Fort Walton Beach Resolution — 2023-18 Accepting Grant Funding Coral Creek Nature Trail — reading text
Part 4 of 10. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — fwb-41459-original.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
contract, or
ii. Construct the Project utilizing existing Recipient employees, if the Recipient can complete said
Project within the time frame set forth in this Agreement. The Recipient' s use of this option is subject
to approval by the Department.
c. The Recipient shall hire a qualified contractor using the Recipient' s normal bid procedures to perform the
construction work for the Project. For projects that are not located on the Department' s right- of-way, the
Recipient is not required to hire a contractor prequalified by the Department unless the Department
notifies the Recipient prior to letting that they are required to hire a contractor prequalified by the
Department.
d. The Recipient is responsible for provision of Construction Engineering Inspection ( CEI) services. The
Department reserves the right to require the Recipient to hire a Department pre -qualified consultant firm
that includes one individual that has completed the Advanced Maintenance of Traffic Level Training.
Notwithstanding any provision of law to the contrary, design services and CEI services may not be
performed by the same entity. Administration of the CEI staff shall be under the responsible charge of a
State of Florida Licensed Professional Engineer who shall provide the certification that all design and
construction for the Project meets the minimum construction standards established by Department. The
Department shall have the right to approve the CEI firm. The Department shall have the right, but not the
obligation, to perform independent assurance testing during the course of construction of the Project.
Subject to the approval of the Department, the Recipient may choose to satisfy the requirements set forth
in this paragraph by either hiring a Department prequalified consultant firm or utilizing Recipient staff that
meet the requirements of this paragraph, or a combination thereof.
e. The Recipient is responsible for the preparation of all design plans for the Project. The Department reserves
the right to require the Recipient to hire a Department pre -qualified consultant for the design phase of the
Project using the Recipient' s normal procurement procedures to perform the design services for the Project.
Notwithstanding any provision of law to the contrary, design services and CEI services may not be
performed by the same entity. All design work on the Project shall be performed in accordance with the
requirements of all applicable laws and governmental rules and regulations and federal and state accepted
design standards for the type of construction contemplated by the Project, including, as applicable, but not
limited to, the applicable provisions of the Manual of Uniform Traffic Control Devices ( MUTCD) and the
AASHTO Policy on Geometric Design of Streets and Highways. If any portion of the Project will be located
on, under, or over any Department -owned right-of-way, the Department shall review the Project's design
Page 6 of 14
DocuSign Envelope ID: 4F3C11D1- 19B6- 409B- 9FC5- 798AB66C3206
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525- 010- 60
STATE -FUNDED GRANT AGREEMENT PROGRAM MANAGEMENT
09122
plans for compliance with all applicable standards of the Department, as provided in Exhibit " O", Terms
and Conditions of Construction, which is attached to and incorporated into this Agreement.
f. The Recipient shall adhere to the Department' s Conflict of Interest Procedure ( FDOT Topic No. 375- 030-
006).
g. The Recipient will provide copies of the final design plans and specifications and final bid documents to the
Department' s Construction Project Manager prior to commencing construction of the Project. The
Department will specify the number of copies required and the required format.
h. The Recipient shall require the Recipient' s contractor to post a payment and performance bond in
accordance with applicable law.
I. The Recipient shall be responsible to ensure that the construction work under this Agreement is performed
in accordance with the approved construction documents, and that it will meet all applicable Recipient and
Department standards.
j. Upon completion of the work authorized by this Agreement, the Recipient shall notify the Department in
writing of the completion of construction of the Project; and for all design work that originally required
certification by a Professional Engineer, this notification shall contain an Engineers Certification of
Compliance, signed and sealed by a Professional Engineer, the form of which is attached hereto and
incorporated herein as Exhibit " C", Engineers Certification of Completion. The certification shall state
that work has been completed in compliance with the Project construction plans and specifications. If any
deviations are found from the approved plans, the certification shall include a list of all deviations along with
an explanation that justifies the reason to accept each deviation.
k.
The Recipient shall provide the Department with as -built plans of any portions of the Project funded through
the Agreement prior to final inspection.
11. Maintenance Obligations: In the event the Project includes construction then the following provisions are
incorporated into this Agreement:
a.
The Recipient agrees to maintain any portion of the Project not located on the State Highway System
constructed under this Agreement for its useful life. If the Recipient constructs any improvement on
Department right-of-way, the Recipient
shall
shall not
maintain the improvements located on the Department right-of-way made for their useful life. If the Recipient
is required to maintain Project improvements located on the Department right-of-way beyond final
acceptance, then Recipient shall, prior to any disbursement of the State funding provided under this
Agreement, also execute a Maintenance Memorandum of Agreement in a form that is acceptable to the
Department. The Recipient has agreed to the foregoing by resolution, and such resolution is attached and
incorporated into this Agreement as Exhibit " D". This provision will survive termination of this Agreement.
12. State Single Audit: The administration of resources awarded through the Department to the Recipient by this
Agreement may be subject to audits and/ or monitoring by the Department. The following requirements do not limit
the authority of the Department to conduct or arrange for the conduct of additional audits or evaluations of state
financial assistance or limit the authority of any state agency inspector general, the Auditor General, or any other
state official. The Recipient shall comply with all audit and audit reporting requirements as specified below.
a.
In addition to reviews of audits conducted in accordance with Section 215. 97, Florida Statutes, monitoring
procedures to monitor the Recipient' s use of state financial assistance may include but not be limited to on-
site visits by Department staff and/ or other procedures including, reviewing any required performance and
financial reports, following up, ensuring corrective action, and issuing management decisions on
weaknesses found through audits when those findings pertain to state financial assistance awarded through
the Department by this Agreement. By entering into this Agreement, the Recipient agrees to comply and
Page 7 of 14
DocuSign Envelope ID: 4F3C11D1- 19B6- 409B- 9FC5- 798AB66C3206
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525- 010. 60
PROGRAM MANAGEMENT
STATE -FUNDED GRANT AGREEMENT 09122
cooperate fully with any monitoring procedures/ processes deemed appropriate by the Department. The
Recipient further agrees to comply and cooperate with any inspections, reviews, investigations, or audits
deemed necessary by the Department, the Department of Financial Services (DFS) or the Auditor General.
b. The Recipient, a nonstate entity as defined by Section 215. 97( 2)( n), Florida Statutes, as a recipient of state
financial assistance awarded by the Department through this Agreement is subject to the following
requirements:
In the event the Recipient meets the audit threshold requirements established by Section 215.97,
Florida Statutes, the Recipient must have a State single or project -specific audit conducted for such
fiscal year in accordance with Section 215. 97, Florida Statutes; applicable rules of the Department
of Financial Services; and Chapters 10. 550 ( local governmental entities) or 10. 650 ( nonprofit and
for-profit organizations), Rules of the Auditor General. Exhibit " J", State Financial Assistance
Florida Single Audit Act) to this Agreement indicates state financial assistance awarded through
the Department by this Agreement needed by the Recipient to further comply with the requirements
of Section 215.97, Florida Statutes. In determining the state financial assistance expended in a