READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — September 3, 2013 — Passenger Boarding Bridges LPA_Task Order 15 — reading text
Part 2 of 2. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 17-Passenger Boarding Bridges LPA_Task Order 15.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Use Aeroturn for aircraft wing tip spacing, 6 6
positioning, and ultimate alignment
Apron layout concept 2 4 8 12 26
Determine Boarding Bridge Layout 1 3 4 16 24
Marking Plan 1 2 6 15 24
Site Electrical Modifications 3 10 6 5 24
Engineer's Estimate 1 2 2 5
Develop Plans 14 14 28
RFP Front End Documents 4 6 5 15
RFP Technical Requirements 4 30 3 2 39
Quality Control Review 3 3
Total: 34 101 70 79 11 295
Rate/Hour: $150.00 $100.00 $75.00 $60.00 $45.00
Total Direct Labor: $5,100.00 $10,100.00 $5,250.00 $4,740.00 $495.00 $25,685.00
PRE-DESIGN GEOTECHNICAL TESTING =
PSI, Inc $1,000.00
DIRECT COSTS
Printing, travel $2,200.00
Total Direct Costs 200. $2,200.00
Total Phase 1 (Lump Sum): $28,885.00
NWF Regional Airport
10/11/2013 Page B-2 of B-4
Boarding Bridges
EXIHIBIT B
MANHOUR AND FEE ESTIMATE
OKALOOSA COUNTY NORTHWEST FLORIDA REGIONAL AIRPORT
Boarding Bridges A-1 and A-2
PHASE 2 - BIDDING
PHASE 2-BIDDING —__
_ SR. Project Professional SR.CAD CAD
Item/Task Description Manager Engineer Designer_ _Technician__ Clerical Totals
Advertise and Coordinate 3 3
Distribution of Bidding Documents 1 2 6 9
General Coordination 4 6 5 13
Answers to Bidders/Issue Addenda 1 12 4 5 22
Bid Opening 4 4
Review Bids for Responsiveness 4 14 4 22
Bid Tab 1 1 2 4
Total: 18 33 0 6 20 77
Rate/Hour: $150.00 $100.00 $75.00 $60.00 $45.00
Total Direct Labor: $2,700.00 $3,300.00 $0.00 $360.00 $900.00 $7,260.00
DIRECT COSTS
Reimbursable (plans, spec books,
travel) $900.00
Total Direct Costs $900.00 $900.00
Total Phase 2 (Lump Sum): $8,160.00
NWF Regional Airport
10/11/2013 Page B-3 of B-4
Boarding Bridges
EXIHIBIT B
MANHOUR AND FEE ESTIMATE
OKALOOSA COUNTY NORTHWEST FLORIDA REGIONAL AIRPORT
Boarding Bridges A-1 and A-2
PHASE 3 - CONSTRUCTION MANAGEMENT
_ PHASE 3 - CONSTRUCTION MANAGEMENT
ASSUME 60 DAY CONS TRUS TON SCHEDULE f PLUS Pane LIST WORK
CONSTRUCTION ADMINISTRATION
_ SR. Project Professional SR.CAD CAD
Item/Task Description Manager Engineer Designer_ Technician _ Clerical Totals
General Coordination with the County 4 4 6 14
General Coordination with the 5 3 4 12
Contractor, subconsultants
Prepare for attend Pre-Construction 3 4 3 15
Conference
Prepare minutes to Pre-Con 2 3 5
Review Submittals 2 6 1 9
Review Pay Applications 2 2 1 5
Review Payrolls, DBE Reports, EEO
2 2 1 5
Reports
Periodic Site Visits (8 total) 64 2 66
Review and Respond to RFI's 4 8 1 13
Prepare Change Orders 1 2 1 4
Final Inspection/ Punch List items 8 4 2 14
Prepare Closeout Documents 4 16 5 25
Total: 106 51 0. 3 27 187
Rate/Hour: $150.00 $100.00 $75.00 $60.00 $45.00
Total Direct Labor: $15,900.00 $5,100.00 $0.00 $180.00 $1,215.00 $22,395.00
CONSTRUCTION INSPECTION. =
Not included $0.00
QUALIFY ASSURANCE TESTING.
Not included $0.00
DIRECT COSTS
Reimbursable (travel, FedEx, printing,
closeout books) $4,000.00
Total Direct Costs $4,000.00 $4,000.00
Total Phase 3 (Lump Sum): $26,395.00
NWF Regional Airport
Boarding Bridges 10/11/2013 Page B-4 of B-4