BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: October 6, 2015
TO: Honorable Chairman and Members of the Board
FROM: Sunil Harman
SUBJECT: Request approval of the contract with Environmental Management
Resources of Washington, Inc.
DEPARTMENT: Airport
BCC DISTRICT: 5
STATEMENT OF ISSUE: The Department of Airports requests the Board of County
Commissioners approve the contract with Environmental Management Resources of
Washington, Inc. (EMR, Inc.), for the construction of an Air Traffic Control Tower at the Destin
Executive Airport in the amount of $4,824,940.00 (RFB AP 60-15) and Resolution for Adoption
of the Air Traffic Control Tower (ATCT) Agreement.
BACKGROUND: On August 18, 2015, the Board of County Commissioners approved the
request presented by the Purchasing Department to award EMR, Inc., the contract for the
construction of the Air Traffic Control Tower at the Destin Executive Airport in the amount of
$4,824,940.00 (RFB AP 60-15). All federal, state and local relevant permits have been issued.
Staff has prepared the contract which has been coordinated per Okaloosa County policies and
procedures.
Funding for the project will be as follows: Florida Department of Transportation (FDOT)
$1,486,682; Federal Aviation Administration (FAA) $2,000,000; approved Passenger Facility
Charges (PFCs) $1,283,057; Local Match $55,201.
Previous Board action in support of the FAA Contract Air Traffic Control Tower:
November 7, 2006: Board approved FDOT JPA $400,000 for the ATCT
March 6, 2010: Board approved the FAA Tower Operating Agreement
October 16, 2012: Board approved TO 8 with RSH to prepare Environmental Assessment
December 4, 2012: Board approved FDOT SJPA for ATCT funding
March 19, 2013: Board update as to legislative trip - potential closure of 180 FAA ATCT
September 17, 2013: Board approved Task Order 13 with RSH to design & bid the ATCT
February 4, 2014: Board approved FDOT JPA for ATCT design & construction
July 7, 2014: Board approved FDOT SJPA for ATCT design
August 19, 2014: Board approved FAA AIP ATCT grant
October 7, 2014: Board approved rejection of all bids and re-bid
April 7, 2015: Board approved TO #2 with RSH to final design, bidding and CPS and:
1. A Resolution Authorizing Release of Phosphate and Mineral Rights for the mitigation
site
2. The Release of Phosphate and Mineral Rights
3. The Title Commitment
4. The Letter of No Encumbrance
5. The ATCT Wetland Mitigation Conservation Easement Area
6. A Unity of Title Documents
7. Closing Affidavit
OPTIONS: Approve/Reject or Table
RECOMMENDATIONS: It is Staff’s recommendation that the Board approve the contract
with EMR, Inc. for the construction of an Air Traffic Control Tower at the Destin Executive
Airport in the amount of $4,824,940.00 and Adoption of Resolution for agreement.
RECOMMENDED BY:
APPROVED BY:
John Hofstad, County Administrator