Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 25 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
which the Project is located.
General Conditions
Page 00700-43
SECTION 00800
SUPPLEMENTARY CONDITIONS
These Supplementary Conditions amend or supplement the Standard General Conditions of the
Construction Contract (No. 1910-8, 1996 ed.) and other provisions of the Contract Documents as indicated
below. All provisions which are not so amended or supplemented remain in full force and effect.
The terms used in these Supplementary Conditions have the meanings assigned to them in the
General Conditions. Additional terms used in these Supplementary Conditions have the meanings
indicated below, which are applicable to both the singular and plural thereof.
SC-2.02 OWNER shall furnish to CONTRACTOR up to four (4) copies of the Contract Documents
as are reasonably necessary for the execution of the Work. Additional copies will be furnished, upon
request, at the cost of reproduction.
SC-2.04 CONTRACTOR shall start to perform the Work on the date when the Contract Time
commences to run, but no Work shall be done at the site prior to the Effective Date of the Agreement.
SC-2.05.C | The CONTRACTOR shall furnish the ENGINEER with five (5) copies of Certificates of
Insurance on all required policies of insurance showing limits of liability as specified. All policies must
provide thirty (30) days advance notice to the OWNER and ENGINEER in the event of cancellation,
expiration or alteration. Each certificate shall be accompanied by a notarized statement itemizing each and
every exclusion of the policy. All certificates shall be submitted with the Agreement for execution.
SC-2.06 Within twenty (20) days after the Effective Date of the Agreement, a conference attended
by CONTRACTOR, ENGINEER and others as appropriate may be held to establish a working
understanding among the parties as to the work and to discuss the schedules referred to in paragraph 2.05.B
of the General Conditions, procedures for handling Shop Drawings and other submittals, processing
Applications for Payment, and maintaining required records.
SC-2.07 If requested by the OWNER or ENGINEER, at least ten (10) days before submission of the
first Application for Payment a conference attended by CONTRACTOR, ENGINEER and others as
appropriate will be held to review for acceptability to ENGINEER as provided below the schedules
submitted in accordance with paragraph 2.05.B of the General Conditions. CONTRACTOR shall have
an additional ten (10) days to make corrections and adjustments and to complete and resubmit the
schedules. No progress payment shall be made to CONTRACTOR until the schedules are submitted to
and acceptable to ENGINEER as provided below. The progress schedule will be acceptable to ENGINEER
as providing an orderly progression of the Work to completion within any specified Milestones and the
Contract Times, but such acceptance will neither impose on ENGINEER responsibility for the sequencing,
scheduling or progress of the Work nor interfere with or relieve CONTRACTOR from CONTRACTOR's
full responsibility therefor. CONTRACTOR's schedule of Shop Drawing and Sample submissions will be
acceptable to ENGINEER as providing a workable arrangement for reviewing and processing the required
submittals.
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-1 Job No. 41-459
Contractors schedule of values will be acceptable to Engineer as to form and substance if it provides a
reasonable allocation of the contract price to component parts of the work.
SC-3.01 In the event of aconflict between the various items which make up the Contract Documents,
the following Hierarchy of Documents shall prevail:
Contract Change Orders
Addenda
Special Conditions
Agreement
Instructions To Bidders
Supplementary Conditions
General Conditions
Technical Specifications
Drawings.
WPAN NAMNR WN
SC-4.02 When reports of subsurface explorations and tests at the project site are included in the
Bidding Documents, the CONTRACTOR may rely upon the accuracy of the Technical Data contained in
such reports as per paragraphs 4.02.B of the General Conditions. Information included in such reports
which may be considered Technical Data are: The Boring Method, Plan and Logs, Level of Subsurface
Water, Laboratory Test Methods and Results and Similar Factual Data, all as of the dates made. These
reports are not part of the Contract Documents, but the Technical Data contained therein upon which the
CONTRACTOR is entitled to rely as provided in G.C. 4.02 as identified above are incorporated therein
by reference.
SC-4.03, 4.04 The plans show certain features of the topography and certain underground utilities,
but they do not purport to show in detail all such lines or obstructions. Such topography and notes on the
plans were inserted from records available and are for the CONTRACTOR's convenience only, and shall
not be used as basis for any claims of extra compensation.
All pipes or other underground utilities shall be maintained in continuous service where possible and shall
be properly protected and supported. In no case shall interruptions to utilities be allowed to exist outside
of working hours.
Prior to starting the work, the proper authorities of all utilities shall be notified by the Contractor and the
Contractor shall cooperate in every way possible with these authorities. Whenever necessary to determine
the location of existing pipes, valves or other underground structures, the CONTRACTOR shall examine
all available records and shall make all explorations and excavations necessary for such purpose.
SC-5.01 Add the following new paragraph immediately after paragraph 5.01.C of the General
Conditions:
D. Prior to commencing work, payment and performance bonds required by this contract shall be filed
in the public records of the county where said is performed pursuant to the requirements of Title
XVIII, Section 255.05, Florida Statutes.
