CHANGE ORDER FORM
Date: 10/06/14 Contract No.; _C14-2184-FM Change Order No.: _ 14-02
Owner: __ OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS
Contractor: Lord & Son Construction, Inc.
CHANGE TO CONTRACT PRICE
DESCRIPTION AMOUNT
Original Contract Price: 10,000.00
Net change by previously authorized Change Orders: 306,730.00
Present Contract Price: 316,730.00
This Change Order will (add/deduct): 1,167,334.00
New Contract Price: 1,484,064.00
CHANGE TO CONTRACT TIME
DESCRIPTION DATE or NUMBER OF DAYS
Original Contract Time: TBD TBD
Original Substantial Completion Date: TBD
Net change by previously authorized Change Orders: N/A
This Change Order will (add/deduct): N/A
New Contract Time: N/A
New Substantial Completion Date: N/A
APPROVALS
REQUESTED BY: DATE:
PROJECT ENGINEER: Wa DATE:
CONTRACTOR? —L_ DATE: 10/06/14
Leven D. Lord, II, President
OWNER: DATE:
This Change Order is an amendment to the Contract/Agreement between Contractor and the
Owner, and all other contract provisions shall remain in full force and effect unless specifically
amended in writing, signed by both parties.
CHANGE OWNER
od
ORDER ARCHITECT o
CONTRACTOR a
FIELD go
AIA DOCUMENT G701 (Modified) OTHER ag
PROJECT: New Office Addition at the Okaloosa
County Sheriff's Office in Shalimar CHANGE ORDER NUMBER: Two (2)
(name, address) 50 24 Street DATE: 6 October 2014
Shalimar, FL 32579
TO CONTRACTOR: ARCHITECT'S PROJECT NO: 14007
(name, address)
Lord & Son Construction, Inc. CONTRACT DATE: May 12, 2014
Post Office Box 1808
Fort Walton Beach, FL 32549 CONTRACT FOR: CM @ Risk Services
The Contract is changed as follows:
Adjustment to contract for Approved GMP amount (see attached Change Order 2 Breakdown).
Not valid until signed by the Owner and Contractor.
The original (Contract Sum) was..........0..ccsceceeceecceeeeeee tees set ete ete saeteeseeeeeeeeceaeaeae $10,000.00
Net change by previously authorized Change Orders.........0.0::::ceeeeee $306,730.00
The (Contract Sum) prior to this Change Order was ...........:.:.0:0:- rete teeter eesti : $316,730.00
The (Contract Sum)) will be (increased) by this Change Order in the amount of $1,167,334.00
The new (Contract Sum) including this Change Order will be .........0..0cccceeeeeeee $1,484,064.00
The Contract Time will be changed by: N/A
The date of Substantial Completion as of the date of this Change Order therefore is: Per Contract
NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized
by Construction Change Directive.
DAG Architects, Inc. Lord & Son Construction, Inc. Okaloosa County BOCC
Architect Contractor Owner
4223 Airport Road Post Office Box 1808 1804 Lewis Turner Blvd., Ste. 100
Destin, FL 32541 Fort Walton Beach, FL 32549 Fort Walton Beach, FL 32547
wai ‘Vache Address Address
By. By. By.
Crtarles W€lary Ill, FAJA Leven D. Lord li Kelly Windes
President Chairman
Architect
Date: I th U of Date: Date:
AIA DOCUMENT G701 - CHANGE ORDER « 1987 EDITION = AIA - 1987 » THE AMERICAN INSTITUTE OF ARCHITECTS
1755 NEW YORK AVE, NW., WASHINGTON, DC. 20006 G701-1987 (Modified)
Breakdown
Change Order 2
Add 100% GMP to the existing contract for the Okaloosa County Sheriff's Office
oO Addition.
