Okaloosa County BOCC — May 17, 2016 — FDOT LAP Agreement 433572-2 — reading text
Part 2 of 9. These parts divide the reading text for browsing; they are not the source document's page numbers.
FDOT LAP Agreement 433572-2 — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
disbursements of Project funds only in conformity
with the latest approved schedule of funding for the Project. The schedule of funding may be revised by
execution of a Local Agency Program (“LAP”) Supplemental Agreement between the Department and the
Agency. The Agency acknowledges and agrees that funding for this project may be reduced upon
determination of the agency’s contract award amount. If revised, a copy of the Supplemental Agreement
shall be forwarded to the Department's Comptroller. No increase or decrease shall be effective unless it
complies with fund participation requirements of this Agreement and is approved by the Department’s
Comptroller.
J. If, after Project completion, any claim is made by the Department resulting from an audit or for work or
services performed pursuant to this Agreement, the Department may offset such amount from payments
due for work or services done under any agreement which it has with the Agency owing such amount if,
upon demand, payment of the amount is not made within 60 days to the Department. Offsetting any
amount pursuant to this paragraph shall not be considered a breach of contract by the Department.
K. The Agency must submit the final invoice on the Project to the Department within 120 days after the
completion of the Project. Invoices submitted after the 120-day time period may not be paid.
L. The Department’s performance and obligation to pay under this Agreement is contingent upon an annual
appropriation by the Legislature. If the Department's funding for this Project is in multiple fiscal years,
funds approval from the Department's Comptroller must be received each fiscal year prior to costs being
incurred. See Exhibit “B” for funding levels by fiscal year. Project costs utilizing these fiscal year funds
are not eligible for reimbursement if incurred prior to funds approval being received. The Department will
notify the Agency, in writing, when funds are available.
M. In the event this Agreement is in excess of $25,000 and has a term for a period of more than one year,
the provisions of Section 339.135(6)(a), Florida Statutes, are hereby incorporated:
"The Department, during any fiscal year, shall not expend money, incur any liability, or
enter into any contract which, by its terms, involves the expenditure of money in excess
of the amounts budgeted as available for expenditure during such fiscal year. Any
contract, verbal or written, made in violation of this subsection is null and void, and no
money may be paid on such contract. The Department shall require a statement from the
comptroller of the Department that funds are available prior to entering into any such
contract or other binding commitment of funds. Nothing herein contained shall prevent
the making of contracts for periods exceeding 1 year, but any contract so made shall be
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525-010-40
PROGRAM MANAGEMENT
LOCAL AGENCY PROGRAM AGREEMENT OGC– 08/15
Page 4 of 15
executory only for the value of the services to be rendered or agreed to be paid for in
succeeding fiscal years, and this paragraph shall be incorporated verbatim in all contracts
of the Department which are for an amount in excess of $25,000 and which have a term
for a period of more than 1 year."
6. Department Payment Obligations: Subject to other provisions of this Agreement, the Department will honor
requests for reimbursement to the Agency pursuant to this Agreement. However, notwithstanding any other provision of
this Agreement, the Department may elect by notice in writing not to make a payment if:
A. The Agency shall have made misrepresentation of a material nature in its application, or any supplement
or amendment to its application, or with respect to any document or data furnished with its application or
pursuant to this Agreement;
B. There is any pending litigation with respect to the performance by the Agency of any of its duties or
obligations which may jeopardize or adversely affect the Project, the Agreement or payments to the
Project;
C. The Agency shall have taken any action pertaining to the Project which, under this Agreement, requires
the approval of the Department or has made a related expenditure or incurred related obligations without
having been advised by the Department that same are approved;
D. There has been any violation of the conflict of interest provisions contained in paragraph 16.J.; or
E. The Agency has been determined by the Department to be in default under any of the provisions of the
Agreement.
The Department may suspend or terminate payment for that portion of the Project which the Federal Highway
Administration (“FHWA”), or the Department acting in lieu of FHWA, may designate as ineligible for Federal-aid.
In determining the amount of the payment, the Department will exclude all Project costs incurred by the Agency prior to
the Department’s issuance of a Notice to Proceed (“NTP”), costs incurred after the expiration of the Agreement, costs
which are not provided for in the latest approved schedule of funding in Exhibit “B” for the Project, costs agreed to be
borne by the Agency or its contractors and subcontractors for not meeting the Project commencement and final invoice
time lines, and costs attributable to goods or services received under a contract or other arrangements which have not
been approved in writing by the Department.
