American Suncraft Change Order #2 from the Okaloosa County BOCC meeting of May 20, 2014 (IQM2 meeting #1199). Original portal label: American Suncraft Change Order #2. Preserved as a historical public record; part of the meeting linked as a related source.
- Original publication
- American Suncraft Change Order #2
- Date
- May 20, 2014
- Reference collection
- Okaloosa County Board of County Commissioners (IQM2 public portal)
HOW FAR THIS HAS BEEN CHECKED
- File / copy authenticity
- Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
- Transcription / extraction
- Machine produced / unreviewed — machine-extracted, not yet human-corrected
- Claim corroboration
- Not independently verified
View reference catalogue / source ↗
Download this source
American Suncraft Change Order #2 (PDF)
Original PDF as published on the Okaloosa County IQM2 meeting portal.
PDF · 104.8 KB
Download ↓Machine-extracted text — 127-American Suncraft Change Order _2.pdf
Text extracted on 2026-10-31 from 127-American Suncraft Change Order _2.pdf using optical character recognition (ocrmypdf/tesseract). Not human-corrected; may contain recognition errors. Read alongside the source images.
Text · 2.0 KB
Download ↓
Full text
Machine-extracted from the source by optical character recognition. Not yet human-corrected — it may contain recognition errors. Read it alongside the images above.
CHANGE ORDER FORM
Date: 05-02-2014 Contract No; C14-2160-WS
Change OrderNo.: 2
Owner: __ OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS
American Suncraft Construction Company
Contractor:
CHANGE TO CONTRACT PRICE
DESCRIPTION AMOUNT
Original Contract Price: $543,475.00
Net change by previously authorized Change Orders: $4,800.00
Present Contract Price:
$548,275.00
This Change Order will (add/deevet):
$19,220.00
New Contract Price:
$567,495.00
CHANGE TO CONTRAC
T TIME
DESCRIPTION
DATE or NUMBER OF DAYS
Original Contract Time:
180 Days
Original Substantial Completion Date:
July 16, 2014
Net change by previously authorized Change Orders: N/A
This Change Order will (add/deduct): 240 days
420 Days
New Contract Time:
New Substantial Completion Date:
March 13, 2015
Ah yyernovns
REQUESTED BY: | gt !
Lord
VU
PROJECT ENGINEER: AAC) {
CONTRACTOR: fol. fA
OWNER:
This Change Order is an amendment to the Contract/A
DATE: 5f12/Z0l4
DATE: 5- Lol Sf
pate:__5-6-/7
DATE:
reement between Contractor and the
Owner, and all other contract provisions shall remain in full force and effect unless specifically
amended in writing, signed by both parties.
Item
No.
Paint and Repair Countryview and Bluewater Tanks (2014)
Change Order #2 Analysis
Original
Quantity
Unit
Cost
Original
Cost
Change |
Order #2 |
Quantity
“Change”
Order Unit
Cost |
(CO #2).
12
Clean and inspect the
Oddfellow and LiveOak
elevated water storage
tanks via underwater
operations (tanks shall
remain in service) and
prepare signed and sealed
inspection report, per
FDEP regulations,
complete and in place for
$0
$0
$7,620
$7,620
13
Drain, clean and prepare
the Seminole elevated
water tank for FDEP
mandated inspection, and
disinfect tank per contract
specifications post
inspection, complete and
in place for
$0
$0
$5,900
$5,900
14
Drain, clean and prepare
the Playground elevated
water tank for FDEP
mandated inspection, and
disinfect tank per contract
specifications post
inspection, complete and
in place for
$0
$0
$5,700
$5,700
CO #2 Total =
$19,220