Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 20 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
documentation required to be delivered by paragraph
14.07.A will only be to determine generally that their
content complies with the requirements of, and in the case
of certificates of inspections, tests, and approvals that the
results certified indicate compliance with, the Contract
Documents.
E. The limitations upon authority and responsibility
set forth in this paragraph 9.10 shall also apply to
ENGINEER’s Consultants, Resident Project Repre-
sentative, and assistants.
ARTICLE 10 - CHANGES IN THE WORK; CLAIMS
10.01 Authorized Changes in the Work
A. Without invalidating the Agreement and without
notice to any surety, OWNER may, at any time or from time
to time, order additions, deletions, or revisions in the Work
by a Written Amendment, a Change Order, or a Work
Change Directive. Upon receipt of any such document,
CONTRACTOR shall promptly proceed with the Work
involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise
specifically provided).
B. If OWNER and CONTRACTOR are unable to
agree on entitlement to, or on the amount or extent, if any,
of an adjustment in the Contract Price or Contract Times, or
both, that should be allowed as a result of a Work Change
Directive, a Claim may be made therefore as provided in
paragraph 10.05.
10.02 | Unauthorized Changes in the Work
A. CONTRACTOR shall not be entitled to an
increase in the Contract Price or an extension of the
Contract Times with respect to any work performed that is
not required by the Contract Documents as amended,
modified, or supplemented as provided in paragraph 3.04,
except in the case of an emergency as provided in paragraph
6.16 or in the case of uncovering Work as provided in
paragraph 13.04.B.
10.03 Execution of Change Orders
A. OWNER and CONTRACTOR shall execute
appropriate Change Orders recommended by ENGINEER
(or Written Amendments) covering:
1. changes in the Work which are: (i)
ordered by OWNER pursuant to paragraph 10.01.A,
(ii) required because of acceptance of defective
General Conditions
————
Page 00700-29
Work under paragraph 13.08.A or OWNER’s
correction of defective Work under paragraph 13.09,
or (iii) agreed to by the parties;
2. changes in the Contract Price or Contract
Times which are agreed to by the parties, including
any undisputed sum or amount of time for Work
actually performed in accordance with a Work
Change Directive; and
3. changes in the Contract Price or Contract
Times which embody the substance of any written
decision rendered by ENGINEER pursuant to para-
graph 10.05; provided that, in lieu of executing any
such Change Order, an appeal may be taken from
any such decision in accordance with the provisions
of the Contract Documents and applicable Laws and
Regulations, but during any such appeal,
CONTRACTOR shall carry on the Work and adhere
to the progress schedule as provided in paragraph
6.18.A.
10.04 Notification to Surety
A. If notice of any change affecting the general scope
of the Work or the provisions of the Contract Documents
(including, but not limited to, Contract Price or Contract
Times) is required by the provisions of any Bond to be
given to a surety, the giving of any such notice will be
CONTRACTOR’s responsibility. The amount of each
applicable Bond will be adjusted to reflect the effect of any
such change.
10.05 Claims and Disputes
A. Notice: Written notice stating the general nature
of each Claim, dispute, or other matter shall be delivered by
the claimant to ENGINEER and the other party to the
Contract promptly (but in no event later than 30 days) after
the start of the event giving rise thereto. Notice of the
amount or extent of the Claim, dispute, or other matter with
supporting data shall be delivered to the ENGINEER and
the other party to the Contract within 60 days after the start
of such event (unless ENGINEER allows additional time
for claimant to submit additional or more accurate data in
support of such Claim, dispute, or other matter). A Claim
for an adjustment in Contract Price shall be prepared in
accordance with the provisions of paragraph 12.01.B. A
Claim for an adjustment in Contract Time shall be prepared
in accordance with the provisions of paragraph 12.02.B.
Each Claim shall be accompanied by claimant's written
statement that the adjustment claimed is the entire
adjustment to which the claimant believes it is entitled as a
result of said event. The opposing party shall submit any
response to ENGINEER and the claimant within 30 days
after receipt of the claimant’s last submittal (unless
ENGINEER allows additional time).
B. ENGINEER'’s Decision: ENGINEER will render
a formal decision in writing within 30 days after receipt of
the last submittal of the claimant or the last submittal of the
opposing party, if any. ENGINEER’s written decision on
such Claim, dispute, or other matter will be final and
binding upon OWNER and CONTRACTOR unless:
1. an appeal from ENGINEER’s decision is
taken within the time limits and in accordance with
the dispute resolution procedures set forth in Article
16; or
2. if no such dispute resolution procedures
have been set forth in Article 16, a written notice of
intention to appeal from ENGINEER’s written
decision is delivered by OWNER or
CONTRACTOR to the other and to ENGINEER
within 30 days after the date of such decision, and a
formal proceeding is instituted by the appealing
party in a forum of competent jurisdiction within 60
days after the date of such decision or within 60 days
after Substantial Completion, whichever is later
(unless otherwise agreed in writing by OWNER and
CONTRACTOR), to exercise such rights or
remedies as the appealing party may have with
respect to such Claim, dispute, or other matter in
accordance with applicable Laws and Regulations.
C. If ENGINEER does not render a formal decision
in writing within the time stated in paragraph 10.05.B, a
decision denying the Claim in its entirety shall be deemed to
have been issued 31 days after receipt of the last submittal
General Conditions
Page 00700-30
ES S=SASS:;éS=
of the claimant or the last submittal of the opposing party, if
any.
