READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 21 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
to
determine the value of a Change Order or of a
Claim, the cost of premiums for additional Bonds
and insurance required because of the changes in the
Work or caused by the event giving rise to the
Claim.
j. When all the Work is performed on the basis
of cost-plus, the costs of premiums for all Bonds and
insurance CONTRACTOR is required by the
Contract Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work shall
not include any of the following items:
1. Payroll costs and other compensation of
CONTRACTOR’s officers, executives, principals
(of partnerships and sole proprietorships), general
managers, engineers, architects, _ estimators,
attorneys, auditors, accountants, purchasing and
contracting agents, expediters, timekeepers, clerks,
and other personnel employed by CONTRACTOR,
whether at the Site or in CONTRACTOR’s principal
or branch office for general administration of the
Work and not specifically included in the agreed
upon schedule of job classifications referred to in
paragraph 11.01.A.1 or specifically covered by
paragraph 11.01.A.4, all of which are to be
considered administrative costs covered by the
CONTRACTOR’s fee.
2. Expenses of CONTRACTOR’s principal
and branch offices other than CONTRACTOR’s
office at the Site.
3. Any part of CONTRACTOR’s capital
expenses, including interest on CONTRACTOR’s
capital employed for the Work and charges against
CONTRACTOR for delinquent payments.
4. Costs due to the negligence of CON-
TRACTOR, any Subcontractor, or anyone directly
or indirectly employed by any of them or for whose
acts any of them may be liable, including but not
limited to, the correction of defective Work, disposal
of materials or equipment wrongly supplied, and
making good any damage to property.
5. Other overhead or general expense costs
of any kind and the costs of any item not specifically
and expressly included in paragraphs 11.01.A and
11.01.B.
C. CONTRACTOR’s Fee: When all the Work is
performed on the basis of cost-plus, CONTRACTOR’s fee
shall be determined as set forth in the Agreement. When
the value of any Work covered by a Change Order or when
a Claim for an adjustment in Contract Price is determined
on the basis of Cost of the Work, CONTRACTOR’s fee
shall be determined as set forth in paragraph 12.01.C.
D. Documentation: Whenever the Cost of the Work
for any purpose is to be determined pursuant to paragraphs
11.01.A and 11.01.B, CONTRACTOR will establish and
maintain records thereof in accordance with generally
accepted accounting practices and submit in a form
acceptable to ENGINEER an itemized cost breakdown
together with supporting data.
11.02 Cash Allowances
A. It is understood that CONTRACTOR has included
in the Contract Price all allowances so named in the
Contract Documents and shall cause the Work so covered to
be performed for such sums as may be acceptable to
OWNER and ENGINEER. CONTRACTOR agrees that:
1. the allowances include the cost to
CONTRACTOR (less any applicable trade
discounts) of materials and equipment required by
General Conditions
Page 00700-32
the allowances to be delivered at the Site, and all
applicable taxes; and
2. CONTRACTOR’s costs for unloading
and handling on the Site, labor, installation costs,
overhead, profit, and other expenses contemplated
for the allowances have been included in the
Contract Price and not in the allowances, and no
demand for additional payment on account of any of
the foregoing will be valid.
B. Prior to final payment, an appropriate Change
Order will be issued as recommended by ENGINEER to
reflect actual amounts due CONTRACTOR on account of
Work covered by allowances, and the Contract Price shall
be correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that all or
part of the Work is to be Unit Price Work, initially the
Contract Price will be deemed to include for all Unit Price
Work an amount equal to the sum of the unit price for each
separately identified item of Unit Price Work times the
estimated quantity of each item as indicated in the
Agreement. The estimated quantities of items of Unit Price
Work are not guaranteed and are solely for the purpose of
comparison of Bids and determining an initial Contract
Price. Determinations of the actual quantities and
classifications of Unit Price Work performed by
CONTRACTOR will be made by ENGINEER subject to
the provisions of paragraph 9.08.
B. Each unit price will be deemed to include an
amount considered by CONTRACTOR to be adequate to
cover CONTRACTOR’s overhead and profit for each
separately identified item.
SEE SUPLEMENTARY CONDITIONS (SECTION 00800)
ARTICLE 12 - CHANGE OF CONTRACT PRICE;
CHANGE OF CONTRACT TIMES
12.01 Change of Contract Price
A. The Contract Price may only be changed by a
Change Order or by a Written Amendment. Any Claim for
an adjustment in the Contract Price shall be based on
written notice submitted by the party making the Claim to
the ENGINEER and the other party to the Contract in
accordance with the provisions of paragraph 10.05.
B. The value of any Work covered by a Change
Order or of any Claim for an adjustment in the Contract
Price will be determined as follows:
1. where the Work involved is covered by
unit prices contained in the Contract Documents, by
application of such unit prices to the quantities of the
items involved (subject to the provisions of
paragraph 11.03 ); or
2. where the Work involved is not covered
by unit prices contained in the Contract Documents,
by a mutually agreed lump sum (which may include
an allowance for overhead and profit not necessarily
in accordance with paragraph 12.01.C.2); or
3. where the Work involved is not covered
by unit prices contained in the Contract Documents
and agreement to a lump sum is not reached under
paragraph 12.01.B.2, on the basis of the Cost of the
Work (determined as provided in paragraph 11.01)
plus a CONTRACTOR’ fee for overhead and profit
(determined as provided in paragraph 12.01.C).
