TASK ORDER APPROVAL FORM
Qog0
CONTRACT #: C14-280-PW
TASK ORDER #: J]
TASK ORDER AMOUNT: $__ 69,595
OFFERED BY CONSULTANT:
Hatch Mott MacDonald Florida, LLC
FIRM'S NAME
David Skipper, PE
REPRESENTATIVE'S PR?TED NAME
CONTRACT # C14-2080-PW
HATCH MOTT MACDONALD FLORIDA
ENG. CONSULTING SERVICES
EXPIRES: 09/30/2016
—
SIGNATURE
Vice President 4/28/2016
TITLE DATE
RECOMMENDED FOR APPROVAL
(Department Director)
SIGNATU {54 \/
SRS ) ‘T;Eey
Pudic Works DiRectoiR
TITLE
S |4
DATE '
COu ADMINSTRATOR (if applicable)
o HoFsFADN
DATE
APPROVED BY OKALOOSA COUNTY
(Per Purchasing Manual)
e $25,000 or less approved by Purchasing
Director
e Between $25,001 and $50,000 approved by
Purchasing Director and County
Administrator
e In excess of $50,000 approved by the Board.
ASING DIRECTOR
7z FehoRrAK
S/
DATE 7 '}
A,
CHAIRMAN (if applicable)
CHALLes K WIKBES TR
Tz /e
DATE / °
: Hatch Mott MacDonald
: ' HatCh MOtt 5111 North 12th Ave
Pensacola, FL 32504
* MaCDonald T 850.484.6011 www.hatchmott.com
AAC000035 EBO000155 LBO0006783
April 28, 2016
Mr. Scott Henson
Public Works Program Director
Okaloosa County Public Works
84 Ready Avenue
Fort Walton Beach, FL 32548
RE: Meigs Drive Drainage Improvements — Shalimar, FL
Dear Mr. Henson:
Hatch Mott MacDonald (HMM) is pleased to provide this proposal for purposes of
providing civil engineering design, environmental assessment and permitting assistance
for improvements to Meigs Drive in Shalimar, FL as described in Okaloosa County
Stormwater Improvements Report (HMM Project #301252) “Meigs Drive - Alternate No.
2.
This Scope of Work will be performed in accordance with the existing Contract #C14-
2080-PW between Hatch Mott MacDonald Florida, LLC and Okaloosa County dated
10/03/2013.
Proposal Conditions
= Construction Observation Services are not included in this scope of work, but
can be negotiated at a future date if required.
= The project design is based on “Meigs Drive Alternate 2” as shown in Figure 4.1
of the Okaloosa County Stormwater Improvements Report (HMM #301252).
Scope of Services
Task 1 —30% Design Services
The following Tasks will be performed as part of 30% Design Services for the project.
Jurisdictional Determination
A jurisdictional determination of wetland areas in the immediate proximity of the
project will be determined by an environmental scientist. These limits will be used to
determine the quantity of impact for the proposed project. Permitting activities by the
environmental scientist will be performed outside of Task 1.
i
Hatch Mott
MacDonald
Right of Way and Topographic Survey
HMM will perform a survey to determine the existing grades for the site within the
limits of construction. Right of way, property lines, easements and environmentally
sensitive delineations in the project area will be located.
Task deliverables consist of Civil 3D drawing of the existing conditions for use in the Civil
Design of the project.
Geotechnical Engineering
A geotechnical engineering evaluation and report will be performed for the project to
determine the characteristics of the existing soil in order to specify roadway fill for the
raised roadway, culvert bearing design and pavement design.
A signed and sealed geotech report will be provided with Task 1.
30% Civil Engineering Design
HMM will prepare civil design drawings at a 30% complete status along with an opinion
of probable construction cost.
Civil design drawings will include:
= Existing conditions with proposed demolition and erosion control
= Site dimension and layout plan
= Grading plan
= Construction details
Task 2 — Construction Plan Development
After receiving Okaloosa County approval in writing, HMM will provide 90% design plans
for review and final plans for project construction.
