. The CONTRACTOR shall include in his base bid two gallons of pit filler.
D. Seam/Seal Welding
1. All areas of apparent seam deterioration shall be abrasive blast cleaned, and any
seam corrosion or undercut marked by the Engineer shall be repaired by arc-
gouging and welding.
2. The number of linear feet of seam welding shall be paid for by the unit price as
listed in the Bid Proposal.
E. Handrail Addition (in base bid - both tanks)
Fabricate and install a handrail on the exterior of the access tube at the top of both
tanks as depicted in the detailed drawing in the Appendix. Depicted on side of access
tube, but final location (access tube or top of tank) to be determined by OWNER at
time of installation. An additional coat of zinc-rich primer shall be shop-applied to all
replacement parts.
G. Tank Vent (separate bid item - Bluewater Tank only)
Replace tank vent with 24" Pressure Vacuum Vent as manufactured by Newlin’s
Welding and Tank Maintenance (Montezuma, IN - Phone No. (765) 245-2741)
K. Roof Manway (separate bid item - both tanks)
Replace existing 24" roof manway with new 30" roof manway as manufactured by
Newlin’s Welding and Tank Maintenance (Montezuma, IN - Phone No. (765) 245-
Repair & Paint 009870 - 17
Countryview & Bluewater Tanks (2014) Job No. 41-459
2741). Details included in Appendix. An additional coat of zinc-rich primer shall be
shop-applied to all replacement parts.
L. Target (in base bid - both tanks)
Remove and dispose of existing target, brackets and any associated appurtenances and
seal all penetrations by welding, as applicable, before commencing blasting and
painting operations.
M. Existing Transducer and New Conduit (in base bid — both tanks)
Remove existing transducer and cable under supervision of OWNER’s SCADA
personnel. Install new rigid galvanized conduit from existing transducer tap to RTU
panel, routing down through dry riser. Transducer and cable to be re-installed at later
date by others. Details for conduit in Electrical Drawings in Appendix.
N. Countryview Tank Repairs (in base bid)
1. Replace dry riser entrance door hinges and weatherstrip around door to prevent
entrance by insects.
2. Replace screens on vent and dry riser vents.
O. Bluewater Tank Repairs (separate bid item)
Replace screened end of overflow pipe with weighted flapper and screen to meet FDEP
regulations.
P. Bluewater Tank Repairs (in base bid)
1. Repair door frame before blasting and painting
Seal conduit penetrations in dry pillar by welding plates as needed, reducing size
of penetrations to match conduit size.
Remove and grind smooth existing old ladder brackets.
4. Replace vent screens.
ive)
3.6 REPAINTING THE TANKS
A. General
1. All cleaning and painting shall be done in a workmanlike manner. Curing times
and ventilation requirements of the paint manufacturer shall be strictly enforced by
the CONTRACTOR.
Repair & Paint 009870 - 18
Countryview & Bluewater Tanks (2014) Job No. 41-459
The CONTRACTOR shall have sufficient Wet Film Thickness Gauges and a
calibrated Dry Film Thickness Gauge on the premises during all working hours
after any painting begins.
In addition to the minimum and maximum dry film requirements (See Appendix,
Table 1), all sags, runs, pinholes, craters, roller nap, and other irregularities which
would be detrimental to the life or appearance of the coating(s) shall be removed
and repaired at no additional cost to the OWNER.
Finish coats shall be uniform in color, hide and sheen (gloss) without streaks, laps,
runs, drips, sags or missed areas.
B. Painting Environment
1.
Repair & Paint
All temperature and humidity requirements of the paint manufacturer's published
product data shall be followed.
In addition, no painting shall be done when the relative humidity is greater than
80%, or the temperature of the steel is or is expected to be less than 5 degrees F
above the dew point temperature during application and until the coating has cured
to resist moisture in accordance with the manufacturer's published product data.
The CONTRACTOR shall have wet bulb-dry bulb measuring equipment and steel
temperature measuring equipment on the job at all times. Readings shall be
recorded at the beginning and end of each painting session and at no less than two
(2) hour intervals. Wind velocities during exterior painting shall be compatible for
the quality application of the exterior coatings. Measurements shall be recorded on
the Daily Coatings Report.
Minimum Temperature
a. Each component shall be maintained at a minimum of 75 degrees F prior to
mixing.
b. The mixed coatings shall also be maintained at a minimum of 65 degrees F
during application.
c. All costs associated with keeping the coating material at the minimum
specified temperature shall be included in the Base Bid.
