READ ALONGSIDE THE SOURCE
Fort Walton Beach Resolution — 2021-08--Funding for SR 189 Traffic Analysis — reading text
Part 2 of 9. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — fwb-40270-original.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
incorporated in this
Agreement. The Schedule of Financial Assistance may be modified by execution of an amendment of the
Agreement by the Parties.
b. The Department agrees to participate in the Project cost up to the maximum amount of $ 100, 000 and,
exceed 66. 7% of the total cost of the
additionally the Department' s participation in the Project shall not
Project, and as more fully described in Exhibit " B". The Department' s participation may be increased or
reduced upon a determination of the actual bid amounts of the Project by the execution of an
amendment. The Recipient agrees to bear all expenses in excess of the amount of the Department' s
participation and any cost overruns or deficits incurred in connection with completion of the Project.
c. The Department' s participation in eligible Project costs is subject to, but not limited to:
i. Legislative approval of the Department' s appropriation request in the work program year that the
Project is scheduled to be committed;
ii. Approval of all plans, specifications, contracts or other obligating documents and all other terms of
this Agreement; and
Page 2 of 14
525-010- 60
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
PROGRAM MANAGEMENT
STATE- FUNDED GRANT AGREEMENT 10/ 0
iii. Department approval of the Project scope and budget at the time appropriation authority becomes
available.
7. Compensation and Payment:
a. The Department shall reimburse the Recipient for costs incurred to perform services described in the
Project Description and Responsibilities in Exhibit " A", and as set forth in the Schedule of Financial
Assistance in Exhibit " B".
b. The Recipient shall provide quantifiable, measurable, and verifiable units of deliverables. Each deliverable
must specify the required minimum level of service to be performed and the criteria for evaluating successful
completion. The Project and the quantifiable, measurable, and verifiable units of deliverables are described
more fully in Exhibit " A", Project Description and Responsibilities. Any changes to the deliverables shall
require an amendment executed by both parties.
c. Invoices shall be submitted no more often than monthly and no less than quarterly by the Recipient in detail
sufficient for a proper pre- audit and post-audit, based on the quantifiable, measurable and verifiable
deliverables as established in Exhibit" A". Deliverables and costs incurred must be received and approved
by the Department prior to reimbursements. Requests for reimbursement by the Recipient shall include an
invoice, progress report and supporting documentation for the period of services being billed that are
acceptable to the Department. The Recipient shall use the format for the invoice and progress report that
is approved by the Department.
d. Supporting documentation must establish that the deliverables were received and accepted in writing by
the Recipient and must also establish that the required minimum standards or level of service to be
performed based on the criteria for evaluating successful completion as specified in Exhibit " A" has been
met. All costs invoiced shall be supported by properly executed payrolls, time records, invoices, contracts
or vouchers evidencing in proper detail the nature and propriety of charges as described in Exhibit " F",
Contract Payment Requirements.
e. Travel expenses are not compensable under this Agreement.
f. Payment shall be made only after receipt and approval of deliverables and costs incurred unless advance
payments are authorized by the Chief Financial Officer of the State of Florida under Chapters 215 and 216,
Florida Statutes or the Department' s Comptroller under Section 334. 044( 29), Florida Statutes.
If the Department determines that the performance of the Recipient is unsatisfactory, the Department shall
notify the Recipient of the deficiency to be corrected, which correction shall be made within a time-frame to
be specified by the Department. The Recipient shall, within thirty( 30) days after notice from the Department,
provide the Department with a corrective action plan describing how the Recipient will address all issues of
contract non- performance, unacceptable performance, failure to meet the minimum performance levels,
deliverable deficiencies, or contract non- compliance. If the corrective action plan is unacceptable to the
Department, the Recipient will not be reimbursed to the extent of the non- performance. The Recipient will
not be reimbursed until the Recipient resolves the deficiency. If the deficiency is subsequently resolved, the
Recipient may bill the Department for the unpaid reimbursement request( s) during the next billing period. If
the Recipient is unable to resolve the deficiency, the funds shall be forfeited at the end of the Agreement' s
term.