Construction Documents will include:
= Existing conditions with proposed demolition and erosion control
= Site dimension and layout plan
= Grading plan
= Construction details
= Project Specifications
Bidding assistance will be provided during this Task.
Okaloosa Co. Page 2 April 28, 2016
C:\Users\jen31351\Desktop\PROSPECTS\PROPOSALS\2015.12 Okaloosa Meigs & Wetlands\Scope-Fee -Okaloosa Meigs 2016.04.28.doc
oo
Hatch Mott
MacDonald
Task 3 — Permitting
HMM will prepare and submit required documentation to NWFMWD, FDEP, and USACE
for permitting required for the project.
This phase will consist of drawings, reports, calculations and applications for the
proposed design for the project. HMM will respond to comments received by reviewing
agencies during this Task.
This Task does not include permit application fees.
Construction Observation
Construction Observation is not included in this scope of work. It is anticipated that
some construction observation will be required by the Engineer of Record in order to
certify project completion. The fee for Construction Observation (if required) will be
negotiated at a future date.
Summary
‘fif.h Mott
In summary, our not to exceed fee amount is $69,595 to include Tasks 1 - 3. We look
forward to working with you on this project.
Sincerely,
/
T. Heath Jenkins, David D. Skipper, PE
Project Manager Vice President
\
Recommended for Approval:
Department Director
Jé‘s&r)A}ftr oy, P\E\} Public Works Director
Okaloosa Co. Page 3 April 28, 2016
C:\Users\jen31351\Desktop\PROSPECTS\PROPOSALS\2015.12 Okaloosa Meigs & Wetlands\Scope-Fee -Okaloosa Meigs 2016.04.28.doc
Since 1976 Geotechnical Engineering \l w’/ Materials Testing Drilling Services
February 25, 2016
Mr. Heath Jenkins, PE
Hatch Mott MacDonald
220 West Garden Street, Suite 700
Pensacola, Florida 32502
SUBJECT: Geotechnical Exploration Proposal
Meigs Drive Pavement
Shalimar, Florida
Dear Mr. Jenkins:
Larry M. Jacobs & Associates, Inc. (LMJ) sincerely appreciates the opportunity to submit the following
proposal for providing a geotechnical exploration for the subject project. The purpose of the exploration is
to determine the subsurface conditions in the pavement area and use this information to provide
recommendations for earthwork and pavement design. The following sections outline our recommended
scope of services, a cost estimate for providing these services, and the proposed terms and conditions.
PROJECT AND SITE DESCRIPTION
The project site is located on Meigs Drive where it crosses Lake Vivian in Shalimar, Florida. Reportedly,
the project consists of the replacement of roughly 500 feet of Meigs Drive, as well as raising the grade of
that length of the road about two feet. We understand that the project includes the construction of a new
culvert with headwalls. Reportedly, the roadway is known to flood. If any of this information is incorrect,
please let us know as it may require changes to our scope.
PROPOSED SCOPE OF SERVICES
The following proposed scope of services is based on the information supplied and our experience in the
area with similar projects. We propose to perform the following:
v Locate the borings at the site with a hand held GPS unit.
v Clear registered utilities at the site with the Sunshine Network. Non-registered or private utilities are
the responsibility of the client to clear.
v Mobilize a truck mounted and tripod mounted drill rig(s) and drill team to the site.
v Use proper MOT to close one lane of Meigs Drive to allow drilling operations, and we have
included prices for sign rental and two flagmen. If the county or city will provide flagmen, we can
forgo that fee. Drilling operations are expected to take roughly 1-1.5 days.
v Core the asphalt pavement at two locations (4 inch diameter) in order to obtain accurate
information on existing pavement thickness.
v Patch core holes after completion of drilling operations.
v Drill 2 Standard Penetration Test (SPT) borings to a depth of 15 feet in the new roadway at the
core locations. Since grades are being raised about two feet, these borings are being drilled
deeper than normal roadway borings to check for the presence of compressible peat or clay.
v Drill 2 SPT borings at the culvert headwall locations to a depth of 25 feet, and these borings will be
drilled with our portable tripod mounted drill rig since access is difficult and narrow.