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-2 Job No. 41-459
SC-5.04 Add the following new paragraph immediately after paragraph 5.04.B of the General
Conditions:
C. The limits of liability for the insurance required by paragraph 5.04 of the General Conditions
shall provide coverage for not less than the following amounts or greater where required by Laws and
Regulations:
1. Workers' Compensation and related coverages under paragraphs 5.04.A.1 and 5.04.A.2 of the
General Conditions:
a.) State: Statutory
b.) Applicable Federal (e.g. Longshoreman's): Statutory
c.) Employer’s Liability $1,000,000
2. CONTRACTOR 's Liability Insurance under paragraphs 5.04.A.3 through A.6 of the General
Conditions which shall also include completed operations and product liability coverages and eliminate the
exclusion with respect to property under the care custody and control of the CONTRACTOR:
a.) General Aggregate
(Except Products - Completed Operations) $2,000,000
b.) Products - Completed Operations Aggregate $2,000,000
c.) Personal and Advertising
Injury (Per Person/Organization) $1,000,000
d.) Each Occurrence
(Bodily Injury and Property Damage) $1,000,000
e.) Property Damage Liability Insurance will provide Explosion,
Collapse and Underground coverages where applicable.
f.) Excess Liability
General Aggregate $2,000,000
Each Occurrence $2,000,000
3. Automobile Liability:
a.) Bodily Injury: $1,000,000 Each Person
$1,000,000 Each Accident
b.) Property Damage: $500,000 Each Accident
OR
c.) Combined Single Limit
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-3 Job No. 41-459
(Bodily Injury and Property Damage): $2,000,000 Each Accident
4. In addition to the requirements of Paragraph 5.04.B.1 of the General Conditions concerning
the naming of the Owner, Engineer, and Engineer's consultants as additional insureds under the
CONTRACTOR's General Liability Policy. Also, the CONTRACTOR shall at his expense provide an
OWNER's and CONTRACTOR's Protective Liability Policy issued in the name of the OWNER and
ENGINEER covering the CONTRACTOR's obligations under Paragraph 5.04.B.4 of the General
Conditions. Coverage shall be provided under this policy for not less than the following amounts:
(1) Bodily Injury: $1,000,000 Each Occurrence
(2) Property Damage: $1,000,000 Each Occurrence
$1,000,000 Annual Aggregate
SC-5.07
A. OWNER and CONTRACTOR intend that all policies purchased in accordance with paragraphs SC
5.06 will protect OWNER, CONTRACTOR, Subcontractors, ENGINEER, ENGINEER's Consultants and:
all other persons or entities identified in the Supplementary Conditions to be listed as insured or additional
insureds (and the officers, directors, partners, employees, agents, and other consultants and subcontractors
of each and any of them) in such policies and will provide primary coverage for all losses and damages
caused by the perils or causes of loss covered thereby. All such policies shall contain provisions to the
effect that in the event of payment of any loss or damage the insurers will have no rights of recovery against
any of the insureds or additional insureds thereunder. OWNER and CONTRACTOR waive all rights
against each other and their respective officers, directors, partners, employees, agents and other consultants
and subcontractors of each and any of them for all losses and damages caused by, arising out of or resulting
from any of the perils covered by such policies and any other property insurance applicable to the Work;
and, in addition, waive all such rights against Subcontractors, ENGINEER, ENGINEER's Consultants and
all other individuals or entities identified in the Supplementary Conditions to be listed as insureds or
additional insureds (and the officers, directors, partners, employees, agents, and other consultants and
subcontractors of each and any of them) under such policies for losses and damages so caused. None of
the above waivers shall extend to the rights that any party making such waiver may have to the proceeds
of insurance held by CONTRACTOR as trustee or otherwise payable under any policy so issued.
B. In addition, OWNER waives all rights against CONTRACTOR, Subcontractors, ENGINEER,
ENGINEER's Consultants and the officers, directors, partners, employees and agents and other consultants
and subcontractors of each and any of them, for:
1. loss due to business interruption, loss of use or other consequential loss extending beyond direct
physical loss or damage to OWNER's property or the Work caused by, arising out of or resulting from fire
or other peril, whether or not insured by OWNER; and
2. loss or damage to the completed Project or part thereof caused by, arising out of or resulting from
fire or other insured peril covered by any property insurance maintained on the completed Project or part
thereof by OWNER during partial utilization pursuant to paragraph 14.05, after substantial completion
pursuant to paragraph 14.04 or after final payment pursuant to paragraph 14.07.
Repair & Paint
Countryview & Bluewater Tanks (2014) 00800-4 Job No. 41-459
C. Any insurance policy maintained by CONTRACTOR covering any loss, damage or consequential
loss referred to in this paragraph SC 5.07.B shall contain provisions to the effect that in the event of
payment of any such loss, damage or consequential loss the insurers will have no rights of recovery against
OWNER, Subcontractors, ENGINEER, ENGINEER's Consultants and the officers, directors, partners,
employees, agents and other consultants and subcontractors of each and any of them.
SC-6.06.B |The CONTRACTOR, or apparent successful Bidder, shall identify Subcontractors,
Suppliers, or other persons or organizations as follows:
1) Prior to the Effective Date of the Agreement, the apparent Successful Bidder shall within
seven (7) days of the receipt of a Written Request from the OWNER or the ENGINEER
identify Subcontractors, Suppliers, or others specifically requested. Should such
identification be required, attention is directed to Article 12 of the Information For Bidders.
2) Within thirty (30)