Okaloosa County BOCC — December 31, 2012 — Construction Timeline 11 26 12 — reading text

Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.

Machine-extracted text — 83-Construction Timeline 11 26 12.pdf

Machine-extracted OCR text · Review label: Machine produced / unreviewed

Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.

Destin Airport RWY 14-32 Rehab 26-Nov-12 10:58 Schedule as of 13-Nov-12 Activity ID Activity Name Original Remaining Activity % Start Finish Total November 2012 December 2012 January 2013 February 2013 March 2013 pril 2013 Duration Duration Complete Float 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 Phase 1 - Preconstruction Activities Activi 11-Jan-13, Phase 1 - Preconstruction Activities G1000 Notice To Proceed 0d 0d 0% 13-Nov-12 -1d Notice To Proceed G1010 Submittals 49d 49d 0% 13-Nov-12 11-Jan-13 81d Submittals G1012 Lighting Submittals 10d 10d 0% 13-Nov-12 28-Nov-12 -1d Lighting Submittals G1020 Temp Office Trailer 10d 10d 0% 29-Nov-12* 12-Dec-12 58d Temp Office Trailer A1000 Mobilize Electrical 10d 10d 0% 29-Nov-12 12-Dec-12 48d Mobilize Electrical G1014 Produce Lights (5 week lead time) 25d 25d 0% 29-Nov-12 11-Jan-13 -1d Produce Lights (5 week lead time) G1030 Locate Existing Airfield Utilities 10d 10d 0% 13-Dec-12 04-Jan-13 48d Locate Existing Airfield Utilities Phase 2 - 23 Days Night Time Only On 04-Feb-13, Phase 2 - 23 Days Night Time Only B0990 Precast Light Base 5d 5d 0% 07-Jan-13 11-Jan-13 35d Precast Light Base B1000 Install Conduit 20d 20d 0% 12-Jan-13 01-Feb-13 -1d Install Conduit B1010 Directional Bore Conduit 3d 3d 0% 12-Jan-13 14-Jan-13 78d Directional Bore Conduit B1020 Pull Wire 5d 5d 0% 28-Jan-13 01-Feb-13 -1d Pull Wire B1030 Set Base for Lights/Signs 15d 15d 0% 28-Jan-13 04-Feb-13 -1d Set Base for Lights/Signs Phase 3 - 7 Day Runway Closure 11-Feb-13, Phase 3 - 7 Day Runway Closure C1000 Close Runway - 7 Days 0d 0d 0% 04-Feb-13 -1d Close Runway - 7 Days C1010 Mill Existing Runway 4d 4d 0% 04-Feb-13 06-Feb-13 -1d Mill Existing Runway B1040 Install Lights/Signs 10d 10d 0% 04-Feb-13 08-Feb-13 39d Install Lights/Signs B1060 Demo Old Lighting 10d 10d 0% 04-Feb-13 08-Feb-13 41d Demo Old Lighting C1020 Layout - Paving 4d 4d 0% 05-Feb-13 07-Feb-13 -1d Layout - Paving C1060 Dress Runway Shoulders 6d 6d 0% 06-Feb-13 08-Feb-13 37d Dress Runway Shoulders C1030 Pave Leveling Course 4d 4d 0% 07-Feb-13 08-Feb-13 -1d Pave Leveling Course C1070 Sod Runway Shoulders 4d 4d 0% 08-Feb-13 09-Feb-13 37d Sod Runway Shoulders B1050 Test New Light System 2d 2d 0% 08-Feb-13 08-Feb-13 39d Test New Light System C1040 Pave Surface Course 4d 4d 0% 08-Feb-13 09-Feb-13 -1d Pave Surface Course C1050 Install Temp Striping 4d 4d 0% 09-Feb-13 11-Feb-13 33d Install Temp Striping C1080 Survey Finished Surface 1d 1d 0% 09-Feb-13 10-Feb-13 35d Survey Finished Surface C1090 Open Runway 0d 0d 0% 11-Feb-13 33d Open Runway Phase 4 - 35 Day Cure/Final Striping Strip 18-Mar-13, Phase 4 - 3 D1000 30 Day Asphalt Cure 30d 30d 0% 09-Feb-13 11-Mar-13 -1d 30 Day Asphalt Cure D1010 Haul Off Millings 10d 10d 0% 11-Feb-13 25-Feb-13 6d Haul Off Millings D1020 Cleanup Stockpile Area 7d 7d 0% 26-Feb-13 06-Mar-13 6d Cleanup Stockpile Area D1030 Regrass Stockpile Area 1d 1d 0% 07-Mar-13 07-Mar-13 6d Regrass Stockpile Area D1040 Apply Final Paint Application to Runw 5d 5d 0% 12-Mar-13 18-Mar-13 -1d Apply Final Paint Applic D1050 Final Completion 0d 0d 0% 18-Mar-13 -1d Final Completion Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities Remaining Work Milestone © Primavera Systems, Inc.

Download this text file with its original spacing ↓