Larry M. Jacobs & Associates 328 E Gadsden St, Pensacola, FL 32501 850.434.0846 * www.Imj-a.com
v Perform a visual classification and laboratory testing of the soil samples obtained during our
exploration. Our proposal includes a small budget for basic properties testing like natural moisture
content, Atterberg limits and sieve analysis to evaluate and document basic soil properties.
v Analyze the test data to develop geotechnical engineering recommendations for the project.
A professional geotechnical engineer licensed in the state of Florida will manage the project, and the
results of the exploration will be presented in a report that will address the following:
Existing site characteristics.
Exploration, testing, and sampling methods.
Subsurface soils encountered and soil classifications.
Depth to groundwater at the time of drilling.
A discussion of laboratory test results.
Site preparation recommendations, including fill placement and compaction recommendations.
4 4 4 4 4@ <« 4
General recommendations for design of asphalt pavement, including recommend asphalt and base
types, as well as compaction and testing recommendations. Recommendations for subgrade
stabilization will be provided if needed. We will provide typical asphalt and base thickness for
roadways of this category.
v Shallow foundation design recommendations for culvert headwalls, including allowable bearing
capacity and estimated settlement.
ESTIMATED COSTS & SCHEDULE
Our cost breakdown for this work is attached as Figure #1. LMJ proposes to provide the geotechnical
scope of services in this proposal for an estimated fee of $3,625.00. If done by LMJ, MOT and flagmen
during drilling operations is estimated to cost an additional $1,350.00, for an estimated total project cost of
$4,975.00. This proposal assumes that the boring locations are accessible with our truck mounted or tripod
mounted drill rig, we have right of entry to the boring locations, and that we will not experience excessive
delays due to debris at borehole locations or for other reasons outside of our control. If such conditions are
encountered that may cause the cost of the exploration to exceed the budget figure, we will notify the client
and obtain approval for the additional work before proceeding. At this time, we estimate that drilling
operations could start 1-2 weeks after written authorization is received, weather permitting.
AUTHORIZATION
To authorize us to proceed with this project, please complete, sign, and return a copy of the attached
Agreement for Professional Services (Figure #2) to our office. If the authorization for this work is faxed
or emailed to initiate the work, the original signed authorization is needed for our records, which can be
forwarded by return mail. LMJ appreciates the opportunity to present you with this proposal, and we look
forward to working with you on this project. If you have any questions or comments, please call us at your
convenience.
Sincerely,
LARRY M. JACOBS AND ASSOCIATES, INC.
Terry Niemann
Project Manager
Attachments
Figure #1 LMJ COST BREAKDOWN
CLIENT: Hatch Mott MacDonald
PROJECT: Meigs Drive, Shalimar, Florida
[ UNIT FEE EST. QTY EST. COST
FIELD TESTING/DRILLING SERVICES
MOBILIZATION 0-25 MI [$350.00 /EA
26-75 MI | $425.00 /EA 1 425.00
STANDARD PENETRATION TEST BORINGS 0-40 FT | $13.00 /LF 30 390.00
2@15ft 41-80 FT | $15.00 /LF
TRIPOD BORINGS 0-30 FT | $19.00 /LF 50 950.00
2 @25 ft 31-60 FT | $21.00 /LF
TWO FLAGMEN $100.00 /HR 12 1,200.00
MOT SIGNS RENTAL $150.00 /EA 1 150.00
OBTAIN UNDISTURBED/SHELBY TUBE/BULK SAMPLE $80.00 /EA
CORE & PATCH ASPHALT PAVEMENT $80.00 /EA 2 160.00
ENG. TECH. (LOCATE BORINGS & CLEAR UTILITIES) $50.00 /HR 3 150.00
FIELD TESTING/DRILLING TOTAL $3,425.00
LABORATORY TESTING SERVICES