READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — January 19, 2016 — FWC Grant — reading text
Part 10 of 14. These parts divide the reading text for browsing; they are not the source document's page numbers.
FWC Grant — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
will be placed on the deployment vessel. The COMMISSION will approve all materials prior
to deployment.
i. Minimum Level of Performance
Each artificial reef must be deployed within the boundaries of the permitted area, at
the approximate center point of each permit area and in compliance with all the
applicable permits and authorizations associated with the permitted area. The
minimum acceptable level of performance is the placement of two patch reefs of
approximately equal size composed of inspected COMMISSION and GRANTEE
approved pre-cast concrete culvert and steel reinforced concrete manholes and beams
or concrete and steel target material deployed at the center points of two Okaloosa
County Fish Haven permitted artificial reef locations (FH 15 and16) in accordance
with the specifications in this Agreement. The patch reef footprint and vertical relief
of the tightly stacked material deployed from a double anchored vessel will depend
upon the maximum tonnage of reef material that can be transported and deployed with
total funding not to exceed $60,000 provided by the COMMISSION and $67,000
provided by the GRANTEE.
ii. Documentation / Criteria Used as Evidence of Performance
1. A Materials Placement Report shall be submitted to the COMMISSION's
Project Manager within 30 days of field operations completion. The Materials
Placement Report form is available on the COMMISSION’s website at
http://www.myfwc.com/conservation/saltwater/artificial-reefs/. The Materials
Placement Report must have a certification signature and reflect an accurate
material tonnage for the reef deployed as well as a detailed description of the
type, number, dimensions and overall tonnage of the various sizes of reef
materials deployed. This information may be submitted on the materials
placement report in lieu of taking loaded and unloaded barge measurements.
If accurate individual weights of concrete units cannot be obtained or are not
known, barge displacement measurements are required. The GRANTEE's
Project Manager or GRANTEE’s designee shall then record the waterline
length, width and draft (to the nearest inch) of the loaded barge at all four (4)
Version 1.0 – June 2013 Attachment A, Page 7 of 12
Attachment A – SCOPE OF WORK
Project Name: Okaloosa County Artificial Reef FWC Agreement No. 15274
Construction 2016-17
corners to calculate the average displacement of water due to the weight of the
artificial reef materials. The same barge measurements must be taken by either
the GRANTEE's Project Manager or GRANTEE’s designee when the barge
returns to shore after the deployment has been completed. These
measurements may not be taken while the barge is offshore at the deployment
site. The barge measurements are to be included in the Materials Placement
Report.
2. A final field report providing the designated observer's narrative, for each day
of the reef deployment operations, is required prior to reimbursement. The
field report shall include a written chronology and narrative describing details
of the deployment, and a performance evaluation of the marine contractors
who performed the work. The final field report should include photos of the
material and loaded barge prior to each deployment and, if available,
underwater photographs and video footage (surface and/or underwater).
iii. Timeline for Completion
All artificial reef construction must be completed by December 31,2016. Advance
planning that avoids dependence on a favorable weather window during the final weeks
of the project is strongly encouraged. All requests for bid packages from the
GRANTEE to potential contractors must include language that specifies a completion
date that ensures all materials will be in the water by December 31, 2016. Subcontracts
with completion dates significantly earlier than December 31, 2016 to provide an
additional buffer are strongly encouraged.
FINANCIAL CONSEQUENCES
B. If the GRANTEE fails to complete construction within the time frame specified by the Scope
of Work, the budget amount allocated for that portion of the construction project deliverable
not yet completed at the expiration of the Agreement will be deducted from the GRANTEE’s
payment.
C. The GRANTEE will not be eligible for reimbursement until all reports have been provided
to the satisfaction of the COMMISSION documenting that all work has been completed in
accordance with the Scope of Work, and in compliance with all permit conditions.
3. PERFORMANCE
A. Written or electronically transmitted progress reports must be sent to the COMMISSION's
Contract Manager at no less than 60 day intervals beginning from the date of execution of this
agreement.
B. The GRANTEE agrees to provide the COMMISSION with a minimum of five (5) days
notice for any artificial reef construction that occurs as a result of this Agreement.
