READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — February 18, 2014 — Repair & Paint Countryview & Bluewater Tanks — reading text
Part 13 of 35. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 90-Repair _ Paint Countryview _ Bluewater Tanks.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
equipment complete and
ready for intended use.
4. When “furnish,” “install,” “perform,” or “pro-
vide” is not used in connection with services, materials,
or equipment in a context clearly requiring an obligation
of CONTRACTOR, “provide” is implied.
E. Unless stated otherwise in the Contract Docu-
ments, words or phrases which have a well-known technical
or construction industry or trade meaning are used in the
Contract Documents in accordance with such recognized
meaning.
ARTICLE 2 - PRELIMINARY MATTERS
2.01 Delivery of Bonds
A. When CONTRACTOR delivers the executed
Agreements to OWNER, CONTRACTOR shall also deliver
to OWNER such Bonds as CONTRACTOR may be
required to furnish.
2.02 Copies of Documents
SEE SUPPLEMENTARY CONDITIONS (SECTION
00800)
2.03 Commencement of Contract Times; Notice to
Proceed
A. The Contract Times will commence to run on the
thirtieth day after the Effective Date of the Agreement or, if
a Notice to Proceed is given, on the day indicated in the
Notice to Proceed. A Notice to Proceed may be given at
any time within 30 days after the Effective Date of the
Agreement. In no event will the Contract Times commence
to run later than the sixtieth day after the day of Bid opening
or the thirtieth day after the Effective Date of the
Agreement, whichever date is earlier.
2.04 = Starting the Work
SEE SUPPLEMENTARY CONDITIONS (SECTION
00800)
2.05 Before Starting Construction
A. CONTRACTOR’s Review of Contract Documents:
Before undertaking each part of the Work,
CONTRACTOR shall carefully study and compare the
Contract Documents and check and verify pertinent figures
therein and all applicable field measurements.
CONTRACTOR shall promptly report in writing to
ENGINEER any conflict, error, ambiguity, or discrepancy
which CONTRACTOR may discover and shall obtain a
written interpretation or clarification from ENGINEER
before proceeding with any Work affected thereby;
however, CONTRACTOR shall not be liable to OWNER
or ENGINEER for failure to report any conflict, error,
ambiguity, or discrepancy in the Contract Documents unless
CONTRACTOR knew or reasonably should have known
thereof.
B. Preliminary Schedules: Within ten days after the
Effective Date of the Agreement (unless otherwise specified
in the General Requirements), CONTRACTOR shall
submit to ENGINEER for its timely review:
1. a preliminary progress schedule
indicating the times (numbers of days or dates) for
starting and completing the various stages of the
Work, including any Milestones specified in the
Contract Documents;
2. a preliminary schedule of Shop Drawing
and Sample submittals which will list each required
submittal and the times for submitting, reviewing,
and processing such submittal; and
General Conditions
Page 00700-9
3. apreliminary schedule of values for all of
the Work which includes quantities and prices of
items which when added together equal the Contract
Price and subdivides the Work into component parts
in sufficient detail to serve as the basis for progress
payments during performance of the Work. Such
prices will include an appropriate amount of
overhead and profit applicable to each item of
Work.
SEE SUPPLEMENTARY CONDITIONS (SECTION 00800)
2.06 Preconstruction Conference
SEE SUPPLEMENTARY CONDITIONS (SECTION
00800)
2.07 Initial Acceptance of Schedules
SEE SUPPLEMENTARY CONDITIONS (SECTION 00800)
INTENT,
ARTICLE 3 - CONTRACT DOCUMENTS:
AMENDING, REUSE
3.01 Intent
SEE ALSO SUPPLEMENTARY CONDITIONS (SECTION
00800)
A. The Contract Documents are complementary,
what is called for by one is as binding as if called for by all.
B. It is the intent of the Contract Documents to
describe a functionally complete Project (or part thereof) to
be constructed in accordance with the Contract Documents.
Any labor, documentation, services, materials, or
equipment that may reasonably be inferred from the
Contract Documents or from prevailing custom or trade
usage as being required to produce the intended result will
be provided whether or not specifically called for at no
additional cost to OWNER.
C. Clarifications and interpretations of the Contract
Documents shall be issued by ENGINEER as provided in
Article 9.
3.02 Reference Standards
A. Standards, Specifications, Codes, Laws, and
Regulations
1. Reference to standards, specifications,
manuals, or codes of any technical society,
organization, or association, or to Laws or
Regulations, whether such reference be specific or
by implication, shall mean the standard,
specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the
Effective Date of the Agreement if there were no
Bids), except as may be otherwise specifically stated
in the Contract Documents.
General Conditions
Page 00700-10
2. No provision of any such standard,
specification, manual or code, or any instruction of a
Supplier shall be effective to change the duties or
responsibilities of OWNER, CONTRACTOR, or
ENGINEER, or any of their subcontractors,
consultants, agents, or employees from those set
forth in the Contract Documents, nor shall any such
provision or instruction be effective to assign to
OWNER, ENGINEER, or any of ENGINEER’s
Consultants, agents, or employees any duty or
authority to supervise or direct the performance of
the Work or any duty or authority to undertake
responsibility inconsistent with the provisions of the
Contract Documents.
