OKALOOSA SHERIFF’S OFFICE ADDITION
100% GMP PROPOSAL
SEPTEMBER 16, 2014
State of FL Certified General Contractor #CG C008942
State of FL Certified General Contractor #CG CO57094
CONSTRUCTION , State of AL Certified General Contractor #12776
INC. State of GA Certified General Contractor #GCCO002537
CONSTRUCTION MANAGER / GENERAL CONTRACTOR State of MS Certified General Contractor #08714-MC
Trusted Performance ... Lasting Value
Sheriff's Office Addition
100% G.M.P. Proposal
Summary:
Attached is the breakdown information for the G.M.P. proposal for the subject
project. Bids were received at 2:00 P.M. on August 20, 2014 based on the 100%
construction documents dated July 15, 2014.
We have attached the bid breakdown, subcontractor recommendations, revised
schedule, and assumptions with clarifications.
The original budget estimate of $1,269,512 was impacted by a major revision to
the foundation design. This redesign increased dewatering, reinforcing, concrete and
compaction requirements. We had no information concerning the site utilities at the time
of the initial budget estimate, and we stated that the estimate was for buildings only. The
cost impacts for these two additions to scope equal over $200,000.
Please note that the schematic estimate developed in April 2014 appears to be at
the beginning of construction resurgence in this local area. We are seeing dramatic
increases of 3 to 5% in many of the work areas (primarily concrete, masonry, mechanical,
electrical, and plumbing) due to increased material costs and labor shortages of skilled
workers.
Our 50% estimate captured these additional costs as well as minor scope
increases in plumbing, HVAC, and access control. The 50% estimate total was
$1,573,715. As noted in the 50% budget estimate review, some of the documents were
not as complete as others, and our assumptions, while conservative, did not anticipate all
of the scope as drawn on 100% documents. These differences are minor and do not
appreciably affect the G.M.P.
We have included governmental requirement fees that are cost of doing work (i.e.
building permit and fire department fee), but not the water, sewer, development fees, and
storm water department fees, as they have not been furnished to us.
We have included a revised schedule that incorporates the design time lost during
the redesign of foundation and site utilities.
LY 19 David Street - Fort Walton Beach, Florida 32547
~ aN P.O. Box 1808 + Fort Walton Beach, Florida 32549
> \ 850-863-5158 + FAX 850-862-4904
info@lordandson.com
Associated Builders www.lordandson.com
and Contractors, Inc.
North Florida
Chapter
Specializing in Commercial Construction
Since 1975
We have bid the project out to a wide range of subcontractors and received
numerous bids in all categories. We have developed an aggressive schedule and will
work diligently to complete the project ahead of schedule allow the Sheriff to take
occupancy as soon as possible.
Our total G.M.P. cost is $1,474,064 as noted on page 4 of our proposal. We look
forward to completing this project ahead of schedule and under budget.
bb cth-
Leven D. Lord, II
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
September 16, 2014
The following list of information and qualifications serve as the basis for the Schematic Budget.
LIST OF PLAN SHEETS
Civil Sheet 1 through 7 dated 07/10/2014 prepared by Choctaw Engineering, Inc.
Sheets GO001, LS101, A010 (07/29/2014) , A101 (07/29/2014), A102, A103, A201, A301,
A401, A402, A403, A501 (07/29/2014), A601 (07/29/2014), A602 (07/29/2014), FP101, P101,
P102, P201, P301, M101 (07/29/2014), M201 (07/29/2014), M301, M302, E1.0 (07/29/2014),
E1.1, £1.2, E2.0, E3.0 (08/18/2014), E3.1(08/18/2014), E4.0 (08/18/2014), E4.1 (08/18/2014),
E4.2 (08/18/2014), and E5.0 (08/18/2014) dated 07/15/2014 (unless otherwise noted) as
prepared by DAG Architects Inc.