Mixing of Coatings
a. Each component shall be thoroughly mixed on-site with a power agitator in
accordance with the manufacturer’s printed instructions to ensure no pigment
remains on the bottom of the container.
b. Anentire kit shall be mixed together to ensure proper ratios of components.
c. The container shall be large enough to hold all components to be mixed,
009870 - 19
Countryview & Bluewater Tanks (2014) Job No. 41-459
including thinner. The combined material shall be thoroughly mixed with a power
agitator that shall be driven by a 3/4" drill motor not exceeding 300 rpm and which
do not cause air entrainment to achieve a uniform consistency.
Adherence to proper induction times and re-coat schedule for the combined
coating material shall be in accordance with the manufacturer's published product
data. No coating shall be applied until the minimum induction time has been
reached.
6. Coatings Application
a.
Methods of application are at the discretion of the CONTRACTOR as long as the
materials are applied in accordance with the manufacturer's published data and the
end results are in compliance with these specifications (including all others
inferred by reference).
Brushes shall be: Purdy Corporation, Professional Quality, Black China Bristle
Series, or Wooster Brush Company Pro 10, Professional Quality, Black China,
sash and trim brushes, or approved equal.
Rollers shall be Purdy Corporation, Professional Quality, Lambskin rollers with
phenolic core, or Wooster Brush Company, Professional Quality, Resin/Coat
Rollers, or Premier Lint Free, Epoxy Bonded to Phenolic Core, Premier Richmond
Hill, NY, or approved equal.
Techniques shall be used which will not allow coating droplets to travel from the
base of the tank or escape from the containment apparatus.
Prior to the cleaning or coating of any surface, the CONTRACTOR shall present a
written plan for approval by the PROJECT REPRESENTATIVE and the
ENGINEER concerning how abrasive and/or paint damage to automobiles and
property will be handled, including a process for quick removal of the abrasive or
paint, and who will do the Work. This approval in no way shall relieve the
CONTRACTOR from the responsibility of settling claims for damage, but is
intended as an avenue to expedite and minimize said claims.
7. Coating Thickness
a. Dry film thicknesses (DFT) specified in the attached painting schedule (see
Appendix, Table 1), are dry mil thicknesses measured in accordance with Steel
Structures Painting Council SSPC-PA-2, Paint Application Specification No. 2,
“Measurement of Dry Paint Thickness with Magnetic Gauges.” Painting
Contractor shall apply additional coats as necessary to achieve the specified
minimum dry film thickness range per coat.
b. The thickness of each type paint is essential to the system's integrity (see
Repair & Paint
Countryview & Bluewater Tanks (2014)
Appendix, Table 1). The addition of mils in a succeeding coat of a different
generic type or formulation to make up for thin preceding coat(s) shall not be
allowed. Ifa thicker finish coat is needed to hide the underlying darker color on
the exterior of the tank, a thicker coat may be applied, but it shall not exceed the
009870 - 20
Job No. 41-459
maximum allowable thickness recommended by the coating manufacturer.
- c. Under no circumstances shall the dry film thickness of an individual coat or of the
total coating system exceed the coating manufacturer's maximum allowable
thickness limit.
f. Dry mil thickness greater than the coating manufacturer's maximum allowable
thickness shall be considered unacceptable and shall be removed by the
CONTRACTOR at no additional cost to the OWNER at the direction of the
ENGINEER and OWNER.
g. Some coatings may require additional coats applied to achieve the specified
thickness when applied by brush or roller. No additional compensation shall be
made for additional coats required to achieve the specified minimum thickness.
8. Surface Conditions
a. The surfaces to be painted shall be free from mud, oil, grease, dust, moisture,
salts, and other foreign material which would cause adhesion or other
problems in the finished product.
b. If field tests by the ENGINEER find questionable amounts of contamination
on the steel surfaces or painted surfaces to be top-coated, a representative of
the paint manufacturer may be called to examine the surfaces in question and
determine if the surfaces are in accordance with these Detailed Technical
Specifications and the manufacturer's published product data.
9. Painting Schedule
a. The tank should be entirely cleaned and primed prior to the start of the
intermediate painting to avoid damage to the topcoats from adjacent cleaning
operations.
b. The primer shall not be applied closer than 6" to the edge of a surface yet to
be cleaned.
c. Ifthe re-coat cycle of the primer prevents completing cleaning and priming of
the tank before applying the intermediate coat, then the CONTRACTOR shall
submit, in writing, a schedule for coating application which will avoid damage
to the intermediate and finish coats when applied close to uncleaned surfaces.
10. Piping
a. The CONTRACTOR shall be responsible for assuring that no foreign material
including, but not limited to paint, abrasive, rags, or tools enter the :
inlet/outlet, drain, or overflow piping during the prosecution of the Work.
b. Any material found in this piping at the time the tank is placed back into
service shall be removed at the expense of the CONTRACTOR. To aid in
preventing the entrance of foreign material, the CONTRACTOR shall drain
the pipe and either lower the protective cover to the top of the