100% GMP Proposal $1,504,147.00
Exhibit A dated 9/16/2014
Deduct Estimated Sales Tax Savings ($ 30,083.00)
Adjusted GMP - Approved $1,474,064.00
Deduct CO #1 ; ($ 306,730.00)
Exhibit B dated 7/2/2014
Total Change Order 2 $1,167,334.00
Okaloosa County Sherif's Office Addition
Contract C14-2184-FM
Change Order 2 Breakdown for Contract Adjustment per Approved GMP
GMP Budget $1,504,147.00
Less Est. Sales Tax Savings ($30,083.00)
Adjusted GMP Budget - Approved $1,474,064.00
Less Change Order 1 ($306,730.00)
Total Adjustment for Approved GMP - CO 2 $1,167,334.00
JIII0 3D
)
OKALOOSA SHERIFF’S OFFICE.ADDITION
_ 100% GMP PROPOSAL
SEPTEMBER 16, 2014
State of FL Certified General Contractor #CG CO08942
State of FL Certified General Contractor #CG CO57094
CONSTRUCTION, State of AL Certified General Contractor #12776
NC. State of GA Certified General Contractor #@CCO002537
CONSTRUCTION MANAGER / GENERAL CONTRACTOR State of MS Certiied General Contractor #08714-MC
Trusted Performance ... Lasting Value
Sheriff's Office Addition
100% G.M.P. Proposal
Summary:
Attached is the breakdown information for the G.M.P. proposal for the subject
project. Bids were received at 2:00 P.M. on August 20, 2014 based on the 100%
construction documents dated July 15, 2014.
We have attached the bid breakdown, subcontractor recommendations, revised
schedule, and assumptions with clarifications.
The original budget estimate of $1,269,512 was impacted by a major revision to
the foundation design. This redesign increased dewatering, reinforcing, concrete and
compaction requirements. We had no information concerning the site utilities at the time
of the initial budget estimate, and we stated that the estimate was for buildings only. The
cost impacts for these two additions to scope equal over $200,000.
Please note that the schematic estimate developed in April 2014 appears to be at
the beginning of construction resurgence in this local area. We are seeing dramatic
increases of 3 to 5% in many of the work areas (primarily concrete, masonry, mechanical,
electrical, and plumbing) due to increased material costs and labor shortages of skilled
workers.
Our 50% estimate captured these additional costs as well as minor scope
increases in plumbing, HVAC, and access control. The 50% estimate total was
$1,573,715. As noted in the 50% budget estimate review, some of the documents were
not as compiete as others, and our assumptions, while conservative, did not anticipate all
of the scope as drawn on 100% documents. These differences are minor and do not
appreciably affect the G.M.P.
We have included governmental requirement fees that are cost of doing work (i.e.
building permit and fire department fee), but not the water, sewer, development fees, and
storm water department fees, as they have not been furnished to us.
We have included a revised schedule that incorporates the design time lost during
the redesign of foundation and site utilities.
CN 19 David Street - Fort Walton Beach, Florida 32547
a P.O. Box 1808 - Fort Walton Beach, Florida 32549
850-863-5158 « FAX 850-862-4904
Lonty tetas info@lordandson.com
‘Associated Builders www.lordandson.com
North Fiorida
Chapter
Specializing in Commercial Construction
Sie 1975
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
September 16, 2014
The following list of information and qualifications serve as the basis for the Schematic Budget.
LIST OF PLAN SHEETS
Civil Sheet 1 through 7 dated 07/10/2014 prepared by Choctaw Engineering, Inc.
Sheets G001, LS101, A010 (07/29/2014) , A101 (07/29/2014), A102, A103, A201, A301,
A401, A402, A403, A501 (07/29/2014), A601 (07/29/2014), A602 (07/29/2014), FP101, P101,
P102, P201, P301, M101 (07/29/2014), M201 (07/29/2014), M301, M302, E1.0 (07/29/2014),
E1.1, £1.2, E2.0, £3.0 (08/18/2014), E3.1(08/18/2014), E4.0 (08/18/2014), E4.1 (08/18/2014),
E4.2 (08/18/2014), and E5.0 (08/18/2014) dated 07/15/2014 (unless otherwise noted) as
prepared by DAG Architects Inc.
Structural Sheets S.0, S.1, and S.2 Addendum date 07/18/2014 prepared by RAC
Engineering, Inc.
Pre-Engineered Metal Building Drawings E1 through E19 dated 6/19/2014 as prepared by
Kirby Building Systems.