Structural Sheets S.0, S.1, and S.2 Addendum date 07/18/2014 prepared by RAC
Engineering, Inc.
Pre-Engineered Metal Building Drawings E1 through E19 dated 6/19/2014 as prepared by
Kirby Building Systems.
Ecospan Composite Floor System Sheets J-1, D-1, and JN-1 dated 7/3/2014 as prepared by
Nucor Detaining Center.
Specification dated 07/23/2014 as prepared by dag Architects Inc.
Report of Geotechnical Exploration dated 07/15/2014 as prepared by Larry M. Jacobs &
Associates, Inc.
Addendum 01 dated 08/04/2014 and Addendum 02 dated 08/18/2014
General Conditions
Building permit is included at an allowance $8924.
Fire Department Fee is included in the Building Permit Allowance.
Bond is included.
Builder Risk Insurance is included.
Contractors Liability Insurance is included
Water & sewer tap and impact fees are NOT included.
Temporary construction fence is included in this budget as dictated by the security
requirements of the Sheriff's office.
Development fees and storm water fees are NOT included.
Architectural & Engineering fees are not included in this construction budget.
Staking out of the building, As-Built Survey, and foundation survey are included.
Sitework
Sitework is included.
o Demolition of concrete paving.
o New building pad and concrete paving select fill.
Domestic water, fire water and sanitary utilities to within 5’ of the building are included to the
property line only.
Storm drainage system for the building is included per the drawings provided.
Concrete Paving & Sidewalks are included.
Termite treatment is included with a one year warranty which includes damage repair.
Landscaping and irrigation is not included.
Silt fence is included.
Temporary storm water piping is included to divert water from the building slab.
Dewatering of the elevator pit is included.
Rework of the existing fence is included at the allowance of $2,500.
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
Concrete
e Concrete building slab is included as a floating slab using 3000 psi concrete with rebar
reinforcing steel.
e Second floor slab is quoted as a 4” slab using 3000 psi concrete and 6 x 6 6/6 welded wire
fabric.
Masonry
e CMU walls are included at the elevator shaft.
Metals
e Steel pan stairs (2 each) with railings to the second floor are included.
e Miscellaneous metals at the elevator tower are included.
e Elevator pit ladder is included.
Carpentry
¢ Wood wall blocking is included for specialties.
e Casework is included per the drawings. Counter tops are quoted plastic laminate.
e Window sills are included.
Waterproofing
e Waterproofing for elevator pit is included.
Doors/Frames/Storefront
e Hollow metal frames, wood doors, and hardware are in this budget for the interior and exterior
openings. Electronic hardware for the access control is included.
¢ Wood doors are rotary natural birch, 5 ply construction with a factory finish.
e Door hardware will be keyed into the existing building and will match existing.
e Sheriff's office is providing a bullet resistant view window at Room101 to be installed by this
contractor.
e Exterior storefront windows are included as clear anodized aluminum storefront frames with
bronze or grey tint insulated glass.
e Door lights are included per the drawings.
e Access control system is included.
Finishes
e At exterior walls and masonry walls, 1.5 inch metal studs and one layer of 5/8” gypsum wall
board is included.
¢ All new interior walls are included using 3 5/8” metal framing and 5/8” gypsum board with
sound insulation.
¢ One hour fire walls are included at the east and west walls on the building between the stair
wells and the main building.
¢ Gypsum board ceilings are included as indicated.
e Acoustical ceilings are included as a standard 2x2 lay-in using Armstrong 1732 ceiling tile or
equal with insulation being laid 4 feet on each side of walls.
¢ Carpet flooring is included as Shaw |, Neyland-Neyland 2, 260z., unitary back — Color: Scotch
Pine — or equal.
e VCT is included as Mannington Essentials or Armstrong Excelon in standard colors.
e Rubber base is included as Johnsonite 4” rubber base in standard colors.
e Hard tile in the toilets for the floors and walls are included as follows:
o Wall Tile — Daltile Semi-Gloss/Matte Group 1.
o Floor Tile — Daltile Mosaic Colorbody Porcelain, Keystones, Groups 1 & 2, 2”x2”.
