Construction Timeline 11 26 12 from the Okaloosa County BOCC meeting of December 31, 2012 (IQM2 meeting #1101). Original portal label: Construction Timeline 11 26 12. Preserved as a historical public record; part of the meeting linked as a related source.
- Original publication
- Construction Timeline 11 26 12
- Date
- December 31, 2012
- Reference collection
- Okaloosa County Board of County Commissioners (IQM2 public portal)
View reference catalogue / source ↗
Download this source
Construction Timeline 11 26 12 (PDF)
Original PDF as published on the Okaloosa County IQM2 meeting portal.
PDF · 0.1 MB
Download ↓Machine-extracted text — 83-Construction Timeline 11 26 12.pdf
Text extracted on 2026-10-29 from 83-Construction Timeline 11 26 12.pdf using the PDF text layer (pdftotext). Not human-corrected; may contain recognition errors. Read alongside the source images.
File · 0.0 MB
Download ↓
Full text
Machine-extracted from the source by optical character recognition. Not yet human-corrected — it may contain recognition errors. Read it alongside the images above.
Destin Airport RWY 14-32 Rehab 26-Nov-12 10:58
Schedule as of 13-Nov-12
Activity ID Activity Name Original Remaining Activity % Start Finish Total November 2012 December 2012 January 2013 February 2013 March 2013 pril 2013
Duration Duration Complete Float
05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01
Phase 1 - Preconstruction Activities
Activi 11-Jan-13, Phase 1 - Preconstruction Activities
G1000 Notice To Proceed 0d 0d 0% 13-Nov-12 -1d Notice To Proceed
G1010 Submittals 49d 49d 0% 13-Nov-12 11-Jan-13 81d Submittals
G1012 Lighting Submittals 10d 10d 0% 13-Nov-12 28-Nov-12 -1d Lighting Submittals
G1020 Temp Office Trailer 10d 10d 0% 29-Nov-12* 12-Dec-12 58d Temp Office Trailer
A1000 Mobilize Electrical 10d 10d 0% 29-Nov-12 12-Dec-12 48d Mobilize Electrical
G1014 Produce Lights (5 week lead time) 25d 25d 0% 29-Nov-12 11-Jan-13 -1d Produce Lights (5 week lead time)
G1030 Locate Existing Airfield Utilities 10d 10d 0% 13-Dec-12 04-Jan-13 48d Locate Existing Airfield Utilities
Phase 2 - 23 Days Night Time Only
On 04-Feb-13, Phase 2 - 23 Days Night Time Only
B0990 Precast Light Base 5d 5d 0% 07-Jan-13 11-Jan-13 35d Precast Light Base
B1000 Install Conduit 20d 20d 0% 12-Jan-13 01-Feb-13 -1d Install Conduit
B1010 Directional Bore Conduit 3d 3d 0% 12-Jan-13 14-Jan-13 78d Directional Bore Conduit
B1020 Pull Wire 5d 5d 0% 28-Jan-13 01-Feb-13 -1d Pull Wire
B1030 Set Base for Lights/Signs 15d 15d 0% 28-Jan-13 04-Feb-13 -1d Set Base for Lights/Signs
Phase 3 - 7 Day Runway Closure 11-Feb-13, Phase 3 - 7 Day Runway Closure
C1000 Close Runway - 7 Days 0d 0d 0% 04-Feb-13 -1d Close Runway - 7 Days
C1010 Mill Existing Runway 4d 4d 0% 04-Feb-13 06-Feb-13 -1d Mill Existing Runway
B1040 Install Lights/Signs 10d 10d 0% 04-Feb-13 08-Feb-13 39d Install Lights/Signs
B1060 Demo Old Lighting 10d 10d 0% 04-Feb-13 08-Feb-13 41d Demo Old Lighting
C1020 Layout - Paving 4d 4d 0% 05-Feb-13 07-Feb-13 -1d Layout - Paving
C1060 Dress Runway Shoulders 6d 6d 0% 06-Feb-13 08-Feb-13 37d Dress Runway Shoulders
C1030 Pave Leveling Course 4d 4d 0% 07-Feb-13 08-Feb-13 -1d Pave Leveling Course
C1070 Sod Runway Shoulders 4d 4d 0% 08-Feb-13 09-Feb-13 37d Sod Runway Shoulders
B1050 Test New Light System 2d 2d 0% 08-Feb-13 08-Feb-13 39d Test New Light System
C1040 Pave Surface Course 4d 4d 0% 08-Feb-13 09-Feb-13 -1d Pave Surface Course
C1050 Install Temp Striping 4d 4d 0% 09-Feb-13 11-Feb-13 33d Install Temp Striping
C1080 Survey Finished Surface 1d 1d 0% 09-Feb-13 10-Feb-13 35d Survey Finished Surface
C1090 Open Runway 0d 0d 0% 11-Feb-13 33d Open Runway
Phase 4 - 35 Day Cure/Final Striping
Strip 18-Mar-13, Phase 4 - 3
D1000 30 Day Asphalt Cure 30d 30d 0% 09-Feb-13 11-Mar-13 -1d 30 Day Asphalt Cure
D1010 Haul Off Millings 10d 10d 0% 11-Feb-13 25-Feb-13 6d Haul Off Millings
D1020 Cleanup Stockpile Area 7d 7d 0% 26-Feb-13 06-Mar-13 6d Cleanup Stockpile Area
D1030 Regrass Stockpile Area 1d 1d 0% 07-Mar-13 07-Mar-13 6d Regrass Stockpile Area
D1040 Apply Final Paint Application to Runw 5d 5d 0% 12-Mar-13 18-Mar-13 -1d Apply Final Paint Applic
D1050 Final Completion 0d 0d 0% 18-Mar-13 -1d Final Completion
Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities
Remaining Work Milestone © Primavera Systems, Inc.