Okaloosa County Jail Master Plan
EXHIBIT B - FEE CALCULATION - TIME AND COST MATRIX
DLR Group Pulitzer/ Choctaw WCCI Totals
Bogard Engineering
Staff
Position
Billable Rate Total Total Total Total Total Total Total Total Total Total
Task Description Hrs. $ Hrs. $ Hrs. $ Hrs. $ Hrs. $
1 Develop Profiles of the Detention Population 72 $14,760 137 $22,570 8 $1,400 0 $0 217 $38,730
1.1 County Workshop Session #1 32 $7,520 21 $3,810 8 $1,400 0 $0 61 $12,730
1.2 Formulate Data Request 12 $2,100 16 $2,760 0 $0 0 $0 28 $4,860
1.3 Compile and Review Relevant Data 12 $2,100 40 $6,400 0 $0 0 $0 52 $8,500
1.4 Analyze Data, Prepare Graphic Charts 12 $2,100 40 $6,400 0 $0 0 $0 52 $8,500
1.5 Onsite Visit to Review Analysis Assumptions 4 $940 20 $3,200 0 $0 0 $0 24 $4,140
2 Prepare Inmate Population Forecasts 12 $2,340 188 $31,380 0 $0 0 $0 200 $33,720
2.1 Compile County Demographics 0 $0 24 $4,040 0 $0 0 $0 24 $4,040
2.2 Develop Base Projection by Classification Segment 0 $0 34 $5,640 0 $0 0 $0 34 $5,640
Develop Alternative Projections Based on Possible System
2.3 0 $0 34 $5,640 0 $0 0 $0 34 $5,640
Changes
2.4 Develop Profiles of Detention Population 4 $940 16 $2,760 0 $0 0 $0 20 $3,700
2.5 Produce Projected Needs Report 4 $940 68 $11,280 0 $0 0 $0 72 $12,220
2.6 Revise Report to Incorporate Comments 4 $460 12 $2,020 0 $0 0 $0 16 $2,480
3 Evaluation of Existing Operating Practices 40 $8,920 12 $1,920 0 $0 0 $0 52 $10,840
3.1 Document Current Operational Practices/ Issues 12 $2,820 0 $0 0 $0 0 $0 12 $2,820
3.2 Document Existing Staff and Operating Costs 12 $2,820 12 $1,920 0 $0 0 $0 24 $4,740
3.3 Compile Operational Deficiencies. 16 $3,280 0 $0 0 $0 0 $0 16 $3,280
4 Assessment of Existing Facility Physical Conditions 212 $38,060 2 $420 0 $0 0 $0 214 $38,480
4.1 Inventory Existing Physical Conditions 70 $11,830 0 $0 0 $0 0 $0 70 $11,830
4.2 Document Current Utilization by Component 62 $10,910 0 $0 0 $0 0 $0 62 $10,910
4.3 Evaluate Facility for Reuse/Adaptation Potential 24 $5,160 0 $0 0 $0 0 $0 24 $5,160
4.4 Develop Existing Conditions Report 56 $10,160 2 $420 0 $0 0 $0 58 $10,580
5 Preliminary Report 144 $32,400 21 $3,810 80 $8,680 0 $0 245 $44,890
5.1 Define Projected Needs 28 $6,100 0 $0 18 $1,820 0 $0 46 $7,920
5.2 Review Available Resources 28 $6,340 0 $0 18 $1,820 0 $0 46 $8,160
5.3 Perform Shortfall Analysis 28 $6,340 0 $0 18 $1,820 0 $0 46 $8,160
5.4 Outline Strategies for a Solution 28 $6,100 0 $0 18 $1,820 0 $0 46 $7,920
5.5 County Workshop Session #2 32 $7,520 21 $3,810 8 $1,400 0 $0 61 $12,730
6 Identify Future Facility Solutions 236 $39,500 97 $17,370 186 $17,545 0 $0 519 $74,415
6.1 Develop Operational and Architectural Program 24 $5,640 84 $14,640 0 $0 0 $0 108 $20,280
6.2 Evaluate New Site Prototype 52 $8,540 0 $0 87 $8,120 0 $0 139 $16,660
6.3 Evaluate Existing Site Expansion Options 52 $8,540 0 $0 40 $3,800 0 $0 92 $12,340
6.4 Recommendations for Reuse/Adaptation of Facilities 24 $5,160 9 $1,890 25 $2,400 0 $0 58 $9,450
6.5 Develop Options for Consideration 84 $11,620 4 $840 34 $3,225 0 $0 122 $15,685
7 Budget Projections 64 $13,600 68 $11,280 25 $2,540 130 $16,000 287 $43,420
7.1 Develop Staffing Plan and Operating Costs 32 $7,040 68 $11,280 0 $0 0 $0 100 $18,320
Develop Capital and Operating Budgets for Phased
7.2 16 $3,280 0 $0 17 $1,650 130 $16,000 163 $20,930
Approach
7.3 Develop Schedule based upon Phased Approach 16 $3,280 0 $0 8 $890 0 $0 24 $4,170
8 Final Report 104 $19,800 33 $6,230 52 $5,210 0 $0 189 $31,240
8.1 Prepare Draft report 32 $7,040 16 $2,860 27 $2,280 0 $0 75 $12,180
8.2 County Workshop Session #3 16 $3,760 9 $1,890 8 $1,400 0 $0 33 $7,050
8.3 Finalize report with comments from County staff 40 $6,720 8 $1,480 17 $1,530 0 $0 65 $9,730
8.4 Issue Final Report 16 $2,280 0 $0 0 $0 0 $0 16 $2,280
TOTAL 884 $ 169,380 558 $ 94,980 351 $ 35,375 130 $ 16,000 1923 $ 315,735
Estimated Expenses $8,550 $9,800 0 0 $18,350
TOTAL FEE including estimated expenses $334,085
DLR Group 8/24/2016