Preserved among the June 2, 2015 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1262). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used ; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
FEMAValidation
Date
June 2, 2015
Publisher
Okaloosa County Board of County Commissioners
Where to find it
8
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
FEMAValidation — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Federal Emergency Management Agency
To report suspected fraud, waste, or abuse, please call
FEMA's hotline at 1-800-323-8603.
Disaster recovery assistance is available without regard to race,
color, national origin, sex, age, religion, disability, or economic
status. Anyone who believes he/she has been discriminated
against should contact the FEMA Helpline at 1-800-525-0321.
Small Project Validation
Chapter 5
Small Project Validation
What is Small Project Validation?
A distinctive aspect of small project approval is the verification of
the accuracy of your claims by FEMA and/or State officials
through a process called validation. This process assures FEMA
that you understand the documentation and eligibility provisions
of the Public Assistance
Program and that you are
capturing all eligible costs.
Your records are the basis for
validation, which will be
limited to the minimum
amount of review needed to
ensure statutory and regulatory compliance.
• This will normally be 20%, barring significant discrepancies,
of all your small projects, for projects submitted within the
first 30 days after the Kickoff Meeting. Normally, projects
submitted after 30 days will be subject to 100% validation.
• Your PAC will schedule validation at a time convenient for
you, and you will be notified in advance which projects have
been selected. This will allow you to have the appropriate
records ready for review.
• Validation can normally be completed within 15 days of
submission of all Project Worksheets to the PAC.
How does it work?
The validation process begins when your Project Worksheets are
submitted to the PAC. The PAC will review each worksheet to
ensure the scope of work is complete and that all Special
Considerations have been identified. Once you have determined
that all small projects have been submitted, or a large batch of
projects has been submitted, you should notify the PAC to
proceed with validation. The PAC will request a Specialist from
the FEMA I State resource pool to conduct the validation. The
Federal Emergency Management Agency 41
Applicant Handbook
Small Project Validation
PAC, with input from the State, will select two samples from all
the small projects you have submitted. Each sample is made up
of 20% of the total small projects. If the first sample does not
pass validation, the Specialist will conduct a second validation
using the remaining sample. If an applicant has 4 or fewer
Project Worksheets, a minimum of 1 Project Worksheet will
always be validated.
What will the Specialist be looking for?
A Specialist will be assigned to conduct the validation and will
perform the following tasks:
• Visit the sites to confirm all aspects of
the project description are accurate,
complete and that all Special Considerations
have been identified.
• Confirm the damage description is
complete, accurate and eligible.
• Confirm the scope of work is complete,
accurate and eligible.
• Review all actual cost records to ensure
completeness, accuracy and eligibility.
• Review your cost estimate to ensure it
is complete, accurate, reasonable and eligible.
These tasks will require the Specialist to review the project
file including all cost records, computations,
measurements, notes, pictures, blueprints, plans,
environmental conditions, Special Considerations, and any
other documentation related to the project. You are
responsible for documenting all claimed costs. This is a
critical responsibility since undocumented costs could be
considered a variance and potentially put you over the
20% allowable variance
Only a preview is loaded on this record page. The linked reading pages contain the remaining text and work without JavaScript.
Citation & reuse
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — June 2, 2015 — FEMAValidation.” June 2, 2015. FEMAValidation. Crypt of Echoes evidence ID LED-2026-79e1251fb0c14d879e46812764d1d8b8. http://127.0.0.1:58097/evidence/LED-2026-79e1251fb0c14d879e46812764d1d8b8. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, FEMAValidation, meeting materials for June 2, 2015. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=4&ID=8354&MeetingID=1262
Preserved county public-record source. Third-party attachments may retain their original rights.