Okaloosa County BOCC — October 20, 2015 — DRMP LAPDesign Signed — reading text
Part 2 of 9. These parts divide the reading text for browsing; they are not the source document's page numbers.
DRMP LAPDesign Signed — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Analysis: The Consultant shall analyze and document Roadway Tasks in accordance
with all applicable manuals, guidelines, standards, handbooks, procedures, and current design
memorandums.
Typical Section Package — The Consultant shall provide an approved Typical Section
Package prior to the Phase I plans submittal date.
Pavement Design Package — The Consultant shall provide an approved Pavement Design
Package in accordance with applicable FDOT pavement design manuals prior to the Phase II
plans submittal date.
Horizontal/Vertical Master Design Files — The Consultant shall design the geometrics using
the design standards that are most appropriate with proper consideration given to the
design traffic volumes, design speed, capacity and levels of service, functional classification,
adjacent land use, design consistency and driver expectancy, aesthetics, pedestrian and
bicycle concerns, ADA requirements, elder road user policy, access management, PD&E
documents and scope of work.
Access Management — The Consultant shall incorporate access management standards for
each project in coordination with County staff. The Consultant shall review adopted access
management standards and the existing access conditions (interchange spacing, signalized
intersection spacing, median opening spacing, and connection spacing). Median openings
that will be closed, relocated, or substantially altered shall be shown on plan sheets and
submitted with supporting documentation for review with the Phase I plans submittal.
The County shall provide access management classification information and information
derived from PD&E studies and public hearings to be used by the Consultant.
Cross Section Design Files — The Consultant shall establish and develop cross section design
files in accordance with standard engineering practices.
Traffic Control Analysis — The Consultant shall design a safe and effective Traffic Control
Plan to move vehicular and pedestrian traffic during all phases of construction. The design
shall include construction phasing of roadways ingress and egress to existing property
owners and businesses, routing, signing and pavement markings, and detour quantity
tabulations, roadway pavement, drainage structures, ditches, front slopes, back slopes, drop
offs within clear zone, and traffic monitoring sites. Special consideration shall be given to
the construction of the drainage system when developing the construction phases. Positive
drainage must be maintained at all times. The design shall include construction phasing of
roadways to accommodate the construction or relocation of utilities when the contract
includes Joint Project Agreements (JPAs).
3/23
TASK ORDER AGREEMENT FOR CONSULTANT SERVICES
(LAP DESIGN CONTINUING SERVICES AGREEMENT)
The Consultant shall investigate the need for temporary traffic signals, temporary lighting,
alternate detour roads, and the use of materials such as sheet piling in the analysis. The
Traffic Control Plan shall be prepared by a certified designer who has completed training as
required by the County. Before proceeding with the Traffic Control Plan, the Consultant
shall meet with the appropriate County personnel. The purpose of this meeting is to
provide information to the Consultant that will better coordinate the Preliminary and Final
Traffic Control Plan efforts.
The Consultant shall consider the local impact of any lane closures or alternate routes.
When the need to close a road is identified during this analysis, the Consultant shall notify
the County's Project Manager as soon as possible. Proposed road closings must be
reviewed and approved by the County. Diligence shall be used to minimize negative
impacts by appropriate specifications, recommendations or plans development. Local
impacts to consider will be local events, holidays, peak seasons, detour route deterioration
and other eventualities. Consultant shall be responsible to obtain local authorities
permission for use of detour routes not on state highways.
Master TCP Design Files — The Consultant shall develop master Traffic Control Plan (TCP)
files (for Level II and Level III only) showing each phase of the Traffic Control Plan.
Design Variations and Exceptions — The Consultant shall prepare the documentation
necessary to gain County approval of all appropriate Design Variations and/or Design
Exceptions before the Phase 1 submittal.
Design Report — The Consultant shall prepare all applicable report(s) as listed in the section
below.
The Consultant shall submit to the County design notes, data, and calculations to document
the design conclusions reached during the development of the contract plans. The design
notes, data, and computations shall be recorded on size 8½"x11" sheets, fully titled,
numbered, dated, indexed and signed by the designer and the checker. Computer output
forms and other oversized sheets shall be folded to 8½"x11" size. The data shall be in a
hardback folder for submittal to the County.
Quantities — The Consultant shall prepare all required summary of quantities sheets. This
includes all efforts required to develop accurate quantities and the supporting
documentation, including construction days when required.
Roadway Plans: The Consultant shall prepare Roadway, Drainage, Traffic Control, Utility
Adjustment plan sheets, notes, and details. The plans shall include the sheets necessary to
convey the intent and scope of the project for the purposes of construction.
