READ ALONGSIDE THE SOURCE

Okaloosa County BOCC — August 19, 2014 — FAA Grant Application_VPS Boarding Ramps — reading text

Part 4 of 4. These parts divide the reading text for browsing; they are not the source document's page numbers.

Machine-extracted text — 39-FAA Grant Application_VPS Boarding Ramps.pdf

Machine-extracted OCR text · Review label: Machine produced / unreviewed

Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.

INon-Reflective Pavement Markings 3,000 | SF $1.50 $4,500.00 $1.90 $5,700.00 * 4 S-140 Pavement Marking Removal 7,000 SF $2.10 $14,700.00 $2.80 $19,600.00 5 “S140 al of Existing Lit BS i ts $4,752.00 $4,752.00 Provide and Install New Ground Power Cables and 6 01920A Connections. This pay item includes both bridges. 1 LS $6,500.00 - $6,500.00) $16,434.00 $16,434.00 7 019208 land Connections. This pay item includes both 4 ts $8,500.00 $8,500.00 $10,150.00 $10,150.00 8 01920C Relocate Interior Gate Signage 1 LS $4,500.00 $4,500.00) $2,172.00 $2,172.00 Baggage Lifting System. This item shall include ali necessary for a complete operational system in place as required by the plans and specifications. Work items include but are not : 9 14540 bited 16 foundational fe electica! 4 EA $30,000.00 $120,000.00) $34,930.25 : USE! co ions, baggage cart, modification of and watertight attachment to existing passenger Passenger Boarding Bndge. This item shall include all design, fabrication, procurement, installation, and construction of a complete 10 14950 operational apron drive passenger boarding bridge 2 EA $600,000.00 $1,200,000.00 $711,043.50 $1,422,087.00 and fixed bridge system to be connected to the Total $1,458,950.00} {Total ADD BiD PR OND O D AIR {tem} Pay Item Number item Description - Quantity } Unit Unit Price Amount Unit Price Amount (A1-4 $-140 |Remove Existing Pre Conditioned Air Unit. 2 EA $5,000.00 $10,000.00} $1,700.56 $3,401.00 DEDUCT - "Provide and Install New Pre A1-2 01920 Conditioned Air Hoses and Connections" from 1 LS (38,500.C0) -$8,500.00 (310,150.00) -$10,150.00 BASE BID ITEM7 above. At 1060 | Pee eee ee 2 | EA | $100,000.00 $200,000.00] | $102,163.00 $204,326.00 Total $201,500.004 {Total ADD BID RO D PO Item] Pay Item Number Item Description Quantity | Unit Unit Price Amount Unit Price Amount jA2-4 $-140 Remove Existing Ground Power Unit. 2 EA $6,500.00 $13,000.00} $905.00 | $1,810.00 DEDUCT - "Provide and Install New Ground Power Cables and Connections. This pay item (REAR BRI - any 4 A2-2) 01920 includes both bridges." from BASE BID ITEM 6 A Ls dais 95,908.00 (318.434 00 diaiadiaad above. Provide and Install 28VDC/400Hz Frequency A2-3 14950 Converter Ground Power Unk C 6s ih Place. 2 EA $60,000.00 $120,000. $64,617.50 $129,235.00 Total $126,500.004 {Total * Represents an error in math from the bid form e. puters contgined within this Bid Tabulation are July 14, 2014 Doug Hambrecht, P.E. THE LPA GROUP INCORPORATED 7/14/2014 HH e_ YN GRouP SSS TRANS! PORTATION CONSULTANTS. A.Unt of Michoe! Boker Grant #1 FUNDING ADJUSTMENTS AP 49-14 Base minus item 9 (Bag Lifts) $1,546,729.00 Boarding Bridge Base plus Additive Bid 1 $1,744,306.00 | Boarding Bridge Base Additive Bid 2 $1,661,340.00 | psa Bridge Base plus Additive Bid 1 &2 $1,858,917.00 Grant #2 {Bag Lifts 8-1, 8-2, B-3, and B-5 (item 9} $139,721.00} = Boarding Bridges Base BOARDING BRIDGES AND BAG LIFTS- Bid Tab.xlsx

Download this text file with its original spacing ↓