TOURIST DEVELOPMENT DEPARTMENT MEMORANDUM
DATE: July 21, 2016
TO: Tourist Development Council
FROM: Ed Schroeder, Tourist Development Department Director
Jim Trifilio, Coastal Management Coordinator
SUBJECT: FY 2017/18 Local Government Funding Request Submittal
STATEMENT OF ISSUE: Advising the Council of a FY 2017/18 Local Government Funding Request
application for design/permitting work associated with the construction of a sand trap for the East Pass
Federal Navigation channel.
BACKGROUND: The Florida Department of Environmental Protection, Division of Water Restoration
Assistance, is accepting funding requests from Florida Local Governments for the FY 2017-2018 Beach
Management Funding Assistance Program. This includes funding assistance for inlet management as
well.
East Pass channel requires maintenance dredging approximately every 3-4 years in order to allow vessels
access to the Gulf of Mexico. This dredging is very costly and is in the range of $2-$4 million per dredge
event. The time between these dredging events can be lengthened with the design and construction of a
sand trap. The purpose of the sand trap is to provide additional area within the channel for sand deposition
without significantly decreasing the depth of the channel. Potential savings from decreased dredging
requirements would be considerable. Additionally, the sand trap would provide the highest quality sand
for beach restoration utilizing an in-shore, economical source.
It is estimated that the cost of the design/permitting work will be approximately $500,000. Funding
assistance from the State would require a 50/50 match with the local sponsor. The County’s $250,000
match would be provided by the Tourist Development Tax and is included in the Tourist Development
Department's proposed budget for FY17.
The application will be ranked against other projects around the State that are seeking funding. If the
County’s application ranks high enough to be funded, a grant agreement will be brought back at a later
date. Due to the application deadline of August 1, the application was presented to the Board for approval
on July 19.
OPTIONS: N/A – for informational purposes only.
RECOMMENDATION TO BCC: N/A – for informational purposes only.
FY 2017/18 Local Government Funding Request
Okaloosa County Inlet Management Project
Project Name: East Pass Sediment Impoundment Basin – Design and Permitting
Project Description: The project will develop and apply numerous numerical (MIKE) models
to evaluate various sediment impoundment basin design alternatives in East Pass to facilitate
bypassing of sediment to the adjacent beaches. The project scope includes the alternatives
evaluation and the design and permitting (including state and federal permits) of the recommended
basin alternative. The project will comply with the Department’s East Pass Inlet Management
Implementation Plan (IMIP), specifically the final strategy to investigate availability and feasibility
of supplemental inlet sediment excavation outside the federal navigation channels to help mitigate
gulf beach erosion that exceeds the bypassing quantities obtained from maintenance of the federal
navigation channels
County: Okaloosa
Range Monuments: NA (Immediately west of R-17)
Location:
East Pass is located adjacent to Destin, FL, approximately 45 miles east of Pensacola and
approximately 50 miles northwest of Panama City. Separating Santa Rosa Island to the west and
Moreno Point to the east, East Pass is a structured inlet that provides direct tidal link between the
Gulf of Mexico and Choctawhatchee Bay.
Project History:
The East Pass Federal navigation channel requires frequent maintenance dredging to alleviate
shoaling of sediment within the channel. The East Pass Maintenance Dredging is authorized by
joint coastal permit number 0288799-001-JC, issued to the U.S. Army Corps of Engineers
(USACE) October 2009 and expires October 2019. East Pass navigation channel (maintenance)
dredging is also authorized by 0288799-003-JC, which was recently issued to the City of Destin in
February 2015 and expires in February 2030. Both permits authorize maintenance dredging within
the federal navigation channels that extend from approximately 3,500 ft south of the inlet jetties
northward past the US98 Bridge into Choctawhatchee Bay. The permits also authorize maintenance
dredging within the Destin Harbor (Old Pass Lagoon) entrance channel.
The updated and adopted inlet management plan (2010) reports that the USACE has dredged
2,352,600 cy of material from east pass since 1986. The frequency of dredging ranges between one
and three years, with a historic, average annual dredge rate of approximately 98,000 cy/year.
Notably, federal and budget constraints have since eliminated Operations and Maintenance
dredging operations of non-deepwater ports, removing East Pass and Destin Harbor from the
USACE project list.