7. General Requirements: The Agency shall complete the Project with all practical dispatch, in a sound,
economical, and efficient manner, and in accordance with the provisions in this Agreement, and all applicable laws. The
Project will be performed in accordance with all applicable Department procedures, guidelines, manuals, standards, and
directives as described in the Department's Local Agency Program Manual, which by this reference is made a part of this
Agreement. Time is of the essence as to each and every obligation under this Agreement.
A. A full time employee of the Agency, qualified to ensure that the work being pursued is complete, accurate,
and consistent with the terms, conditions, and specifications of this Agreement shall be in responsible
charge of the Project, which employee should be able to perform the following duties and functions:
i. Administers inherently governmental project activities, including those dealing with cost, time,
adherence to contract requirements, construction quality and scope of Federal-aid projects;
ii. Maintains familiarity of day to day Project operations, including Project safety issues;
iii. Makes or participates in decisions about changed conditions or scope changes that require
change orders or supplemental agreements;
iv. Visits and reviews the Project on a frequency that is commensurate with the magnitude and
complexity of the Project;
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525-010-40
PROGRAM MANAGEMENT
LOCAL AGENCY PROGRAM AGREEMENT OGC– 08/15
Page 5 of 15
v. Reviews financial processes, transactions and documentation to ensure that safeguards are in
place to minimize fraud, waste, and abuse;
vi. Directs Project staff, agency or consultant, to carry out Project administration and contract
oversight, including proper documentation;
vii. Is aware of the qualifications, assignments and on-the-job performance of the Agency and
consultant staff at all stages of the Project.
B. Once the Department issues the NTP for the Project, the Agency shall be obligated to submit an invoice
or other request for reimbursement to the Department on a quarterly basis, beginning from the day the
NTP is issued. If the Agency fails to submit quarterly invoices to the Department, and in the event the
failure to timely submit invoices to the Department results in the “FHWA” removing any unbilled funding or
the loss of State appropriation authority (which may include the loss of state and federal funds, if there
are state funds programmed to the Project), then the Agency will be solely responsible to provide all
funds necessary to complete the Project and the Department will not be obligated to provide any
additional funding for the Project. The Agency waives the right to contest such removal of funds by the
Department, if the removal is related to FHWA’s withdrawal of funds or if the removal is related to the loss
of State appropriation authority. In addition to the loss of funding for the Project, the Department will also
consider the de-certification of the Agency for future LAP Projects. No cost may be incurred under this
Agreement until after the Agency has received a written NTP from the Department. The Agency agrees to
advertise or put the Project out to bid thirty (30) days from the date the Department issues the NTP to
advertise the Project. If the Agency is not able to meet the scheduled advertisement, the District LAP
Administrator should be notified as soon as possible.
C. If all funds are removed from the Project, including amounts previously billed to the Department and
reimbursed to the Agency, and the Project is off the state highway system, then the Department will have
to request repayment for the previously billed amounts from the Agency. No state funds can be used on
off-system projects, unless authorized pursuant to Exhibit “G”, State Funds Addendum, which will be
attached to and incorporated in this Agreement in the event state funds are used on the Project.
D. In the event that any election, referendum, approval, permit, notice or other proceeding or authorization is
required under applicable law to enable the Agency to enter into this Agreement or to undertake the
Project or to observe, assume or carry out any of the provisions of the Agreement, the Agency will initiate
and consummate, as provided by law, all actions necessary with respect to any such matters.
E. The Agency shall initiate and prosecute to completion all proceedings necessary, including Federal-aid
requirements, to enable the Agency to provide the necessary funds for completion of the Project.
F. The Agency shall submit to the Department such data, reports, records, contracts, and other documents
relating to the Project as the Department and FHWA may require. The Agency shall use the
Department’s Local Agency Program Information Tool and applicable information systems as required.
G. Federal-aid funds shall not participate in any cost which is not incurred in conformity with applicable
federal and State laws, the regulations in 23 Code of Federal Regulations (C.F.R.) and 49 C.F.R., and