pleted hundreds of local projects. The map below shows just a few of the projects Lord & Son has completed in
the Fort Walton Beach/Shalimar area, but Lord & Son projects can be found all over the county, all the way
from Crestview to Destin. )
NWF Regional Airport Eastside
Development
wot
a?
yenis Tumer Blvd OF
(ies)
[Garpiier Bayou
May flow.
(hus) Cinco Bayou
ie
(1838)
|} Fort Walton Beach ugh:
Emerald Coast Conference
: [ ; Center
Calvary Baptist Church
) (as
Community Building) i
¢
& if =
y indian Temple
ound Museum
Pomme
FWB Recreation /
Center Jobsite /
Page 29
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEW OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
LOCAL PROJECT EXPERIENCE
Renovations to Building 810 (Gym) at Eglin AFB, FL
Lord & Son provided Design/Build services for the
renovation of Building 810, the main fitness center for
Eglin Air Force Base. The building had to remain open
to the public at all times during construction, so
renovation had to be performed in phases.
The renovations to the 1970s building included minor
demolition of finishes in the lobby area, as well as
offices and locker rooms. All new finishes (flooring,
ceilings, painting) were installed, as well as much
improved sound attenuation, surveillance system, fire
alarm, and sauna duress alarms. Some new
penetrations were required at masonry exterior walls
that took advantage of a strong concrete structural
system. Selective interior demolition involved non-
load bearing interior partition in administrative office
areas and the men’s locker room. Several new
Openings were made through existing block walls. A
new mechanical room with exterior doors was built on
the west side of the building, occupying approximately
11’-0” x 20’ to house new mechanical equipment and
upgrades.
The new utility systems were designed around energy
efficient equipment. All light fixtures had energy
efficient ballasts and bulbs, and the HVAC system was
chilled water with DDC controls. Plumbing _ fixtures
were replaced with low flow models, and the hot
water system balances flow and temperature to
maximize economy. All common areas were equipped
with emergency lighting, TV monitors, and oscillating
fans. The entire interior was renovated to modern
standards and was designed with high strength - low
maintenance materials to provide lasting service.
Project Team:
Project Manager: Ryan Chavers
Project Superintendent: Todd Powell
Page 30
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEw OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
Construction Cost:
At Award: $1,505,100.00
Final Cost: $1,597,368.00
Reason for the cost growth: Owner requested modifications.
Construction Dates:
Start Date: September 26, 2011
Final Completion: April 1, 2013
Owner:
96 AAC/PKOA, Department of the Air Force
308 West D Avenue
Eglin AFB, FL 32542
Ms. Marina Hobson
850-882-0245 (P)
850-882-1680 (F)
marina.hobson @eglin.af.mil
Architect:
DC Architects, Inc.
139 Beal Parkway, Suite 101
Fort Walton Beach, FL 32548
850-433-8632 (P)
850-226-8565 (F)
dchavez@dcarchitects.com
Page 31
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
New OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
LOCAL PROJECT EXPERIENCE
Additions and Renovations to Crestview High School in Crestview, FL
we be. &, _
Lord & Son was the General Contractor for the new construction of a 28,000 square foot five classroom
addition and 12,500 square foot addition and new construction to the existing Field House to include a new
weight room, locker room, team rooms, and coach offices. The classroom addition also included the
renovation of the existing weight room that was converted into three new classrooms and office space for
teachers. The project included typical school interior and exterior finishes (painted CMU, gyp board, ceramic
tile and epoxy flooring in the bathroos, VCT floors throughout the balance). The exterior was a mixture of
brick over load-bearing masonry, painted exposed CMU, and metal framing with EIFS. The roofing system was
composed of standing seam metal roofing on all new construction with Tremco roofing products on all
existing and connecting construction. The mechanical systems were DX HVAC systems with 100% Outside Air
Units—package rooftop units for the Field House and split ground systems for the five classroom addition.
The work began in November and had to be complete and ready for the start of the next school year. The
work was phased. Equipment/material deliveries had to be scheduled around the arrival and departure of the
buses each day because the site was within the bus loop, and we could not block the loop in the mornings
from 6:45 am to 7:30 am or in the afternoons from 2:00 pm to 2:30 pm. We had to schedule out concrete
deliveries to coincide with the school traffic. We were able to complete the various phases and had all the
rooms ready for occupancy prior to the start of the school year—four days ahead of schedule.
Page 32
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEW OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
Project Team:
Project Manager: Ryan Chavers
Project Superintendent: Hiram Atwell
Construction Cost:
At Award: $1,685,100.00
Final Cost: $1,742,522.00
Reason for the cost growth: Owner requested
changes.
Construction Dates:
Start Date: October 26, 2007
Final Completion: July 25, 2008
Owner:
Okaloosa County School Board, Represented by Jacobs/Titan
120 Lowery Place
Fort Walton Beach, FL 32548
Mr. Joel Lindner
850-897-6199 (P)
850--897-0123 (F)
joel.lindner@jacobs.com
Architect:
Jacobs/Titan
1501 Merchants Way
Niceville, FL 32578
850-897-6199
Page 33
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEW OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF’S OFFICE IN SHALIMAR
LOCAL PROJECT EXPERIENCE
First United Methodist Church Children’s Education Building in Niceville, FL
Lord & Son provided General Contractor services to construct this two-story 32,000 square foot building to
house the church’s preschool and Sunday School programs. The building includes 25 classrooms, 10 re-
strooms, children’s worship area, theater/stage, three separate lobby areas, indoor playground, and support
spaces. Exterior construction is concrete block with steel beams and columns, metal roof panels with steel
roof beam system, and brick veneer.
