and both projects will be bid together with an anticipated construction duration of 180 days.
OPTIONS: Approve/Disapprove the request to advertise the RFB and administer the
construction contract for Grant Agreement No. S0697 for the Tanglewood and Overbrook
Stormwater Basin Improvements.
RECOMMENDATIONS: Approve the request to advertise the RFB and administer the
construction contract for Grant Agreement No. S0697 for the Tanglewood and Overbrook
Stormwater Basin Improvements.
RECOMMENDED BY:
Packet Pg. 399
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 400
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Final Payment - 12th Avenue Sidewalk Addition LAP
DEPARTMENT: Public Works
BCC DISTRICT: 2
STATEMENT OF ISSUE: Main Street Construction Services, LLC contracted with Okaloosa
County to perform the work associated with the 12th Avenue Sidewalk Addition LAP Project.
All work has been completed and found to be in compliance with the approved plans and
specifications. Substantial Completion was achieved on April 24, 2014 and Final Acceptance of
the project was given on May 15, 2014 after a final inspection was conducted by Genesis CEI
and County representatives. The Contractor has submitted a final invoice along with all required
documentation and is requesting final payment including release of retainage.
BACKGROUND AND ANALYSIS: On October 10, 2013 Okaloosa County entered into a
contract with Main Street Construction Services, LLC to perform the work associated with the
12th Avenue Sidewalk Addition LAP Project. Through the course of the project there were two
change orders resulting in a net decrease of $4,940.00 with 12 added contract days (due to
weather). This total change order amount includes balancing estimated plan quantities with final
installed quantities used to complete the project.
Main Street Construction Services, LLC has requested that final payment be made for all work
performed. A final pay application for the contract balance of $9,086.28 is attached. This final
pay request will release all retainage and cause the work to enter the one year performance
warranty period.
OPTIONS: Approve/Disapprove final payment to Main Street Construction Services, LLC in
the amount of $9,086.28 for work associated with the 12th Avenue Sidewalk Addition LAP
Project.
RECOMMENDATION: Approve final payment to Main Street Construction Services, LLC in
the amount of $9,086.28 for work associated with the 12th Avenue Sidewalk Addition LAP
Project.
RECOMMENDED BY:
Packet Pg. 401
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 402
Packet Pg. 403
Packet Pg. 404
Packet Pg. 405
Packet Pg. 406
Packet Pg. 407
Packet Pg. 408
Packet Pg. 409
Packet Pg. 410
Packet Pg. 411
Packet Pg. 412
Packet Pg. 413
Packet Pg. 414
Packet Pg. 415
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Event Permit - Emerald Coast 2014 Fall Classic Volleyball Event
DEPARTMENT: Public Works
BCC DISTRICT: Two
STATEMENT OF ISSUE: Southern Events Management, Inc., has requested permission to
utilize county beach area to conduct a five day volleyball tournament.
BACKGROUND and ANALYSIS: County Ordinance #13-07 (regulation of county
recreational areas, including parks and beaches) addresses Special Events at county parks,
beaches, or recreational areas within Okaloosa County.
A request has been received from Southern Events Management, Inc., to conduct a five day
volleyball tournament near the Boardwalk on Okaloosa Island. The event would take place
beginning Wednesday, Oct. 1st and would continue through Sunday, Oct. 5th between the hours
of 7:30 A.M. and 5:00 P.M. each day. Setup for the event would begin Monday, Sept. 29th and
final break down would take place Monday, Oct. 6th.
This request has been reviewed by Public Works, Public Safety, the Sheriff’s Office and the
Tourist Development Department. The Lessee at the Boardwalk has concurred with the request.
OPTIONS: Approve/Disapprove
RECOMMENDATIONS: Approve the request for a Special Event permit for Southern Events
Management to conduct a 5-day volleyball tournament to be held on the County beach adjacent
to the Boardwalk on Okaloosa Island.
RECOMMENDED BY:
APPROVED BY:
Packet Pg. 416
Ernie Padgett, County Administrator
Packet Pg. 417
Packet Pg. 418
Packet Pg. 419
Packet Pg. 420
Packet Pg. 421
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: John Hofstad
SUBJECT: Seeking Approval to Purchase Class 1 Rip Rap.
DEPARTMENT: Public Works
BCC DISTRICT: All
STATEMENT OF ISSUE: [PW] Seeking approval to purchase Class 1 Rip Rap from Southern
Rock & Lime for the Gilmore Road Project.