Recipients receiving financial assistance from the Department should be aware of the following time
frames. Inspection and approval of deliverables and costs incurred shall take no longer than 20 days
from the Department' s receipt of the invoice. The Department has 20 days to deliver a request for
payment (voucher) to the Department of Financial Services. The 20 days are measured from the latter of
the date the invoice is received or the deliverables and costs incurred are received, inspected, and
approved.
If a payment is not available within 40 days, a separate interest penalty at a rate as established pursuant
Florida Statutes, will be due and payable, in addition to the invoice amount, to the
to Section 55. 03( 1),
Recipient. Interest penalties of less than one ( 1) dollar will not be enforced unless the Recipient requests
Page 3 of 14
525- 010- 60
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
PROGRAM NT
STATE- FUNDED GRANT AGREEMENT MANAGEMD/
payment. Invoices that have to be returned to a Recipient because of Recipient preparation errors will
result in a delay in the payment. The invoice payment requirements do not start until a properly
completed invoice is provided to the Department.
A Vendor Ombudsman has been established within the Department of Financial Services. The duties of
this individual include acting as an advocate for Recipient who may be experiencing problems in obtaining
timely payment( s) from a state agency. The Vendor Ombudsman may be contacted at ( 850) 413- 5516.
g. The Recipient shall maintain an accounting system or separate accounts to ensure funds and projects are
tracked separately. Records of costs incurred under the terms of this Agreement shall be maintained and
made available upon request to the Department at all times during the period of this Agreement and for five
years after final payment is made. Copies of these documents and records shall be furnished to the
Department upon request. Records of costs incurred include the Recipient' s general accounting records
and the project records, together with supporting documents and records, of the contractor and all
subcontractors performing work on the project, and all other records of the contractor and subcontractors
considered necessary by the Department for a proper audit of costs.
h. Progress Reports. Upon request, the Recipient agrees to provide progress reports to the Department in
the standard format used by the Department and at intervals established by the Department. The
Department will be entitled at all times to be advised, at its request, as to the status of the Project and of
details thereof.
i. If, after Project completion, any claim is made by the Department resulting from an audit or for work or
services performed pursuant to this Agreement, the Department may offset such amount from payments
due for work or services done under any agreement which it has with the Recipient owing such amount if,
upon demand, payment of the amount is not made within 60 days to the Department. Offsetting any amount
pursuant to this paragraph shall not be considered a breach of contract by the Department.
j. The Recipient must submit the final invoice on the Project to the Department within 120 days after the
completion of the Project. Invoices submitted after the 120- day time period may not be paid.
k. The Department' s performance and obligation to pay under this Agreement is contingent upon an annual
appropriation by the Legislature. If the Department' s financial assistance for this Project is in multiple fiscal
years, a notice of availability of funds from the Department' s project manager must be received prior to
for funding levels by fiscal year. Project costs
costs being incurred by the Recipient. See Exhibit " B"
utilizing any fiscal year funds are not eligible for reimbursement if incurred prior to funds approval being
received. The Department will notify the Recipient, in writing, when funds are available.
I. In the event this Agreement is in excess of$ 25, 000 and has a term for a period of more than one year, the
provisions of Section 339. 135( 6)( a), Florida Statutes, are hereby incorporated:
The Department, during any fiscal year, shall not expend money, incur any liability, or
enter into any contract which, by its terms, involves the expenditure of money in excess of
the amounts budgeted as available for expenditure during such fiscal year. Any contract,
verbal or written, made in violation of this subsection is null and void, and no money may
be paid on such contract. The Department shall require a statement from the comptroller
of the Department that funds are available prior to entering into any such contract or other
binding commitment of funds. Nothing herein contained shall prevent the
