Okaloosa County BOCC — January 3, 2017 — Change Order No. 2 for Checked Baggage Screening Project — agenda request — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Change Order No. 2 for Checked Baggage Screening Project — agenda request — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: January 3, 2017
TO: Honorable Chairman and Members of the Board
FROM: Tracy Stage
SUBJECT: Change Order No. 2 for Checked Baggage Screening Project
DEPARTMENT: Airport
BCC DISTRICT:
STATEMENT OF ISSUE: The Airports Department requests the Board of County
Commissioners approve Change Order No. 2 with Lord & Son Construction, Inc. to extend the
construction time by 240 days and add $43,683.00 to Contract No. C15-2310-AP in order to
complete the Checked Baggage Screening Project. Staff also requests approval to reallocate the
remaining allowances included within the contract.
BACKGROUND: The construction contract for the Checked Baggage Screening Project at
Destin-Fort Walton Beach Airport (VPS) was issued on July 7, 2015 to Lord and Son
Construction, Inc. and the Notice-to-Proceed was issued on October 1, 2015. The scope of
services to be performed under the contract includes the construction of an in-line Baggage
Handling Conveyor System complete with Explosives Detection System (EDS) machines at the
Destin-Fort Walton Beach Airport.
Change Order No. 1 was approved by the Board on August 2, 2016. It extended the construction
time of the project by 77 days as well as re-allocated the allowances included within the contract.
The Transportation Security Administration (TSA) has requested additional items to further
optimize the system to meet local TSA preferences that were not included in the original
construction documents. In addition, TSA staff limitations delayed a planned transition in the
construction phase. Costs associated with these changes are to be covered by the remaining
Allowance within the Contract ($7,577.00) and available contingency funds within the existing
Other Transaction Agreement with TSA ($76,664). This change order will increase the contract
time by 240 days to a total of 587 giving the contract a new substantial completion date of May
9, 2017. It will also increase the contract price by $43,683.00 to a total of $3,714,183.00.
The project is 100% funded by Other Transaction Agreement (HSTS04-13-H-CT1161) in the
amount of $4,318,169, issued by the Department of Homeland Security.
Attached as back-up to this Agenda Request:
Change Order No. 2 increases the amount of time needed to complete the project and
adds funds to incorporate modifications to the system to enhance functionality. Problems
with the system programming extended the testing time frame and impacted the schedule.
In addition, TSA staff limitations delayed a planned transition to construction phase. The
additional time allows sufficient time to continue to adjust the system to optimize its
performance and complete project closeout including TSA coordination and final
acceptance. A portion of the additional costs associated with these changes are covered
by existing allowances with the contract; the balance will be covered by the existing OTA
Funding Agreement between the County and the TSA. Change Order No. 2 has been
approved by Airports Director, Tracy Stage, Senior Project Manager, Mark Kistler, and
Lord & Son’s President, Leven D. Lord II.
• TSA's digitally signed approval of Change Order No.2, is signed by John L. Reed, TSA's
Regional Director.
• Attachments
A-County Schedule of Value
B-Lord & Son Construction, Inc.'s Additional Cost Proposal
B.1-Lord & Son Construction, Inc.'s Summary Sheet
B.2-Siemens Proposal for additional control pads
B.3-TSA Work Station (Furniture Orders/Receipts)
B.4-Daifuku Logan Teleflex proposal for changes to system per TSA.
C-TSA Change Order Concurrence/Approval Form
• The current Certificate of Insurance expires January 1, 2017. An updated Certificate of
Insurance is attached.
OPTIONS: Accept, Reject, or Table
RECOMMENDATIONS: It is Staff's recommendation that the Board approve Change Order
No. 2 with Lord and Son Construction, Inc. to extend the construction time by 240 calendar days
on their contract No. ClS-2310-AP. Staff also recommends that the Board approve the
reallocation of Allowances included within contract No. ClS-2310-AP.