BACKGROUND & ANALYSIS: The Public Works Department has requested the purchase of
class 1 rip rap for the construction of Gilmore Road. The amount of rip rap needed was not
anticipated as part of the initial project design/estimate. Bids were solicited through Purchasing
and three bids were received. Southern Rock and Lime submitted a bid meeting specifications
for a total cost of $57,776.25. The total funding approved for the project in the FY14 Local
Option Gas Tax (LOGT - 3202) account was $150,000. Public Works staff is requesting the
Board also approve exceeding the $150,000 project budget for the purchase of the rip rap. Due
to storm and other project delays, it is unlikely that the Road Department will get to placement of
all of the Asphalt Millings projects this year. The asphalt millings account has a balance of
$100,000 that can be utilized to fund the over run for Gilmore Road.
OPTIONS: Approve/Deny purchase of class 1 rip rap from Southern Rock and Lime and
approve the transfer of funding.
RECOMMENDATION: Staff recommends approving purchase of class 1 rip rap from
Southern Rock and Lime in the amount of $57,776.25and approve the transfer of funding from
3202-553038 Materials-Millings to 3202-563162 Gilmore Road.
.
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 422
Packet Pg. 423
Packet Pg. 424
Packet Pg. 425
Packet Pg. 426
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: Ed Schroeder
SUBJECT: IMap Software - 50% advance payment
DEPARTMENT: Tourist Development Department
BCC DISTRICT:
STATEMENT OF ISSUE: Request approval for payment in advance for 50% of first-year
interactive floor plan software costs for the Emerald Coast Convention Center.
BACKGROUND: iMap Multimedia provides an interactive floor plan service allowing people
to virtually tour the Emerald Coast Convention Center online. Visitors to
emeraldcoastconventioncenter.com will simply click on the landing page floor plans and be able
to link out to the iMap site which hosts all the convention center’s diagrams and pictures in an
interactive format that gives clients the ability to see rooms and determine how their event will
fit within the convention center’s space. Although the software doesn’t in anyway touch the
county network, Tourist Development sought and obtained Information Systems concurrence
with the purchase.
The total package price is $11,760 for the first year, including the first year’s license fee. The
annual license fee of $1,960 is recurring every year thereafter. There is a considerable amount of
resource requirements to customize the software to meet the specific needs of the Emerald Coast
Convention Center, and advanced payment is industry standard practice. iMap’s official policy
is to receive 50% of payment upon agreement acceptance to secure and schedule in the project
and help fund the development cost for the project, with the other 50% upon projection
completion. There is no exception to this policy and iMap can only engage in delivering projects
under this payment arrangement presented in the proposal.
Pursuant to Section E.700(2) of the Tourist Development Department Operations and Procedures
Manual, no advancement of funds will be issued unless specifically approved by the Board.
Pursuant to the State Chief Financial Officer’s Reference Guide for State Expenditures, advance
payment may be made if the payment results in savings equal to or greater than the amount
earned by investing the funds and paying later or if the payment is essential to the operations of
the agency and the goods or services are available only if advance payment is made. In this
particular case, the services are available only if advance payment of 50% of first-year cost of
$11,760 is made.
OPTIONS: Approve or Disapprove
RECOMMENDATION: Approve payment in advance for 50% of first-year interactive floor
plan software costs for the Emerald Coast Convention Center.
Packet Pg. 427
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator
Packet Pg. 428
Packet Pg. 429
Packet Pg. 430
Packet Pg. 431
Packet Pg. 432
Packet Pg. 433
Packet Pg. 434
Packet Pg. 435
Packet Pg. 436
Packet Pg. 437
Packet Pg. 438
Packet Pg. 439
Packet Pg. 440
Packet Pg. 441
Packet Pg. 442
Packet Pg. 443
Packet Pg. 444
Packet Pg. 445
Packet Pg. 446
Packet Pg. 447
Packet Pg. 448
Packet Pg. 449
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: July 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: Ed Schroeder
SUBJECT: Sport Fishing TV Promotional Marketing Opportunity
DEPARTMENT: Tourist Development Department
BCC DISTRICT:
STATEMENT OF ISSUE: Request approval of an amount not-to-exceed $15K from
Promotional Reserve for a 30-minute sport fishing television episode, online video production,
and print and online editorial.
BACKGROUND: The Tourist Development Department was approached in late June about a
30-minute television episode showcasing Destin fishing. The episode would air 76 times during
the year on nine networks, including the World Fishing Network. The $10K cost includes a
sport fishing television episode, online video production, and print and online editorial, with the
objective of increasing visitation and lodging facility occupancy. Additionally, meals,
accommodations, and transportation are estimated at $5K. However, based on when filming
occurs, a large portion of these ancillary expenses may be covered by industry partners.
The Consolidated Strategic Marketing Plan (SMP) adopted by BCC on May 6, 2014 includes a
Promotional Reserve category in the amount of $150,061. Funding in the amount of $80,699