Following Implementation Strategy #4 of the East Pass Inlet Management Implementation Plan
(2013), current project aspirations are to design and permit sediment impoundment basins (“sand
traps”) to reduce the maintenance dredging frequency of the East Pass federal navigation channels
and increase the volume of beach-quality sand available to the Gulf coast beaches. From the
Implementation Plan: “Implementation Strategy #4 initiates greater flexibility in the future
management of East Pass. Continued Congressional appropriations for the maintenance of the
federal navigation project are not guaranteed. Also, a planned channel maintenance dredging
project might not even provide a sufficient quantity of sand to balance the sediment budget with
adjacent eroding beaches. Additional inlet excavation outside the authorized channels may be
warranted. A problem inherent with the existing natural channel alignment is the eastward
migration of the channel against the east jetty spur. Between the channel and the west jetty is a
developing shoal. The reduced depth and cross-sectional flow area of this shoal within the inlet
inhibits tidal flow resulting in an increased flow within the channel. This increased flow has caused
scour to depths in excess of 50 feet at the jetty spur. Removal of this interior shoal would improve
the hydrodynamic conditions between the inlet jetties as well as make available sediment for the
adjacent eroding beaches. The concept of dredging interior inlet sediment catch basins or sand traps
has been successfully implemented at other inlets in Florida to improve inlet sand transfer.
Implementation Strategy #4 would induce the cooperative effort between the department and a
local sponsor to conduct the necessary feasibility study and engineering design to facilitate
dredging interior inlet shoals.” Finally, the proposed project will provide significant costs savings
to the local, state and federal governments by: 1) reducing the frequency of maintenance dredging
and, 2) provide a high-quality sand source for future beach restoration events immediately adjacent
to existing (permitted) Western Destin beach project area, eliminating the costly need to obtain
beach-quality sand from distant, offshore borrow areas.
Upcoming Activities:
Norriego Point Stabilization
Utilizing NRDA funds and following the recommendations of the FDEP East Pass
IMP Implementation Plan (Strategy #3), the City of Destin is working in close
coordination with the State to stabilize critically eroded Norriego Point, which
separates Destin harbor from East Pass. The project consists of shoreline
stabilization structures and shoreline restoration (sand placement) to provide storm
protection to Destin Harbor and reduce maintenance dredging frequency within
this area of East Pass. The project will greatly reduce frequency of emergency
dredging requirements and allow the USACE and/or City of Destin to place a
greater volume of material from channel maintenance dredging events onto
adjacent eroding beaches.
Use of Requested Program Funds:
Funds are requested to accomplish Implementation Strategy #4 of the East Pass Inlet Management
Implementation Plan to reduce the maintenance dredging frequency of the East Pass federal
navigation channel and increase the volume of sand available to the adjacent gulf coast beaches.
Specifically, the County proposes to investigate management solutions that include the
implementation of sediment impoundment basins (sand traps), and channel re-
alignments/widening. The study will require the collection of current and wave data, literature
review, hydrodynamic/wave/sediment transport modeling, and final alternatives analysis.
Extensive numerical modeling will assess potential effects of the management alternatives and
provide the data to make specific management recommendations for East Pass.
Maintenance of the East Pass channel is necessary for public recreational opportunity as well as
charter boat captains and commercial fisherman, which provide significant economic benefit to the
surrounding area. The proposed study will provide recommendations to reduce East Pass
maintenance dredging, thus reducing federal costs, and provide additional sand to adjacent beaches
potentially reducing City, County, and State costs.
Local Government Contact:
Name Title Email
Jim Trifilio Coastal Management Coordinator, jtrifilio@co.okaloosa.fl.us
Okaloosa County Tourist Development Council
Address 1540 Miracle Strip Parkway SE Phone: (850) 651-7131
Fort Walton Beach, FL 32548 Fax:
Mapping- Maps should be provided as attachments.
Mapping elements include:
□ Project Boundary with Inlet, area of inlet influence and Critically Eroded Shoreline
□ Range Monuments
Length of Area of Inlet Influence in Feet (As Determined by IMP or SBMP): 20,000 ft
Length of area of inlet influence ranges from 6,000-ft to 12,000-ft contingent on selected time
period and storm events. These values are in reference to the 1999 (original) and the 2010 (updated)
East Pass Inlet Management Plans. The adopted 2013 Inlet Management Implementation Plan cites
“the area direct inlet impact was determined to be approximately 10,000 feet to the east and west
of East Pass.”
Schedule and Budget:
(Include estimated phases for 10 years and estimated project costs for 5 years.)
Proposed Estimate Project Costs ($1,000’s)
Year Description
Phase Total Federal State Local
Feasibility 0 0 0 0
Alternatives analysis,
2017/ 500 0 250 250
Design & Permitting design, and permitting
2018
Construction
Monitoring
Feasibility
Design & Permitting
2018/
Contract docs & bid
2019
Construction admin
Monitoring
Feasibility
2019/ Design & Permitting
2020 Construction Basin Construction
Monitoring Physical
Feasibility
2020/ Design & Permitting
2021 Construction
Monitoring Physical
Feasibility
2021/ Design & Permitting
2022 Construction Sand bypassing
Monitoring Physical