C. CONTRACTOR’s Fee: The CONTRACTOR’s
fee for overhead and profit shall be determined as follows:
1. amutually acceptable fixed fee; or
2. if'a fixed fee is not agreed upon, then a
fee based on the following percentages of the
various portions of the Cost of the Work:
a. for costs incurred under paragraphs
11.01.A.1 and 11.01.A.2, the CONTRACTOR’s
fee shall be 15 percent;
b. for costs incurred under paragraph
11.01.4.3, the CONTRACTOR’s fee shall be
five percent;
General Conditions
Page 00700-33
c. where one or more tiers of subcontracts
are on the basis of Cost of the Work plus a fee
and no fixed fee is agreed upon, the intent of
paragraph 12.01.C.2.a is that the Subcontractor
who actually performs the Work, at whatever
tier, will be paid a fee of 15 percent of the costs
incurred by such Subcontractor under paragraphs
11.01.A.1 and 11.01.A.2 and that any higher tier
Subcontractor and CONTRACTOR will each be
paid a fee of five percent of the amount paid to
the next lower tier Subcontractor;
d. no fee shall be payable on the basis of
costs itemized under paragraphs 11.01.A.4,
11.01.A.5, and 11.01.B;
e. the amount of credit to be allowed by
CONTRACTOR to OWNER for any change
which results in a net decrease in cost will be the
amount of the actual net decrease in cost plus a
deduction in CONTRACTOR’s fee by an
amount equal to five percent of such net
decrease; and
f; when both additions and credits are in-
volved in any one change, the adjustment in
CONTRACTOR’s fee shal! be computed on the
basis of the net change in accordance with
paragraphs 12.01.C.2.a through 12.01.C.2.,
inclusive.
12.02 Change of Contract Times
A. The Contract Times (or Milestones) may only be
changed by a Change Order or by a Written Amendment.
Any Claim for an adjustment in the Contract Times (or
Milestones) shall be based on written notice submitted by
the party making the claim to the ENGINEER and the other
party to the Contract in accordance with the provisions of
paragraph 10.05.
B. Any adjustment of the Contract Times (or
Milestones) covered by a Change Order or of any Claim for
an adjustment in the Contract Times (or Milestones) will be
determined in accordance with the provisions of this
Article 12.
12.03 Delays Beyond CONTRACTOR’s Control
A. Where CONTRACTOR is prevented from
completing any part of the Work within the Contract Times
(or Milestones) due to delay beyond the control of
CONTRACTOR, the Contract Times (or Milestones) will
be extended in an amount equal to the time lost due to such
delay if a Claim is made therefore as provided in paragraph
12.02.A. Delays beyond the control of CONTRACTOR
shall include, but not be limited to, acts or neglect by
OWNER, acts or neglect of -utility owners or other
contractors performing other work as contemplated by
Article 7, fires, floods, epidemics, abnormal weather
conditions, or acts of God.
12.04 Delays Within CONTRACTOR’s Control
A. The Contract Times (or Milestones) will not be
extended due to delays within the control of
CONTRACTOR. Delays attributable to and within the
control of a Subcontractor or Supplier shall be deemed to be
delays within the control of CONTRACTOR.
12.05 Delays Beyond OWNER’s and CONTRACTOR’s
Control
A. Where CONTRACTOR is prevented from
completing any part of the Work within the Contract Times
(or Milestones) due to delay beyond the control of both
OWNER and CONTRACTOR, an extension of the
Contract Times (or Milestones) in an amount equal to the
time lost due to such delay shall be CONTRACTOR’s sole
and exclusive remedy for such delay.
12.06 Delay Damages
A. In no event shall OWNER or ENGINEER be
liable to CONTRACTOR, any Subcontractor, any Supplier,
or any other person or organization, or to any surety for or
employee or agent of any of them, for damages arising out
of or resulting from:
1. delays caused by or within the control of
CONTRACTOR; or
2. delays beyond the control of both
OWNER and CONTRACTOR including but not
limited to fires, floods, epidemics, abnormal weather
conditions, acts of God, or acts or neglect by utility
owners or other contractors performing other work
as contemplated by Article 7.
B. Nothing in this paragraph 12.06 bars a change in
Contract Price pursuant to this Article 12 to compensate
CONTRACTOR due to delay, interference, or disruption
directly attributable to actions or inactions of OWNER or
anyone for whom OWNER is responsible.
ARTICLE 13 - TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
A. Prompt notice of all defective Work of which
OWNER or ENGINEER has actual knowledge will be
given to CONTRACTOR. All defective Work may be
General Conditions
Page 00700-34
ee
rejected, corrected, or accepted as provided in this
Article 13.
13.02 Access to Work
A. OWNER, ENGINEER, ENGINEER’s Con-
sultants, other representatives and personnel of OWNER,
independent testing laboratories, and governmental agencies
with jurisdictional interests will have access to the Site and
the Work at reasonable times for their observation,
inspecting, and testing. CONTRACTOR shall provide
them proper and safe conditions for such access and advise
them of CONTRACTOR’s Site safety procedures and
programs so that they may comply therewith as applicable.
13.03 Tests and Inspections
SEE SUPLEMENTARY CONDITIONS (SECTION 00800)
C. If Laws or Regulations of any public body having
jurisdiction require any Work (or part thereof) specifically
to be inspected, tested, or approved by an employee or other
representative of such public body, CONTRACTOR shall
assume full responsibility for arranging and obtaining such
inspections, tests, or approvals, pay all costs in connection
therewith, and furnish ENGINEER the required certificates
of inspection or approval.
D. CONTRACTOR shall be responsible for
arranging and obtaining and shall pay all costs in connection
with any inspections, tests, or approvals required for
OWNER’s and ENGINEER’s acceptance of