The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in
the proper performance of the Work. Such costs shall be at rates not higher than the standard paid at the
place of the Project except with prior consent of the Owner. The Cost of the Work shall include only the
items set forth in this Article 6.1 through 6.7.
§ 6.1.2 Where any cost is subject to the Owner’s prior approval, the Construction Manager shall obtain this
approval prior to incurring the cost. The parties shall endeavor to identify any such costs prior to executing
Guaranteed Maximum Price Amendment.
§ 6.2 Labor Costs
§ 6.2.1 Wages of construction workers directly employed by the Construction Manager to perform the
construction of the Work at the site or. with the Owner's agreement, at off-site workshops.
§ 6.2.2 Wages or salaries of the Construction Manager's supervisory and administrative personnel when
stationed at the site with the Owner's prior approval.
(if it is intended that the wages or salaries of certain personnel stationed at the Construction Manager's principal or other
offices shall be included in the Cost of the Work, identify in Section 11.5, the personnel to be included, whether for ail or
only part of their time, and the rates at which their time will be charged to the Work.)
§ 6.2.3 Wages and salaries of the Construction Manager's supervisory or administrative personne! engaged
at factories, workshops or on the road, in expediting the production or transportation of materials or
equipment required for the Work, but only for that portion of their time required for the Work.
§ 6.2.4 Costs paid or incurred by the Construction Manager for taxes, insurance, contributions, assessments
and benefits required by law or collective bargaining agreements and, for personnel not covered by such
agreements, customary benefits such as sick leave, medical and health benefits, holidays, vacations and
pensions, provided that such costs are based on wages and salaries included in the Cost of the Work under
Sections 6.2.1 through 6.2.3.
§ 6.3 Subcontract Costs
Payments made by the Construction Manager to Subcontractors in accordance with the requirements of
the subcontracts.
§ 6.4 Costs of Materials and Equipment Incorporated in the Completed Construction
§ 6.4.1 Costs, including transportation and storage, of materials and equipment incorporated or to be
incorporated in the completed construction.
§ 6.4.2 Costs of materials described in the preceding Section 6.4.1 in excess of those actually installed to
allow for reasonable waste and spoilage. Unused excess materials, If any, shall become the Owner's
property at the completion of the Work or, at the Owner's option, shall be sold by the Construction Manager.
Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the
Work.
§ 6.5 Costs of Other Materials and Equipment, Temporary Facilities and Related Items
§ 6.5.1 Costs, including transportation, storage, installation, maintenance, dismantling and removal of
materials, supplies, temporary facilities, machinery, equipment, and hand tools not customarily owned by the
construction workers that are provided by the Construction Manager at the site and fully consumed in the
performance of the Work. Costs of materials, supplies, temporary facilities, machinery, equipment and tools
that are not fully consumed shall be based on the cost or value of the item at the time it is first used on the
Project site less the value of the item when it is no longer | used at the Project site. Costs for items not fully
consumed by the Construction Manager shail mean fair market value. .
§ 6.5.2 Rental charges for temporary facilities, machinery, equipment and hand tools not customarily owned
by the construction workers that are provided by the Construction Manager at the site and costs of
Agreement Between: Owner and Construction Manager Page 12 of 19
Contract Type: Construction Manager as Constructor, payment is based on Document No.OCM133
the Cost of the Work Plus a Fee with a Guaranteed Max Price
transportation, installation, minor repairs, dismantling and removal. The total rental cost of any such
Construction Manager-owned item may not exceed the purchase price of any comparable item. Rates of
Construction Manager-owned equipment and quantities of equipment shail be subject to the Owner's prior
approval.
§ 6.5.3 Costs of removal of debris from the site of the Work and its proper and legal disposal.
§ 6.5.4 Costs of document reproductions, facsimile transmissions and long-distance telephone calls,
postage and parcel delivery charges, telephone service at the site and reasonable petty cash expenses of
the site office.
§ 6.5.5 That portion of the reasonable expenses of the Construction Manager's supervisory or administrative
personnel incurred while traveling in discharge of duties connected with the Work.
§ 6.6 Miscellaneous Costs
§ 6.6.1 Premiums for that portion of insurance and bonds required by the Contract Documents that can be
directly attributed to this Contract. Self-insurance for either full or partial amounts of the coverages required
by the Contract Documents, with the Owner's prior approval.
§ 6.6.2 Sales, use or similar taxes imposed by a governmental authority that are related to the Work and for
which the Construction Manager is liable.
§ 6.6.3 Fees and assessments for the building permit and for other permits, licenses and inspections for
which the Construction Manager is required by the Contract Documents to pay.
§ 6.6.4 Fees of laboratories for tests required by the Contract Documents, except those related to
defective or nonconforming Work for which reimbursement is exclude by Section 13.5.3 of Document
GCC201 or by other provisions of the Contract Documents, and which do not fall within the scope of Section
6.7.3.
