Preserved among the December 6, 2016 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1366). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used September 20, 2016; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Cost Estimate
Date
December 6, 2016
Publisher
Okaloosa County Board of County Commissioners
Where to find it
1
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
Cost Estimate — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
11/22/2016
OCWS Preliminary Cost Estimate
Newport/Essex Area Water System Improvements
Line No. Line Item Quantity Unit Unit Price Total
Material
1 6" PVC C‐900 DR18 3928 LF $5.00 $19,640
2 4" PVC C‐900 DR18 432 LF $4.00 $1,728
3 2" PVC C‐900 DR18 390 LF $3.00 $1,170
4 6" DIP 783 LF $10.00 $7,830
5 fire hydrant assembly (tee to hydrant, including fittings, GV) 6 EA $2,200.00 $13,200
6 flush hydrant assembly (tee to hydrant, including fittings, GV) 3 EA $1,000.00 $3,000
7 6" water main connection (includes tap sleeve & tap valve) 4 LS $1,450.00 $5,800
8 6" Gate Valve 4 EA $630.00 $2,520
9 DI pipe fittings 1 LS $51,370.00 $51,370
10 seeding & mulching 3 AC $200.00 $600
11 erosion control: silt fence 1 LS $5,000.00 $5,000
12 Concrete (driveways & sidewalks) 83 CY $88.00 $7,304
13 8" HDPE DR‐11 Directional Bores 486 LF $45.68 $22,200
14 2" HDPE DR‐11 Directional Bores 50 LF $10.00 $500
15 8" bore transition fittings 8 pair $920.64 $7,365
TOTAL MATERIALS $149,228
Labor/Equipment
16 OCWS in‐house labor (includes fringe) 72 days $2,150.00 $154,800
17 OCWS in‐house equipment (includes maintenance) 72 days $1,700.00 $122,400
TOTAL LABOR/EQUIPMENT $277,200
Subcontracted Work
18 asphalt pavement patches 525 SF $4.00 $2,100
TOTAL SUBCONTRACTED WORK $2,100
19 10% contingency $42,853
TOTAL PROJECT exact $471,380
rounded $472,000
Notes:
1. This cost estimate is based on 90% plans.
2. Labor assumes work occurs during normal business hours on Monday through Thursday.
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — December 6, 2016 — Cost Estimate.” December 6, 2016. Cost Estimate. Crypt of Echoes evidence ID LED-2026-542f443091e8434f9e2702609e1b2c20. http://127.0.0.1:58097/evidence/LED-2026-542f443091e8434f9e2702609e1b2c20. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, Cost Estimate, meeting materials for December 6, 2016. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=4&ID=13263&MeetingID=1366
Preserved county public-record source. Third-party attachments may retain their original rights.