CHANGE ORDER FORM
Date: 4/6/14 Contract No.: C13-2026-WS Change Order No.: _3
Owner: __OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS
Contractor, Layne Christensen Company, Inc.
CHANGE TO CONTRACT PRICE
DESCRIPTION AMOUNT
Original Contract Price: $934,895.00
Net change by previously authorized Change Orders: $31,380.00
Present Contract Price: $966,275.00
This Change Order will (add/deedeet): $99,530.00
New Contract Price: $1,065,805.00
CHANGE TO CONTRACT TIME
DESCRIPTION DATE or NUMBER OF DAYS
Original Contract Time: 345 to Substantial/405 to Final
Original Substantial Completion Date: April 11, 2014
Net change by previously authorized Change Orders: 60 days
This Change Order will (add/deetet) : igs to Substantial? tee ke ea
. 558 to Substantial/587 to Final
New Contract Time:
November 10, 2014 Substantial
New Substantial Completion Date: December 11, 2014 Final
—— eee
‘ ; 7 », ; ——— a 7 7 - fad|| ° won fm Pe r- 0)
REQUESTED BY: #5) we Ft DATE: _—<1/7//4 | al | 20"
PROJECT ENGINEER: + Sten) DATE: _ =f 7 7/14
CONTRACTOR: LAA DATE: Sf ¥
OWNER: DATE:
This Change Order is an amendment to the Contract/Agreement between Contractor and the
Owner, and all other contract provisions shall remain in full force and effect unless specifically
amended in writing, signed by both parties.
Contract Change Order No. 3
Project: Del Cerro II (MC-7) Public Supply Well
Contractor: Layne Christensen Company
Background:
The development of the final well has proven that the water bearing formation continues to
produce sand as was observed during the test well phase. Results indicate a gravel pack and
screen is necessary to prevent sand and other deleterious material from migrating from the
formation to the well.
Gravel Packs and Screens are commonly used in unconsolidated aquifers and sometimes used
in consolidated aquifers dependent on the water bearing formation’s lithology. Historically,
Okaloosa County has not experienced wells that required gravel packs and screens and hence,
the need for such was not anticipated and is deemed a changed condition from what was
designed and bid. The gravel pack and screen is required for the Contractor to fulfill the
performance standard set forth in the contract (Ref. paragraph 1.4 Section 02730L).
In addition to adding the Gravel Pack and Screen, this change order revises the minimum
capacity of the well from 1,000 gpm to 750 gpm. Furthermore, due to the problems
encountered during the test well phase and now the need to add the gravel pack and screen, it
is necessary to revise the contract time to allow for its procurement, installation, development,
and testing including time to compensate for all work activities delayed for need of and
dependent on the final well testing and final well hydraulic characteristics. Therefore, this
Change Order adds 153 days to Substantial Completion and 122 days to Final Completion.
Add the following line item to the contract:
Item Description Est. Unit Unit Rate Total Cost
Qnty
15 Furnish and Install Gravel Pack and Screen 1 LS $99 530.00 $99 530.00
as described in Contractor’s letter dated 4-
April-2014 (copy attached) complete and in
place for the lump sum amount of
WATER +» MINERAL
April 4, 2014
Mr. Roy Petrey, PE
VP Florida Operations
Polyengineering
102 Sunset Lane
Shalimar, Fl 32579
RE: Well Screen Installation Quote - Okaloosa Del Cerro
Dear Mr. Petrey,
Layne Christensen Co. performed a preliminary pump test March 28, 2014 to clear
the well and obtain sand concentration measurements. The preliminary test
disclosed some good news and reinforced the fact the well is producing sand
within the lime rock formation.
The new production well yields 12.64gpm per ft. of drawdown @ 1125gpm and
13.63gpm per ft. of drawdown @ 750gpm. Compared to the test well results the
yield increased by 125%. This increase helps reduce the up hole velocity and the
stress on the formation while pumping water.
The increased yield provided the ability to present a long term resolution
removing the sand produced from the well. Layne Christensen Co. is
recommending the installation of a Gravel Packed Stainless Steel Wire Wrapped
Screen.
Key Factors increasing value of well investment with Gravel Pack and
Screen Installation:
e Gravel pack and screen installation is required to meet the performance
standard guarantee set forth in the contract (Ref. paragraph 1.4 Section
02730L)
e Reduce the risk of erosion within the lime rock formation, eliminating the
potential for an increase in sand production and undermining the cased
area.
e Helps eliminate the fine silts from entering the well and prevents turbidity
issues while pumping.
e Prevents premature wear in the pump bowl assembly
e Based on current results the gravel pack and screen will eliminate the
potential need for an above ground and below ground separator.
WATER RESOURCES
4601 N. 252" Street, Valley, NE 68064 | Office: (402) 359-2042 | Fax: (402) 359-2310 | layne.com
> ENERGY
Original well design outlined a well capacity of 1000gpm. Installation of the
gravel pack and screen will revise the minimum flow rate to 750gpm. The gravel
pack and screen will not remove any form of minerals from the water nor will it
eliminate the potential for water treatment.
Layne Christensen is pleased to provide the following quote to furnish and install a
Gravel Packed Stainless Steel Wire Wrapped Screen.
Quote includes the following:
e 16” x 197 ft. of Stainless Steel Wire Wrapped Screen (Slot size will be
determined upon completion of sieve analysis)
16” x 40ft. of Carbon Steel lap pipe
16 estimated 3000Ib sacks of 20/40 gravel pack
Installation of Screen and Gravel Pack
Swab screen area with tight fitting swab and air lift to remove fines and
settle gravel pack. Allowing gravel pack to properly settle into the screen
area.
e Installation and of Test Pump to develop well and test pump
e Installation of (2) 10” Tee’s with Blind Flanges to distribution line
Total Estimated Cost for above iteMs......... cc ccccceeeeeeeesessetees $99,530.00
Approval of the screen, ordering, delivery of the screen, installation, development
and test pumping will create the need for additional contract time. The improved
yield from the well may bring a change to other contract items adding to lead
times for equipment.
Layne Christensen respectfully request an extension of Substantial and Final
Completion Time. Current Substantial Completion Date is June 10,2014 and Final
Completion August 11, 2014 We would like to extend the Substantial Completion
Date to November 10, 2014 and Final Completion Date to December 11, 2014
Chuck Rabold