Drainage Analysis — The Consultant shall analyze and document Drainage Tasks in
accordance with all applicable manuals, guidelines, standards, handbooks, procedures, and
current design practices.
The Consultant shall be responsible for designing a drainage and stormwater management
system. All engineering analyses and design work shall comply with the requirements of the
appropriate regulatory agencies and the County’s Drainage Manual.
The Consultant shall coordinate fully with the appropriate permitting agencies and the
County’s staff. All activities and submittals should be coordinated through the County’s
Project Manager.
4/23
TASK ORDER AGREEMENT FOR CONSULTANT SERVICES
(LAP DESIGN CONTINUING SERVICES AGREEMENT)
Utilities Coordination — The Consultant shall identify utility facilities and secure
agreements, utility work schedules, and plans from the Utility Agency Owners (UAO)
ensuring all conflicts that exist between utility facilities and the County’s construction
project are addressed. The Consultant shall certify all utility negotiations have been
completed and that arrangements have been made for utility work to be undertaken.
The Consultant is responsible to certify that all necessary arrangements for utility work on
this project have been made and will not conflict with the physical construction schedule.
The Consultant should coordinate with County personnel to coordinate transmittals to
Utility Companies and meet production schedules.
Environmental Permits, Compliances, and Clearances — The Consultant shall notify the
County Project Manager, Environmental Permit Coordinator and other appropriate
personnel in advance of all scheduled meetings with the regulatory agencies to allow a
County representative to attend. The Consultant shall copy in the Project Manager and the
Environmental Permit Coordinator on all permit related correspondence and meetings.
The Consultant shall perform preliminary project research and shall be responsible for early
identification of and coordination with the appropriate regulatory agencies to assure that
design efforts are properly directed toward permit requirements.
Preparation of detail sheets for potential environmental issues such as, underground fuel
tanks and monitoring wells, septic tanks within the proposed right of way. All piping and
pumps in association with the above referenced issues shall also be located and identified
by the survey. The Consultant shall relay to the County any findings of contaminated soil,
monitoring wells, or any features (particularly springs or sinks) relating to contamination or
hazardous material.
Signing and Pavement Markings — The Consultant shall analyze and document Signing and
Pavement Markings Tasks in accordance with all applicable manuals, guidelines, standards,
handbooks, procedures, and current design memorandums.
The Consultant shall prepare a set of Signing and Pavement Marking Plans in accordance
with all applicable manuals, guidelines, standards, handbooks, procedures, and current
design practices.
Traffic Data Analysis — The Consultant shall review the approved preliminary engineering
report (if applicable), typical section package, traffic technical memorandum and proposed
geometric design alignment to identify proposed sign placements and roadway markings.
Perform queue analysis (if required).
Survey: The Consultant shall perform survey tasks in accordance with all applicable statutes
(Florida Statues, Chapter 472), manuals, guidelines, standards, handbooks, procedures, and
current design practices.
The Consultant shall submit all survey notes and computations to document the surveys. All field
survey work shall be recorded in approved media and submitted to the County. Field books
submitted to the County must be of an approved type. The field books shall be certified by the
surveyor in responsible charge of work being performed before the final product is submitted.
The survey notes shall include documentation of decisions reached from meetings, telephone
conversations or site visits. All like work (such as bench lines, reference points, etc.) shall be
recorded contiguously. The County may not accept field survey radial locations of section
5/23
TASK ORDER AGREEMENT FOR CONSULTANT SERVICES
(LAP DESIGN CONTINUING SERVICES AGREEMENT)
corners, platted subdivision lot and block corners, alignment control points, alignment control
reference points and certified section corner references. The County may instead require that
these points be surveyed by true line, traverse or parallel offset.
Horizontal Project Control (HPC) — Establish or recover HPC, for the purpose of establishing
horizontal control on the Florida State Plane Coordinate System or datum approved by the
County Surveyor; may include primary or secondary control points. Includes analysis and
processing of all field collected data, and preparation of forms.
Vertical Project Control (VPC) — Establish or recover VPC, for the purpose of establishing
vertical control on datum approved by the County Surveyor; may include primary or
secondary vertical control points. Includes analysis and processing of all field collected data,
and preparation of forms.
Alignment and/or Existing Right of Way (R/W) Lines — Establish, recover or re-establish
project alignment. Also includes analysis and processing of all field collected data, existing
maps, and/or reports for identifying mainline, ramp, offset, or