July 8, 2015
Jim Trifilio
Coastal Management Coordinator
Okaloosa County Tourist Development Council
1540 Miracle Strip Parkway SE
Fort Walton Beach, FL 32548
Re: Okaloosa County RFB No. TDD 47-15, Okaloosa County Artificial Reef Construction Project
Dear Mr. Trifilio,
On June 10, 2015, Okaloosa County opened bid packages for the Okaloosa County Artificial Reef
Construction Project. A total of three competitive bids were received. Coleen Marine, Inc. (Coleen),
based in Virginia Beach, Virginia, was the apparent low bidder.
Per Taylor Engineering’s Scope of Services for the above-referenced project, we have reviewed
Coleen’s bid package. Of note, our review and recommendations are limited to engineering and
technical issues. Taylor Engineering is not responsible for the review and evaluation of contractor’s
financial condition, business licenses or authorizations, bonding, contractual requirements, and any
other non-engineering or non-technical information. Two Coleen representatives attended the
recommended pre-bid meeting and site visit held on May 18, 2015 and the bid package includes the
required submittals (Bid Form, Addenda Acknowledgement, Bid Bond or Check, Equipment List,
Deployment Plan, Schedule and Description of Previous Artificial Reef Experience) and forms (Drug-Free
Workplace, Conflict of Interest, Federal E-Verify Certification, No Contact Clause, Indemnification and
Hold Harmless, Company Data, Anti-Collusion Statement, Certification Regarding Lobbying, and Eglin
Access Affidavits). Coleen also provided proof of authorization to transact business in the State of
Florida within their RFB response package.
Our review also included the following information:
1. Qualifications and past work experience in the field of artificial reef construction.
Taylor Engineering Review: Coleen has been in business since May, 2014; however, their
targeted key personnel have vast artificial reef building and deployment experience,
including 20,000 tons of repurposed concrete materials in the mid-Atlantic and the
deployment of dozens of vessels. The company is currently the Artificial Reef Contractor for
the State of Delaware Division of Fish and Wildlife and have completed two repurposed
concrete reef deployments totaling 5,145 tons in the past year. Similarly, Coleen has
completed two deployments for Virginia Marine Resources in the past 6 months totaling
approximately 3,850 tons of repurposed concrete (e.g., concrete pipe, culverts, and junction
boxes). Coleen also completed the sinking of the Shirley Brown for Alabama Gulf Coast Reef
and Restoration Foundation on June 2, 2015 off Orange Beach, Alabama. Most recently,
Taylor County, FL has awarded a contract to deploy 224 reef cubes in the Gulf of Mexico –
also a Florida Fish and Wildlife Conservation Commission (FWC) sponsored project.
1221 AIRPORT ROAD, SUITE 210 DESTIN, FL 32541 TEL 850.460.7040 WWW.TAYLORENGINEERING.COM
WWW.TAYLORENGINEERING.COM
Jim Trifilio
July 8, 2015
Page 2 of 3
2. Project work plan and schedule.
Taylor Engineering Review: The work plan provided by Coleen details numerous, large deck
barges (140 – 260 ft in length), loaders, cranes, excavators, and hauling equipment. Coleen
has indicated their understanding and approach to the project from their attendance at the
pre-bid meeting and site visits, as well as through the submitted deployment plan. Taylor
Engineering contacted Mr. Tim Mullane, Coleen’s Vice President of Operations, on June 22
and 23, 2015 to verify the proposed equipment resources discuss details of the deployment
plan.
Coleen anticipates commencing the required coordination and submittal preparation
immediately following authorization and anticipates to commence material hauling and
deployment within 30 days of contract authorization (August 2015). From the anticipated
schedule of 6 – 9 weeks in the deployment plan, the project may extend beyond Okaloosa
County’s anticipated completion date of October 1, 2015; however, the project schedule
indicates construction completion well before December 31, 2015 as required by the FWC
grant. The deployment plan and schedule were verified by Mr. Tim Mullane on June 22 and
23, 2015. Mr. Mullane indicated Coleen expects to complete the actual deployment within
30 days and Coleen provided the additional time to account for the required coordination
with Eglin Air Force Base.
3. Past project performance for artificial reef construction projects.
Taylor Engineering Review: Coleen has completed numerous artificial reef construction and
deployment projects for private groups such as the Alabama Gulf Coast Reef and
Restoration Foundation, Inc., State agencies within Florida, Alabama, North Carolina, New
Jersey, and Delaware, and local-government agencies such as Taylor County, Florida. As
previously mentioned, the Taylor County project (similar to the current Okaloosa project) is
grant funded through FWC.
We contacted FWC’s Artificial Reef Program Environmental Administrator (Mr. Jon Dodrill)
and asked him to comment on the overall quality of work, scheduling, conflicts/problem
resolution, and potential for future work. While Taylor County selected Coleen to perform
the FWC-funded project, Mr. Dodrill’s work experience with Coleen is quite limited, as work
had not yet commenced. However, Mr. Dodrill did indicate he has worked with Coleen’s
Vice President of Operations (Tim Mullane) since 2002 and gave overall positive comments
on his previous experiences. We also contacted Jeff Tinsman (Delaware’s Department of
Fish and Wildlife Artificial Reef Coordinator) and Joe Grist (Virginia’s Marine Resources and
Fisheries Management Deputy Chief). We asked the project managers to comment on the
overall quality of the work, scheduling, conflicts/problem resolution, and potential for
future work. Both individuals provided very positive comments and gave high
recommendations for utilizing Coleen’s services for future artificial reef work.
Jim Trifilio
July 8, 2015
Page 3 of 3
Based on the information submitted within their RFB response package and the information
above, we recommend Okaloosa County enter into a contract agreement with Coleen Marine, Inc. for
construction of the Okaloosa County Artificial Reef Project. If you have any questions or comments,
please contact me at (850) 460-7040 or mtrammell@taylorengineering.com.
Sincerely,
Matthew A. Trammell, P.E.
Senior Engineer, Coastal