READ ALONGSIDE THE SOURCE
Fort Walton Beach Resolution — 96-25-Amendment of DRI for Pirates Bay — reading text
Part 3 of 5. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — fwb-8513-original.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
parking spaces at an
attraction or recreational facility by 5 percent or 300
spaces, whichever is greater, or an increase in the
number of spectators that may be accommodated at such a
facility by 5 percent or 1, 000 spectators, whichever is
greater.
Impact: Not applicable, no parking spaces are to be
added to the development plan.
c 2. A new runway, a new terminal facility, a 10 percent
expansion to an existing runway, or a 20 percent
increase in the floor area of an existing terminal.
Impact: Not applicable, the project does not involve
an airport.
3. An increase in the number of hospital beds by 5 percent
or 60 beds, whichever is greater.
Impact: Not applicable, the project does not involve
a hospital.
4. An increase in industrial development area by 5 percent
or 32 acres, whichever is greater.
Impact: Not applicable, there are no proposed
industrial uses in the NOC.
s. An increase in the average annual acreage mined by 5
percent or 10 acres, whichever is greater, or an
increase in the average daily water consumption by a
mining by 5
operation percent or 300, 000 gallons,
whichever is
greater. An increase in the size of the
mine by 5 percent or 750 acres, whichever is less.
Page 6
Pirates' Bay . 0 o
Nov. 1, 1996
Impact: Not applicable, there are no recreational
vehicle
c park spaces proposed.
13. A decrease in the area set aside for open space of 5
percent or 20 acres, whichever is less.
Impact: The area where the proposed bulkhead is to be
located is currently designated for open space and will
diminish that area less than 1, 000 square feet.
14. A proposed increase to an approved multi- use development
of regional impact where the sum of the increases of
each land use as a percentage of the applicable
substantial deviation criteria is equal or exceeds 100
percent. The percentage of any decline in the amount of
open space shall be treated as an increase for purposes
of determining when 100 percent has been reached or
exceeded.
Impact: Not applicable, the proposed structure is not
classified as one of multi- use land use types, office,
port, etc.
15. A 15 percent increase in the number of vehicle
trips
generated by the development above which was projected
during the original development- of- regional- impact
review.
c Impact: Not applicable, the will
proposed change not
alter the number of vehicle trips generated by the
development.
16. Any change which would result in the development of any
area which specifically set aside in the
was
application for
development approval or in the
development order for preservation or special
protection of endangered or threatened plants or animals
designated as endangered, threatened or species of
special concern and their habitat, primary dunes, or
archaeological and historic sites designated as
significant by the Division of Historical Resources of
the Department of State.
Impact: The DRI site contains an archaeological site,
a black sand midden, which lies slightly landward
from the proposed location of the bulk head site as
identified in the attached " Figure 9. Pirates'
Bay Archaeological Site 80K183 In Relation To
Proposed Construction" from the original Application for
Development Approval( ADA). Staff will receive
appropriate comments regarding this issue from the
Department of State Staff.
r'
Page 7
Pirates' Bay 0 o
Nov. 1, 1996
Staff Comment: other than whatever impact the proposed change
might have on the archaeological site, there does not appear
c to be any substantial change to the previously approved
development plan.
19)( c) An extension of the date of build out of a
development, any phase or by years shall
there of, 7 or more
be presumed to create a substantial deviation subject to
further development- of- regional- impact review.
Staff Comment: Not applicable.
19)( d) change in the plan of development of an approved
A
development of regional impact resulting from requirements
imposed by the DEP or any water management district or any
appropriate federal agency shall be submitted to the local
government pursuant to this subsection. The change shall be
presumed not to create a substantial deviation subject to
further review. The presumption may be rebutted by clear and
convincing evidence at the public hearing held by the local
government.
Staff Comment: Not applicable, the changes are not as a
result of other agency action.
19)( e) 1. A proposed change which, either individually or,
c if there were previous changes, cumulatively with those
changes, is equal to 40 percent of any numerical criterion in
subparagraphs ( b) 1.- 15., but which does not exceed such
criterion, shall be presumed not to create a substantial
deviation subject to further DRI review. The presumption may
be rebutted by clear and convincing evidence presented at the
public hearing.
Staff Comment: None of the
previously changes have
cumulatively or individually equalled as much as a forty
percent total of any criterion.
19)( e) 2. A proposed change that individually or cumulatively
with any previous change is less than 40 percent of any
numerical criterion and does not exceed any other criterion,
or that involves the extension of the build out date less
than 5 years is not subject to the public hearing
requirements.
Staff Comment: The proposed change to the development order
does not exceed any of the criterion nor is it a request for
an extension of the build out time.
19)( e) 3. Any addition of land previously reviewed or
not
any change specified not in paragraphs ( b) or ( c) shall be
c presumed to create a substantial deviation. This presumption
Page 9
Pirates' Bay
u 6
Nov. 1, 1996
process for marine construction for piers, docks, boathouses
or bulkheads when these structures are
required to be
permitted under State Statutes.
City Council has retained jurisdiction to authorize all
marine construction under the following process:
1) The applicant shall submit to the Department of Community
Development Services( CDS) copies of applications, plans and