READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — July 7, 2015 — Change Order #3 Summary — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Change Order #3 Summary — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
=
=
o
NAME OF PROJECT: 2011 Gravity Sewer Rehab
CONTRACTORS NAME: Insituform Technologies, LLC. CHANGE ORDER SUMMARY
ADDRESS: 17988 Edison Ave.
Chesterfield, MO 63005
SUBSTANTIAL COMPLETION DATE:
FINAL COMPLETION DATE: Annual Contract thru May 24, 2016
JOB NO. 41-444
REVISED ;
o Additional - Additional Additional Cost Additional Additional Cost
DESCRIPTION As Bid Quantiies SROIL UNTPRICE gig 7opg Quantiies AAIONBLOt g (CO#2) Quantities (o)
UNIT PRICE {May 2014- (CO#1) (CO#2) At Revised Prices (CO#3) AtRevised Prices
2016)
Furnish and install all materials and labor for
pre-inspection cleaning in 8" gravity sewer
pipe prior to in situ point repairs as described .
in the specifications 2,203 LF g 150 § 155 § 3,304.50 44671 $ 67,006.50 $ - 30000 § 46,500.00
Furnish and install all materials and fabor for
pre-inspection cleaning in 10" gravity sewer
pipe prior to in situ point repairs as described . ‘
in the specifications 3,264 LF§ 200 $ 206 $ 6,528.00 $ - $ - 145 $ 298.70
Furnish and install all materials and labor for : .
pre-inspection cleaning in 12" gravity sewer
pipe prior to in situ point repairs as described
in the specifications 1,685 LF $ 200 $ 206 $ 3,370.00 732 $ 1,464.00 $ -
Furnish and instal all materials and labor for
CCTV inspection in 8" gravity sewer pipe
prior to in situ point repairs as described in - - -
the specifications 2,203 IF$ 100 § 103 § 2,203.00 44671 $ 44,671.00 0 $ - 30000 $ 30,900.00
Furnish and install all materials and labor for :
CCTV inspection in 10" gravity sewer pipe
prior to in situ point repairs as described in .
the specifications 3,264 LF 8 150 § 155 § 4,896.00 $ - $ - 145 $ 24D
Furnish and install all materials and labor for
CCTV inspection in 12" gravity sewer pipe
prior to in situ point repairs as described in
the specifications 1,685 LF$ 150 § 155 § 2,527.50 732 $ 1,098.00 $
Furnish and install all materials and labor for
in-situ point repairs in 8" gravity sewer pipe 1 EA $ 190000 $ 196128 § 1,900.00 $ - 79 $ 154,941.12
Furnish and install all materials and labor for
in-situ point repairs in 10" gravity sewer pipe 23 EA§ 200000 § 206451 § 4600000 $ - $
Furnish and install all materials and labor for
in-situ relining of 8" gravity sewer pipe as
described in the specifications 2,203 LF $ 2500 $ 2581 § 55,075.00 410 $ 10,250.00 15622 $ 403,203.82 30000 $ 774,300.00
Page 1 0of 3
ITEM
NO.
1"
12
13
14
15
186
17
18
19
20
2
DESCRIPTION
Furnish and install all materials and labor for
in-situ relining of 10" gravity sewer pipe as
described in the specifications
Furnish and install all materials and labor for
in-situ relining of 12" gravity sewer pipe as
described in the specifications
Furnish and install all materials and labor for
service re-connections in 8" gravity sewer
pipe as described in the specifications
Furnish and install all materials and labor for
service re-connections in 10" gravity sewer
pipe as described in the specifications
Furnish and install all materials and labor for
point repairs in 8" gravity sewer pipe (if
needed and directed by Engineer) as
described in the specifications
Furnish and install all materials and labor for
point repairs in 10" gravity sewer pipe (if
needed and directed by Engineer)
Furnish and install all materials and labor for
point repairs in 12" gravity sewer pipe (if
needed and directed by Engineer) as
described in the specifications
Complete Mobilization and Demobilization
for original project and any subsequent Task
Order greater than $25,000
Emergency Mobilization and Demobilization
for Task Order less than or equal to $25,000
Mobilization and Demobilization for
Tuberculation Removal
Furnish and install all materials and labor for
tuberculation removal from 12" gravity sewer
pipe as described in the specifications
Furnish and install all materials and labor for
tuberculation removal from 8" gravity sewer
pipe as described in the specifications
As Bid Quantities
3,264 LF
1,685 LF
3 EA
5 EA
1 EA
1 EA
1 EA
1 LS
1 LS
LS
LF
LF
ORIGINAL
$
UNIT PRICE
26.00
29.00
200.00
200.00
5,500.00
5,750.00
6,000.00
3,500.00
6,500.00
7,000.00
82.00
71.00
REVISED
UNIT PRICE
(May 2014-
2016
$ 26.84
$ 29.94
$ 206.45
$ 206.45
$ 567740
$ 593547
$ 619353
$ 361289
$ 6,709.66
$ 722579
$ 84.64
$ 73.29
Total Quantities
Additional Additional Cost Additional Additional Cost Additional Additional Cost ¢ E
Bid Total Quantities T (co#y Quantities (CO#2) Quantities (co#3) - (Bid+Change
(co#) (CO#1) (Co#2) At Revised Prices (CO#3) AtRevisedPrices Orders)
$ 84,864.00 $ - $ 1432 $ 38,434.88
$ 48,865.00 200 $ 5,800.00 197 $ 5,898.18
$ 600.00 $ 153 $ 31,586.85 300 $ 61,935.00
$ 1,000.00 $ - $
$ 5,500.00 $ - $ .
$ 5,750.00 $ $
$ 6,000.00 $ B $ )
$ 3,500.00 1 $ 3,500.00 2 $ 722578 2 8 7,225.78
$ 6,500.00 $ $ -
$ - 1 $ 7,000.00 $ -
$ 200 $ 16,400.00 $ -
$ 190 $ 13,490.00 $
Page 2 of 3
23
24
25
REVISED Additional Addiional ~ Additional Cost Additional ~ Additional Cost Total Quantities 10t3LContract.
DESCRIPTION As Bid Quaniies SROML UNTPRICE gig 7oy Quantites AMUNE Lot gy (Co#2) Quantities (co#3) "(Bid+ Change gf_;’—‘f#——‘;;;"‘—
CNITPRICE - (May 2814 (co#) Lco# (CO#) AtRevisedPrices (CO#3) AtRevisedPrices ~ Orders) =~ ‘ooxoange
Furnish and install all materials and labor for
root removal in 8" gravity sewer pipe prior to
relining as described in the specifications LF$ 150 § 155 § - 15427 $ 23,140.50 3$ - 10000 $ 15,500.00
Furnish and install all materials and labor for
service re-connections in 12" gravity sewer
pipe as described in the specifications EA $ 21000 $ - $ - 1 $ 210.00
Furnish and install all materials and labor for
service relining in 8" gravity sewer pipe as
described in the specifications EA $ 240000 $ - $ - 13 $ 31,200.00
Furnish and install all materials and labor for
service relining in 12" gravity sewer pipe as
described in the specifications EA $ 220000 $ - $ - 1 $ 2,200.00
Totals $288,383.00 $ 193,820.00 $ 636,465.75 $ 975,319.11
As incorrectly submitted in CO #2 (see note below) *s 636,408.73
Note: Value of CO #2 should have been $636,465.75 rather than $636,408.75 as submitted due to rounding errors in the adjusted prices. The $57.02 correction will be added in CO #3.
Page 3 of 3