§ 6.6.5 Royalties and license fees paid for the use of a particular design, process or product required by the
Contract Documents; the cost of defending suits or claims for infringement of patent rights arising from such
requirement of the Contract Documents; and payments made in accordance with legal judgments against
the Construction Manager resulting from such suits or claims and payments of settlements made with the
Owner’s consent. However, such costs of legal defenses, judgments and settlements shall not be included
in the calculation of the Construction Manager's Fee or subject to the Guaranteed Maximum Price. If such
royalties, fees and costs are excluded by the last sentence of Section 3.17 of Document GCC201 or other
provisions of the Contract Documents, then they shall not be | included in the Cost of the Work.
§ 6.6.6 Costs for electronic equipment and software, directly related to the Work with the Owner's prior
approval.
§ 6.6.7 Deposits lost for causes other than the Construction Manager's negligence or failure to fulfill a
specific t responsibility in the Contract Documents.
§ 6.6.8 Legal, mediation and arbitration costs, including attorneys’ fees, other than those arising from
disputes between the Owner and Construction Manager, reasonably incurred by the Construction Manager
after the execution of this Agreement in the performance of the Work and with the Owner's prior approval,
which shall not be unreasonably withheld.
§ 6.6.9 Subject to the Owner's prior approval, expenses incurred in accordance with the Construction
Manager's standard written personnel policy for relocation and temporary living allowances of the
Construction Manager's personnel required for the Work.
§ 6.7 Other Costs and Emergencies
§ 6.7.1 Other costs incurred in the performance of the Work if, and to the extent, approved in advance in
writing by the Owner.
Agreement Between: Owner and Construction Manager Page 13 of 19
Contract Type: Construction Manager as Constructor, payment is based on Document No. OCM133
the Cost of the Work Plus a Fee with a Guaranteed Max Price
§ 6.7.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency
affecting the safety of persons and property, as provided in Section 10.4 of Document GCC201.
§ 6.7.3 Costs of repairing or correcting damaged or nonconforming Work executed by the Construction
Manager, Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused
by negligence or failure to fulfill a specific responsibility of the Construction Manager and only to the extent
that the cost of repair or correction is not recovered by the Construction Manager from insurance, sureties,
Subcontractors, suppliers, or others.
§ 6.7.4 The costs described in Sections 6.1 through 6.7 shall be included in the Cost of the Work,
notwithstanding any provision of Document GCC201 or other Conditions of the Contract which may require
the Construction Manager to pay such costs, unless such costs are excluded by the provisions of Section
6.8.
§ 6.8 Costs Not To Be Reimbursed
§ 6.8.1 The Cost of the Work shall not include the items listed below:
.1 Salaries and other compensation of the Construction Manager’s personnel stationed at the
Construction Manager's principal office or offices other than the site office, except as specifically
provide in Section 6.2, or as may be provide in Article 11;
.2 Expenses of the Construction Manager's principal office and other offices other than the site office:
.3 Overhead and general expenses, expect as may be expressly included ins Section 6.1 to 6.7;
.4 The Construction Manager's capital expenses, including interest on the Construction Manager’s
capital employed for the Work;
.5 Expect as provided in Section 6.7.3 of this Agreement, costs due to the negligence or failure of the
Construction Manager, Subcontractors and suppliers or anyone directly or indirectly employed by
any of them or for whose acts any of them bay be liable to fulfill a specific responsibility of the
Contract;
.6 Any cost not specifically and expressly described in Sections 6.1 to 6.7;
.7 Costs, other than costs included in Change Orders approved by the Owner, that would cause the
Guaranteed Maximum Price to be exceeded; and .
8 Costs for services incurred during the Preconstruction Phase.
§ 6.9 Discounts, Rebates and Refunds
§ 6.9.1 Cash discounts obtained on payments made by the Construction Manager shall accrue to the Owner
if (1) before making the payment, the Construction Manager included them in an Application for Payment and
received payment from the Owner, or (2) the Owner has deposited funds with the Construction Manager
with which to make payments; otherwise, cash discounts shall accrue to the Construction Manager. Trade
discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall
accrue to the Owner, and the Construction Manager shall make provisions so that they can be obtained.
§ 6.9.2 Amounts that accrue to the Owner in accordance with the provisions of Section 6.9.1 shall be
credited to the Owner as a deduction from the Cost of the Work.
§ 6.10 Related Party Transactions
§ 6.10.1 For purposes of Section 6.10, the term “related party” shall mean a parent, subsidiary, affiliate or
other entity | having common ownership or management with the Construction Manager; any entity in which
any stockholder in, or management employee of, the Construction Manager owns any interest in excess of
ten percent in the aggregate; or any person or entity which has the right to control the business or affairs of
the Construction Manager. The term “related party” includes any member of the immediate family of any
person identified above.
§ 6.10.2 If any of the costs to be reimbursed arise from a transaction between the Construction Manager
and a related party, the Construction Manager shall notify the Owner of the specific nature of the
contemplated transaction, including the identity of the related party and the anticipated cost to be incurred,