Okaloosa County BOCC — August 4, 2026 — Cadwell Tanks Agreement
Cadwell Tanks Agreement in the August 4, 2026 Okaloosa County BOCC meeting materials. Preserved county-portal original with machine-extracted reading text.
Preserved among the August 4, 2026 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1998). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used August 15, 2027; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Cadwell Tanks Agreement
Date
August 4, 2026
Publisher
Okaloosa County Board of County Commissioners
Where to find it
328
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Every preserved file is checksummed with SHA-256 when it is added, so any later change to the stored bytes would show. That confirms the file is unchanged since ingest — it does not prove the file matches the original source, who produced it, or when it was captured.
Transcription / extraction
Each reading-text file shows its recorded review status below.
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
Cadwell Tanks Agreement — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
SHOAL RIVER RANK WATER STORAGE TANK APRIL 2026
ITB WS 54-26 POLY JOB NO. 41-492
DOCUMENT 00 52 13 – AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT –
BIDDERS
THIS AGREEMENT is by and between Okaloosa County, a political subdivision of the State of Florida, by and
through its Board of County Commissioners, situated at 1250 N. Eglin Parkway, Shalimar, Florida (“OWNER”) and
Caldwell Tanks, Inc. of 4000 Tower Road, Louisville, KY 40219 (address), certified to do business in the state of
Florida (“CONTRACTOR”).
OWNER and CONTRACTOR hereby agree as follows:
ARTICLE 1 – WORK
CONTRACTOR shall complete all WORK as specified or indicated in the Contract Documents. The
WORK is generally described as follows: SHOAL RIVER RANCH WATER STORAGE TANK.
ARTICLE 2 – THE PROJECT
2.01 The intended Scope of Work is described in the technical specifications in Appendix A of this document.
ARTICLE 3 – ENGINEER
The part of the Project that pertains to the WORK has been designed by Poly, Inc. (Design Engineer).
3.02 The OWNER has retained the Design Engineer (“ENGINEER”) to act as OWNER’s representative, assume
all duties and responsibilities, and have the rights and authority assigned to ENGINEER in the Contract
Documents in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 4 – CONTRACT TIMES
Time of the Essence
a. All time limits for Milestones, if any, Substantial Completion, and completion and readiness
for final payment as stated in the Contract Documents are of the essence of the Contract.
b. Contract Times: Days
i. The Work will be substantially completed within 500 calendar days after the date
when the Contract Times commence to run as provided in Paragraph 4.01 of the
General Conditions, and completed and ready for final payment in accordance with
Paragraph 15.06 of the General Conditions within 560 calendar days after the date
when the Contract Times commence to run.
c. Liquidated Damages
ii. Section 337.18(2) of the Florida Statutes, requires the OWNER adopt regulations
for the determination of default and provisions that the Contractor pay liquidated
damages (daily charge per calendar day) for any failure of the Contractor to
complete the Contract work within the Contract Time.
iii. CONTRACTOR and OWNER recognize that time is of the essence as stated in
Paragraph 4.01 above and that OWNER will suffer financial and other losses if the
Work is not completed and Milestones not achieved within the times specified in
Paragraph 4.02 above, plus any extensions thereof allowed in accordance with the
Contract. The parties also recognize the delays, expense, and difficulties involved in
proving in a legal proceeding the actual loss suffered by OWNER if the Work is not
completed on time. Accordingly, instead of requiring any such proof, OWNER and
CONTRACTOR agree that as liquidated damages for delay. Contractor specifically
Agreement Between Owner & Contractor for Construction Contract Page 00 52 13-1
SHOAL RIVER RANK WATER STORAGE TANK APRIL 2026
ITB WS 54-26
Only a preview is loaded on this record page. The linked reading pages contain the remaining text and work without JavaScript.
Citation & reuse
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — August 4, 2026 — Cadwell Tanks Agreement.” August 4, 2026. Cadwell Tanks Agreement. Crypt of Echoes evidence ID LED-2026-d29047f35d764213a49e1a0b96b2c009. https://cryptofechoes.com/evidence/LED-2026-d29047f35d764213a49e1a0b96b2c009. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, Cadwell Tanks Agreement, meeting materials for August 4, 2026. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=4&ID=49632&MeetingID=1998
Preserved county public-record source. Third-party attachments may retain their original rights.