D. No Claim for an adjustment in Contract Price or
Contract Times (or Milestones) will be valid if not
submitted in accordance with this paragraph 10.05.
ARTICLE 11 - COST OF THE WORK; CASH
ALLOWANCES; UNIT PRICE WORK
11.01 Cost of the Work
A. Costs Included: The term Cost of the Work means
the sum of all costs necessarily incurred and paid by
CONTRACTOR in the proper performance of the Work.
When the value of any Work covered by a Change Order or
when a Claim for an adjustment in Contract Price is
determined on the basis of Cost of the Work, the costs to be
reimbursed to CONTRACTOR will be only those
additional or incremental costs required because of the
change in the Work or because of the event giving rise to
the Claim. Except as otherwise may be agreed to in writing
by OWNER, such costs shall be in amounts no higher than
those prevailing in the locality of the Project, shall include
only the following items, and shall not include any of the
costs itemized in paragraph 11.01.B.
1. Payroll costs for employees in the direct
employ of CONTRACTOR in the performance of
the Work under schedules of job classifications
agreed upon by OWNER and CONTRACTOR.
Such employees shall include without limitation
superintendents, foremen, and other personnel
employed full time at the Site. Payroll costs for
employees not employed full time on the Work shall
be apportioned on the basis of their time spent on the
Work. Payroll costs shall include, but not be limited
to, salaries and wages plus the cost of fringe
benefits, which shall include social security
contributions, unemployment, excise, and payroll
taxes, workers’ compensation, health and retirement
benefits, bonuses, sick leave, vacation and holiday
pay applicable thereto. The expenses of performing
Work outside of regular working hours, on Saturday,
Sunday, or legal holidays, shall be included in the
above to the extent authorized by OWNER.
4. Cost of all materials and equipment
furnished and incorporated in the Work, including
costs of transportation and storage thereof, and
Suppliers’ field services required in connection
therewith. All cash discounts shall accrue to
CONTRACTOR unless OWNER deposits funds
with CONTRACTOR with which to make pay-
ments, in which case the cash discounts shall accrue
to OWNER. All trade discounts, rebates and
refunds and returns from sale of surplus materials
and equipment shall accrue to OWNER, and
CONTRACTOR shall make provisions so that they
may be obtained.
3. Payments made by CONTRACTOR to
Subcontractors for Work performed by
Subcontractors. If required by OWNER, CON-
TRACTOR shall obtain competitive bids from
subcontractors acceptable to OWNER and CON-
TRACTOR and shall deliver such bids to OWNER,
who will then determine, with the advice of
ENGINEER, which bids, if any, will be acceptable.
If any subcontract provides that the Subcontractor is
to be paid on the basis of Cost of the Work plus a
fee, the Subcontractor’s Cost of the Work and fee
shall be determined in the same manner as
CONTRACTOR’s Cost of the Work and fee as
provided in this paragraph 11.01.
4. Costs of special consultants (including
but not limited to engineers, architects, testing
laboratories, surveyors, attorneys, and accountants)
employed for services specifically related to the
Work.
5. Supplemental costs including — the
following:
a. The proportion of necessary transportation,
travel, and subsistence expenses of
CONTRACTOR’s employees incurred in discharge
of duties connected with the Work.
b. Cost, including transportation and
maintenance, of all materials, supplies, equipment,
machinery, appliances, office, and temporary
facilities at the Site, and hand tools not owned by the
workers, which are consumed in the performance of
the Work, and cost, less market value, of such items
used but not consumed which remain the property of
CONTRACTOR.
c. Rentals of all construction equipment and
machinery, and the parts thereof whether rented
from CONTRACTOR or others in accordance with
rental agreements approved by OWNER with the
advice of ENGINEER, and the costs of
transportation, loading, unloading, assembly,
dismantling, and removal thereof. Alli such costs
shall be in accordance with the terms of said rental
agreements. The rental of any such equipment,
machinery, or parts shall cease when the use thereof
is no longer necessary for the Work.
d. Sales, consumer, use, and other similar
taxes related to the Work, and for which CON-
General Conditions
Page 00700-31
TRACTOR is liable, imposed by Laws and Regu-
lations.
e. Deposits lost for causes other than negli-
gence of CONTRACTOR, any Subcontractor, or
anyone directly or indirectly employed by any of
them or for whose acts any of them may be liable,
and royalty payments and fees for permits and
licenses.
f. Losses and damages (and related
expenses) caused by damage to the Work, not
compensated by insurance or otherwise, sustained by
CONTRACTOR in connection with the perfor-
mance of the Work (except losses and damages
within the deductible amounts of property insurance
established in accordance with paragraph 5.06.D),
provided such losses and damages have resulted
from causes other than the negligence of
CONTRACTOR, any Subcontractor, or anyone
directly or indirectly employed by any of them or for
whose acts any of them may be liable. Such losses
Shall include settlements made with the written
consent and approval of OWNER. No such losses,
damages, and expenses shall be included in the Cost
of the Work for the purpose of determining
CONTRACTOR’s fee.
g- The cost of utilities, fuel, and sanitary
facilities at the Site.
h. Minor expenses such as telegrams, long
distance telephone calls, telephone service at the
Site, expressage, and similar petty cash items in
connection with the Work.
i. When the Cost of the Work is used