Version 1.0 – June 2013 Attachment A, Page 8 of 12
Attachment A – SCOPE OF WORK
Project Name: Okaloosa County Artificial Reef FWC Agreement No. 15274
Construction 2016-17
C. The GRANTEE agrees to follow all provisions of Section 379.249, Florida Statutes and
Chapter 68E-9, Florida Administrative Code during the term of this Agreement.
D. The GRANTEE agrees to comply with all applicable federal, state, and local statutes, rules
and regulations in providing goods or services to the COMMISSION under the terms of this
Agreement; including the general and special conditions specified in any permits issued by
the Department of the Army, Corps of Engineers and/or the Florida Department of
Environmental Protection. The GRANTEE further agrees to include this as a separate
provision in all subcontracts issued as a result of this Agreement.
E. Funds from this Agreement may not be expended on salaries, training, or parts replacement
or repairs to rented or contractor owned equipment. Documentation of expenses and survey
reports must be submitted with the closeout package in order for reimbursement to be made.
4. COMPENSATION AND PAYMENT
A. COST REIMBURSEMENT
The GRANTEE shall be compensated for a maximum of $60,000 on a cost reimbursement
basis in accordance with the Cost Reimbursement Contract Payment Requirements as shown
in the Department of Financial Services, “Reference Guide for State Expenditures”
publication. The cost reimbursement requirements section of the Reference Guide is attached
hereto and made a part hereof as Attachment D. .
B. INVOICE SCHEDULE
A single final invoice may be submitted after completion of the deliverable and must be
received by the COMMISSION no later than February 15, 2017 to assure availability of funds
for payment. A timely reimbursement request following completion of actual field operations
is strongly encouraged.
C. TRAVEL EXPENSES
No travel expenses are authorized under the terms of this Agreement.
D. FORMS AND DOCUMENTATION
The GRANTEE shall submit a completed Materials Placement Report form along with the
invoice and request for payment. The Materials Placement Report form is available on the
COMMISSION’s website at: www.myfwc.com/conservation/saltwater/artificial-reefs.
5. MONITORING SCHEDULE
A. The GRANTEE agrees to allow the COMMISSION to conduct on-site inspections of the
artificial reef materials, staging areas and vessel deployment platform before, during, and after
the deployment.
Version 1.0 – June 2013 Attachment A, Page 9 of 12
Attachment A – SCOPE OF WORK
Project Name: Okaloosa County Artificial Reef FWC Agreement No. 15274
Construction 2016-17
B. No additional monitoring activities have been identified at this time.
6. INTELLECTUAL PROPERTY RIGHTS
See Agreement for applicable terms and conditions related to the intellectual property rights.
7. SUBCONTRACTS
A. The GRANTEE agrees to follow all requirements of Section 287.057, Florida Statutes, for
the procurement of commodities or contractual services under this Agreement. The
GRANTEE will obtain a minimum of three written quotes for any subcontracts required for
Agreements in the amount of $35,000 or less, and the GRANTEE will publicly advertise and
send bid specifications to a minimum of five (5) potential subcontractors for any subcontracts
required for Agreements in excess of $35,000.
B. The use of a vendor registered with the Statewide Negotiated Agreement Price Schedule
(SNAPS) does not preclude the GRANTEE from the requirements of Paragraph A.
C. The GRANTEE shall submit bid specifications to the COMMISSION 's Contract Manager
for approval within ninety (90) days following the execution date of this Agreement. The
COMMISSION shall provide comments on the bid specifications to the GRANTEE within
30 days following submittal.
D. All bid specifications must be approved, in writing, in advance by the COMMISSION's
Contract Manager, prior to public advertisement or distribution.
E. Any request to use a sole source vendor by the GRANTEE must be requested and justified in
writing and approved by the COMMISSION's Contract Manager prior to awarding a sole
source subcontract under this Agreement.
F. A summary of the vendor replies and recommended contractor must be sent by the
GRANTEE to the COMMISSION's Contract Manager for review of the County’s
recommendation prior to the awarding of any contracts under this Agreement.
G. Contracts for offshore transport and placement of artificial reef material shall be prepared such
that upon initiation of the handling and movement of these artificial reef materials by the
GRANTEE’s contractor, all liability, risk of loss and responsibility for the safe handling,
storage, transportation and deployment of the materials shall be borne by the contractor. This