3.03 Reporting and Resolving Discrepancies
_ A. Reporting Discrepancies
1. If, during the performance of the Work,
CONTRACTOR discovers any conflict, error,
ambiguity, or discrepancy within the Contract
Documents or between the Contract Documents and
any provision of any Law or Regulation applicable
to the performance of the Work or of any standard,
specification, manual or code, or of any instruction
of any Supplier, CONTRACTOR shall report it to
ENGINEER in writing at once. CONTRACTOR
shall not proceed with the Work affected thereby
(except in an emergency as required by paragraph
6.16.A) until an amendment or supplement to the
Contract Documents has been issued by one of the
methods indicated in paragraph 3.04; provided,
however, that CONTRACTOR shall not be liable to
OWNER or ENGINEER for failure to report any
such conflict, error, ambiguity, or discrepancy unless
CONTRACTOR knew or reasonably should have
known thereof.
B. Resolving Discrepancies
1. | Except as may be otherwise specifically
stated in the Contract Documents, the provisions of
the Contract Documents shall take precedence in
resolving any . conflict, error, ambiguity, or
discrepancy between the provisions of the Contract
Documents and:
a. the provisions of any standard,
specification, manual, code, or instruction
(whether or not specifically incorporated by
reference in the Contract Documents); or
b. the provisions of any Laws or
Regulations applicable to the performance of the
Work (unless such an interpretation of the
provisions of the Contract Documents would
result in violation of such Law or Regulation).
3.04 Amending and Supplementing Contract
Documents
A. The Contract Documents may be amended to
provide for additions, deletions, and revisions in the Work
or to modify the terms and conditions thereof in one or
more of the following ways: (i) a Written Amendment, (ii) a
Change Order; or (iii) a Work Change Directive.
B. The requirements of the Contract Documents may
be supplemented, and minor variations and deviations in the
Work may be authorized, by one or more of the following
ways: (i) a Field Order; (ii) ENGINEER’s approval of a
Shop Drawing or Sample; or (iii) ENGINEER’s written
interpretation or clarification.
3.05 Reuse of Documents
A. CONTRACTOR and any Subcontractor or
Supplier or other individual or entity performing or
furnishing any of the Work under a direct or indirect
contract with OWNER: (i) shall not have or acquire any title
to or ownership rights in any of the Drawings,
Specifications, or other documents (or copies of any
thereof) prepared by or bearing the seal of ENGINEER or
ENGINEER’s Consultant, including electronic media
editions; and (ii) shall not reuse any of such Drawings,
Specifications, other documents, or copies thereof on
extensions of the Project or any other project without
written consent of OWNER and ENGINEER and specific
written verification or adaption by ENGINEER. This
prohibition will survive final payment, completion, and
acceptance of the Work, or termination or completion of the
Contract. Nothing herein shall preclude CONTRACTOR
from retaining copies of the Contract Documents for record
purposes.
ARTICLE 4 - AVAILABILITY OF LANDS;
SUBSURFACE AND PHYSICAL CONDITIONS;
REFERENCE POINTS
4.01 Availability of Lands
A. OWNER shall furnish the Site. OWNER shall
notify CONTRACTOR of any encumbrances or restrictions
not of general application but specifically related to use of
the Site with which CONTRACTOR must comply in
performing the Work. OWNER will obtain in a timely
manner and pay for easements for permanent structures or
permanent changes in existing _ facilities. If
CONTRACTOR and OWNER are unable to agree on
entitlement to or on the amount or extent, if any, of any
adjustment in the Contract Price or Contract Times, or both,
as a result of any delay in OWNER’s furnishing the Site,
CONTRACTOR may make a Claim therefor as provided in
paragraph 10.05.
General Conditions
Page 00700-11
B. Upon reasonable written request, OWNER shall
furnish CONTRACTOR with a current statement of record
legal title and legal description of the lands upon which the
Work is to be performed and OWNER’s interest therein as
necessary for giving notice of or filing a mechanic's or
construction lien against such lands in accordance with
applicable Laws and Regulations.
C. CONTRACTOR shall provide for all additional
lands and access thereto that may be required for temporary
construction facilities or storage of materials and equip-
ment.
4.02 Subsurface and Physical Conditions
A. Reports and Drawings: The Supplementary
Conditions identify:
1. those reports of explorations and tests of
subsurface conditions at or contiguous to the Site
that ENGINEER has used in preparing the Contract
Documents; and
2. those drawings of physical conditions in
or relating to existing surface or subsurface
Structures at or contiguous to the Site (except
Underground Facilities) that ENGINEER has used
in preparing the Contract Documents.
’ B. Limited Reliance by CONTRACTOR on Technical
Data Authorized) CONTRACTOR may rely upon the
general accuracy of the “technical data” contained in such
reports and drawings, but such reports and drawings are not
Contract Documents. Such “technical data” is identified in
the Supplementary Conditions. Except for such reliance on
such “technical data,” CONTRACTOR may not rely upon
or make any Claim against OWNER, ENGINEER, or any
of ENGINEER’s Consultants with respect to:
1. the completeness of such reports and
drawings for CONTRACTOR’s purposes, including,
but not limited to, any aspects of the means,
methods, techniques, sequences, and procedures of
construction to be employed by CONTRACTOR,
and safety precautions and programs incident
thereto; or
2. other data, interpretations, opinions, and
information contained in such reports or shown or
indicated in such drawings; or
3. any CONTRACTOR interpretation of or
conclusion drawn from any "technical data" or any
such other data, interpretations, opinions, or
information.
4.03 Differing Subsurface or Physical Conditions
SEE ALSO SUPPLEMENTARY CONDITIONS (SECTION
00800)
A. Notice: If CONTRACTOR believes that any
subsurface or physical condition at or contiguous to the Site
that is uncovered or revealed either:
1. is of such a nature as to establish that any
“technical data” on which CONTRACTOR is
entitled to rely as provided in paragraph 4.02 is
materially inaccurate; or
2. is of such a nature as to require a change
in the Contract Documents; or
3. differs materially from that shown or