Interior finishes include gypsum sheetrock, bamboo wainscoting/chair rail, fabric awnings, thatched roofing,
and carpet and ceramic tiles. Additional unique interior finishes feature porthole wood doors and extensive
wall coverings by Wacky World of Orlando. The underwater —themed first floor depicts a lifelike submarine,
dolphins, and sharks swimming overhead, while the dockside-themed theater and classrooms are on the sec-
ond floor.
Hydraulic elevator, fire sprinkler, alarm systems, HVAC system, covered driveway and walkways, landscaping,
and sprinkler system round out the project.
The entire building was built to provide a safe and secure place to grow and learn. Security cameras, entrance
and exit monitoring, and computerized sign-in/dismissal program allow children to move throughout the
building while maintaining a high level of safety.
Page 34
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEW OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
Project Team:
Project Manager: John Klumpp
Project Superintendent: Ronnie Jordan
Construction Cost:
At Award: $5,736,600.00
Final Cost: $5,986,026.00
Reason for the cost growth: Owner
requested changes
Construction Dates:
Start Date: July 3, 2008
Final Completion: August 23, 2009
Owner:
First United Methodist Church
214 S. Partin Drive
Niceville, FL 32578
Mr. John Macon
850-443-4411 (P)
850--678-2222 (F)
jmacon@nicevilleumc.com
Architect:
Quina Grundhoefer Royal Architects
400 West Romana Street
Pensacola, FL 32501
850-433-5575 (P)
850-433-5366 (F)
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
New OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
LOCAL PROJECT EXPERIENCE
Northwest Florida Regional Airport Eastside Development at Eglin AFB, FL
Lord & Son provided General Contracting services (Prime Contractor) for this 22 acre development which
included a 130,000 gallon fuel farm, five buildings (a 38,000 square foot rental car administrative/
maintenance building, fuel islands and tenant storage building, a 5000 square foot 5-bay automatic car wash,
a fuel operator shed and fuel tank storage area, a 12,800 square foot cargo and maintenance facility with 10
car lifts), parking lots, public and private roads, extensive site utilities, landscaping, security cameras, and
access control systems.
This project was the recipient of the 2009 ABC Eagle Award for Excellence in Construction in the GC/CM Insti-
tutional $10 - $20 Million category and ABC Gold Level STEP (Safety Training and Evaluation Process) Award.
Project Team:
Project Manager: John Klumpp
Project Superintendent: Jack Harris
Construction Cost:
At Award: $14,728,600.00
Final Cost: $15,037.560.00
Reason for the cost growth: Owner requested changes.
Page 36
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
New OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
Construction Dates:
Start Date: January 7, 2008
Final Completion: July 6, 2009
Note: Final changes were issued for revisions to the fuel farm late in the schedule, which required
waiting for County Board approval, delaying start and completion of these extensive changes.
Owner:
NWF Regional Airport
State Road 85
Eglin AFB, FL 32542
Mr. Tracy Stage, Airports Project Manager
850-651-7160, ext. 4 (P)
850-651-7164 (F)
tstage@co.okaloosa.fl.us
Architect:
LPA Group
1320 Executive Center Drive, Suite 100
Tallahassee, FL 32301
850-205-0460 (P)
850-205-0451 (F)
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
New OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
LOCAL PROJECT EXPERIENCE
Beach Community Bank in Crestview, FL
Lord & Son provided General Contractor services for this one-story, 6,159 square foot banking facility. Con-
struction consisted of load bearing masonry with metal bar joists, standing seam metal and single-ply roof,
and stucco and hardiboard lap siding exterior finish. Interior finishes included carpet, ceramic tile, VCT, gran-
ite countertops, gypboard, and tongue and groove wood paneling. This project required coordination of own-
er-provided bank equipment, which included bank teller trays, pneumatic tube system, vault, ATM, and secu-
rity system.
Complete site development and landscaping was required. Work included the installation of cast-in place
concrete retaining wall, lift station and force main, installation of new traffic signal and turning/deceleration
lane. Irrigation system included installation of new pump and well.
Special features included a force main with grinder pump and jack/bore utilities under State Highway 85.
Bid documents called for the building pad to be prepared by the owner’s forces; however, the work was
found to be substandard and had to be removed and reinstalled. Lord & Son completed the remedial work in
a fast-track method in order to minimize impact to the project schedule and reduce costs to the owner. The
project was completed six days ahead of schedule. Attention to detail during the construction process result-
ed in a minimal punch list that was completed and signed off by the owner within one week.
Page 38
STATEMENT OF QUALIFICATIONS
CONSTRUCTION MANAGEMENT SERVICES
NEW OFFICE BUILDING AT THE OKALOOSA COUNTY SHERIFF'S OFFICE IN SHALIMAR
Project Team:
Project Manager: Mike O’Grady
Project Superintendent: Todd Powell
Construction Cost:
At Award: $1,865,200.00
Final Cost: $2,150,132.00
Reason for the cost growth: