READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — December 31, 2012 — Action Item Printout — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 82-Action Item Printout.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: December 4, 2012
TO: Honorable Chairman and Members of the Board
FROM: Greg Donovan
SUBJECT: Destin Airport Runway Construction
DEPARTMENT: Airport
BCC DISTRICT: All
The Airports Director will brief the BCC on the tentative construction schedule for the
runway project at Destin Airport (DTS).
The project will entail twenty-three nightly closures of the airport from 1800 hours local
time (6:00 PM) to 0600 hours local time (6:00 AM) beginning January 7, 2013 until
January 28, 2013.
Complete closure of the airport is required for seven days beginning February 4, 2013 until
February 11, 2013.
The project is expected to be completed by March 18, 2013. Construction timeline is
attached.