EAST COUNTY PREVIOUS BOARD ACTION — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Request to solicit quotes in lieu of formal bids for the purchase of pipe and associated fitti... Page 1 of 3
Okaloosa County
Florida
P Action Item
ipw”* 1335
VIII.2.a Request to solicit quotes in lieu of formal bids for the purchase of pipe
and associated fittings for the East County/Eglin Master Sewer Plan. District: All.
Information
Department: Water and Sewer Sponsors:
Category: Approval
Attachments
Printout
East County Master Sewer Plan_Pagel
East County Master Sewer Plan_Page2
Body
STATEMENT OF ISSUE: OCWS staff requests BCC approval to authorize the Purchasing
Department to solicit quotes by phase in lieu of formal bids for the purchase of pipe and associated
materials for the East County/Eglin Master Sewer Plan, at the appropriate time during the procurement
process of each phase.
BACKGROUND: OCWS has several construction projects scheduled in the East County/Eglin area
in the immediate future and the next few years. For the purposes of construction scheduling and
material procurement, we have put together a 10-phase plan that encompasses all these projects. All
projects are either currently in OCWS' 5-year CIP or are funded by Eglin AFB. The phases/projects
are depicted on the attached aerial photos and listed as follows:
- Phases 1-4 - Rocky Bayou 16" Force Main
- Phase 5 - Eglin Main Base Wastewater (Main Base Lift Station, Plew Lift Station,
approximately 3.6 miles of 24" force main, approximately 3.8 miles of 16" force main, and
conduit/fiber)
- Phase 6 - Replace 10" Force Main at Canal with 16" Force Main
- Phase 7 - Replace Meigs-Seminole Lift Station
- Phase 8 - Hwy 20 12" Force Main (approximately 1 mile, from Lancaster Drive to Range
Road)
- Phase 9 - College Blvd Re-Pump Station
- Phase 10 - NVOC Force Main (approximately 6.7 miles; 16" preliminary diameter)
The above-mentioned projects will achieve 4 primary goals and objectives of the department:
I Complete the Eglin Main project by the contract date, which is very aggressive
(12/31/2013).
http://okaloosacountyfl.igm2.com/Citizens/Detail _LegiFile.aspx?ID=1335&highlightTerm... 2/19/2015
Request to solicit quotes in lieu of formal bids for the purchase of pipe and associated fitti... Page 2 of 3
2. Complete Eglin Main project ASAP, because this project will be revenue producing.
3. Abandon the Post Office Lift Station, Rocky Bayou Lift Station, and the aging 14" force
main.
4. Divert all East County flow from NVOC WWTP to the Arbennie Pritchett WRF in order
to save significantly on O&M expenses.
Construction of Phases 1-4 (Rocky Bayou Force Main) are already substantially complete, and the
BCC has already approved quotes in lieu of bids for the piping/appurtenances for the material
procurement. The other phases are in surveying, design, or permitting. OCWS and Purchasing staffs
have met to discuss procurement strategy for the remaining phases. On the complex items, such as lift
stations, we feel that the formal bid process is absolutely necessary. On more straightforward items
like pipe and miscellaneous appurtenances, we feel the most economical approach would be to solicit
quotes in lieu of bids. Historically, the same vendors will provide pricing whether it is quotes or a
formal bid process. Because quotes are a competitive process, OCWS and Purchasing believe the
prices will come in under the budgeted amounts. In addition, obtaining quotes instead of bids allows
for a quicker, more streamlined process. In many of these projects, time is of the essence, because of
the above-mentioned goals and objectives. Therefore, OCWS and Purchasing staff request to solicit
quotes in lieu of bids for any piping and miscellaneous appurtenances (valves, manholes, conduit, etc.)
for Phases 5-10. We are asking that quotes be solicited at the appropriate time for each project in the
next 2-3 years. In addition, for any in-house construction projects over $300,000, we will set up
Public Meetings per Florida Statutes to request BCC approval for self performance. This will be done
project by project in the future.
Regarding the budget, Phase 5 is funded by Eglin AFB. In budget years FY2013 & FY2014, a total of
$1,700,000 is budgeted for Phases 6-8. In budget years FY2012 (rollover), FY2013, and FY2014, a
total of $4,500,000 is budgeted for Phases 9-10.
OPTIONS: Approve or Deny.
RECOMMENDATIONS: Staff recommends BCC authorization for the Purchasing Department to
solicit quotes and to then proceed with the (award) purchase from the lowest responsive and
responsible quoter in order to save money and time on the purchase of pipe and miscellaneous
appurtenances for the East County/Eglin Master Sewer Plan.
Meeting History
Board of County Regular Meeting P. Draft
Feb 5, 2013 8:30 AM Video " - (North)
RESULT: ADOPTED [UNANIMOUS]
MOVER: Nathan Boyles, Commissioner, District 3
SECONDER: Dave Parisot, Commissioner District 2
AYES: Don Amunds, Nathan Boyles, Dave Parisot, Kelly Windes
ABSENT: Wayne Harris
http://okaloosacountyfl.igm2.com/Citizens/Detail _LegiFile.aspx?ID=1335&highlightTerm... 2/19/2015
Request to solicit quotes in lieu of formal bids for the purchase of pipe and associated fitti... Page 3 of 3
Public Discussion
%2 Add Comment
Powered by Accela - Legislative Management
http://okaloosacountyfl.igm2.com/Citizens/Detail LegiFile.aspx?ID=1335&highlightTerm... 2/19/2015