2
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
o Grout —- TEC AccuColor Premium Grout.
e Painting of all walls, ceiling, door frames, and doors is included as follows:
o HM Frames & Doors — 2 coats Sherwin Williams Pro Mar 200 semi-gloss latex (or
equal).
o Walls — 1 coat Sherwin Williams Pro Mar 200 primer and 2 coats Pro Mar 200 egg shell
(or equal).
o Ceilings — 1 coat Sherwin Williams Pro Mar 200 primer, 2 coats Pro Mar 200 Flat (or
equal).
o Steel Stairs and Rails — 2 coats Industrial Enamel
Specialties
e Seven each fire extinguishers and fire extinguisher cabinets are included in this budget.
e Doors signs are budgeted for code requirements as follows:
e 4each Toilet signs
e 5 each Stair signs
e 2each Elevator signs
e 1 each Elevator equipment room sign
e Standard commercial toilet accessories are include in the toilets — Toilet tissue dispenser,
paper towel dispenser, waste receptacles, framed mirror (18” x 36”), towel pins, towel bars
with shelf, shower curtain rods, and grab bars.
e Aluminum canopy is included at the front poach as clear anodized aluminum.
e Metal building canopy will be included at the pedestrian door S102B.
Furnishings
e Office cubicles are not included in this budget.
Special Construction
e A pre-engineered building will be 40-0 x 130-0 with a 28-0 average eave height. The building
will have a full second floor system including structural steel, bar joist, and metal decking.
e Roof is a single slope 1:12 standing seam metal roofing. Siding is stucco look concealed
fastener wall panel.
e Insulation is R-19 at the roof, and R-13 insulation in the exterior walls.
Hoisting
e A 2stop hydraulic elevator is included in this proposal.
Mechanical
e Fire protection system is included as a wet pipe system. A fire pump is not included in this
proposal.
e Plumbing is included to 5’-0” outside the building foot print.
e¢ HVAC is quoted using heat pumps:
» Eight each air handler and condenser units, two each PTAC units in the stairs, and one
each ductless split system in the elevator room.
= Sheet metal duct with insulation.
« Grills, Registers, and diffusers are included.
"Four each exterior wall louvers are included
= Two each exhaust fans and duct with backdraft dampers.
e Stand-alone controls are included as shown.
e Test & Balance is included.
Electrical
e Electrical is included per the drawings provided.
3
Lord & Son Construction Inc.
Okaloosa County Sheriff’s Office Addition, Shalimar, Florida
100% GMP Qualifications
e EMT is included for all branch conduits.
e All copper service conductors are included.
¢ Conduit and inner duct is provide for the data and communication systems only. The
communication and data systems are by others.
e Power connects to system furniture is included. Power poles are to be furnished by the
owner’s system furniture contractor.
e No Gulf Power charges are included.
Cost for the New Addition at the Sheriff's Office Shalimar $ 1,504,147.00
Sale Tax Savings 2% $ <30,083.00>
Total with Sales Tax Savings $ 1,474,064.00
Proposed Cost Savings:
Use MC Cable in lieu of EMT for electrical branch circuits - Deduct $ <3,100.00>
Delete PTAC’s in stair wells and add exhaust fans with louvers $ <3,860.00>
Okaloosa County Sheriff's Office Addition
100% GMP
September 22, 2014
DIV DESCRIPTION OF WORK Schematic Budget Total 50% Budget Total 100% GMP TOTALS
ta __|GENERAL CONDITIONS $ 98,637 | $ 106,457 | $ 93,642
1b _|GENERAL REQUIREMENTS $ 19,044
1c {TEMPORARY FENCE $ 1,925 | $ 5,100 | $ 5,100
2__|SITEWORK & STORM $ -|$ 25,634 | $