Ecospan Composite Floor System Sheets J-1, D-1, and JN-1 dated 7/3/2014 as prepared by
Nucor Detaining Center.
Specification dated 07/23/2014 as prepared by dag Architects Inc.
Report of Geotechnical Exploration dated 07/15/2014 as prepared by Larry M. Jacobs &
Associates, Inc.
Addendum 01 dated 08/04/2014 and Addendum 02 dated 08/18/2014
General Conditions
Building permit is included at an allowance $8924.
Fire Department Fee is included in the Building Permit Allowance.
Bond is included.
Builder Risk Insurance is included.
Contractors Liability Insurance is included
Waiter & sewer tap and impact fees are NOT included.
Temporary construction fence is included in this budget as dictated by the security
requirements of the Sheriff's office.
Development fees and storm water fees are NOT included.
Architectural & Engineering fees are not included in this construction budget.
Staking out of the building, As-Built Survey, and foundation survey are included.
Sitework
Sitework is included.
o Demolition of concrete paving.
o New building pad and concrete paving select fill.
Domestic water, fire water and sanitary utilities to within 5’ of the building are included to the
property line only.
Storm drainage system for the building is included per the drawings provided.
Concrete Paving & Sidewalks are included.
Termite treatment is included with a one year warranty which includes damage repair.
Landscaping and irrigation is not included.
Silt fence is included.
Temporary storm water piping is included to divert water from the building slab.
Dewatering of the elevator pit is included.
Rework of the existing fence is included at the allowance of $2,500.
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
Conerete
* Concrete building slab is included as a floating slab using 3000 psi concrete with rebar
reinforcing steel.
e Second floor slab is quoted as a 4” slab using 3000 psi concrete and 6 x 6 6/6 welded wire
fabric.
Masonry
e« CMU walls are included at the elevator shaft.
Metals
¢ Steel pan stairs (2 each) with railings to the second floor are included.
® Miscellaneous metals at the elevator tower are included.
e Elevator pit ladder is included.
Carpentry
*® Wood wall blocking is included for specialties.
« Casework is included per the drawings. Counter tops are quoted plastic laminate.
e Window sills are included.
Waterproofing
e Waterproofing for elevator pit is included.
Doors/Frames/Storefront
* Hollow metal frames, wood doors, and hardware are in this budget for the interior and exterior
openings. Electronic hardware for the access control is included.
Wood doors are rotary natural birch, 5 ply construction with a factory finish.
Door hardware will be keyed into the existing building and will match existing.
Sheriffs office is providing a bullet resistant view window at Reom101 to be installed by this
contractor.
e Exterior storefront windows are included as clear anodized aluminum storefront frames with
bronze or grey tint insulated glass.
Door lights are included per the drawings.
Access conirol system is included.
Finishes ;
e At exterior walls and masonry walls, 1.5 inch metal studs and one layer of 5/8” gypsum wall
board is included.
e All new interior walls are included using 3 5/8” metal framing and 5/8” gypsum board with
sound insulation.
e One hour fire walls are included at the east and west walls on the building between the stair
wells and the main building.
Gypsum board ceilings are included as indicated.
Acoustical ceilings are included as a standard 2x2 lay-in using Armstrong 1732 ceiling tile or
equal with insulation being laid 4 feet on each side of walls.
* Carpet flooring is included as Shaw !, Neyland-Neyland 2, 260z., unitary back — Color: Scotch |
Pine ~ or equal.
VCT is included as Mannington Essentials or Armstrong Excelion in standard colors.
Rubber base is included as Johnsonite 4” rubber base in standard colors.
Hard tile in the toilets for the floors and walls are included as follows:
o Wall Tile — Daltile Semi-Gloss/Matte Group 1.
o Floor Tile — Daltile Mosaic Colorbody Porcelain, Keystones, Groups 1 & 2, 2”x2”.
2
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
o Grout— TEC AccuColor Premium Grout.
« Painting of al! walls, ceiling, door frames, and doors is included as follows:
o HM Frames & Doors — 2 coats Sherwin