Okaloosa County BOCC — March 17, 2015 — CH2M HILL Task Order 3 — agenda request
CH2M HILL Task Order 3 — agenda request in the March 17, 2015 Okaloosa County BOCC meeting materials. Preserved county-portal original with machine-extracted reading text.
Preserved among the March 17, 2015 Okaloosa County Board of County Commissioners meeting materials (IQM2 meeting 1251). The date shown is the verified meeting context, not an independently established creation date for every attachment. The download catalog used Feb 18, 2014; the meeting date was corrected using the agenda/minutes heading and matching source filename.
Original publication
Action Item Printout
Date
March 17, 2015
Publisher
Okaloosa County Board of County Commissioners
Where to find it
2
Reference collection
Okaloosa County Board of County Commissioners (IQM2 public portal)
Source date and document identity checked for this intake. Machine text has not received independent human proofreading.
HOW FAR THIS HAS BEEN CHECKED
File / copy authenticity
Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
Transcription / extraction
Each reading-text file shows its recorded review status below.
CH2M HILL Task Order 3 — agenda request — extracted reading text
Machine extraction of the preserved PDF embedded text using pdftotext -layout. Form-feed page boundaries retained; no words rewritten. Not independently human proofread; consult the original for layout and uncertain characters.
Compare reading text with the preserved source. Line breaks and spacing are retained; long lines wrap to fit the screen. A file's role does not establish that its text has been checked.
CH2M HILL Task Order 3 — agenda request — extracted reading text
Machine-extracted OCR text · Review label: Known limitations
BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: March 17, 2015
TO: Honorable Chairman and Members of the Board
FROM: Jeff Littrell
SUBJECT: CH2M HILL Task Order 3
DEPARTMENT: Water and Sewer
BCC DISTRICT: All
STATEMENT OF ISSUE: Okaloosa County Water & Sewer (OCWS) staff requests BCC
approval for CH2M HILL Task Order 3 per the terms of Contract #C13-2069-WS for a total not
to exceed cost of $82,500. Task Order 3, for a Water Supply Alternatives Analysis, is attached
for your review.
BACKGROUND: OCWS and the U.S. Army Corps of Engineers (USACE) have a long
standing partnership related to future water supply. Three Planning Assistance to States (PAS)
phases have been completed, all in support of planning efforts for the future water supply
program. The three completed phases discussed in the attached BCC agenda request from
12/16/2014 are generally described as follows: 1) site selection of water treatment plant, 2)
water treatability and pilot testing, and 3) system modeling for hydraulics and water quality. All
phases are a 50/50 cost share between USACE and OCWS.
On 12/16/2014, the BCC approved the PAS Phase IV Agreement (attached). The scope of work
proposed for Phase IV (attached in agreement) includes a detailed alternative analysis of the
various sites previously proposed for the future water supply offline reservoir and documents the
process required to obtain a USACE Section 404 Permit necessary to construct the future offline
reservoir. The amount for this grant is a total of $165,000 to again be shared 50/50 between
USACE ($82,500) and OCWS ($82,500). The funding is broken down into tasks in Table 1,
shown on p. 12 of 13 in the attached agreement. As shared in the previous agenda request, staff
recommends to move forward with Okaloosa County's in-kind portion of the cost-share by
executing a task order with CH2M HILL. Therefore, for your consideration and approval is a
task order with CH2M HILL not-to-exceed $82,500.
Staff has been in a holding pattern since 12/16/2014 waiting for USACE to execute the PAS
Phase IV Agreement, and then to secure funding. As you can see from the attached
documentation, USACE has now secured $82,500 to fully fund their portion.
OPTIONS: Approve or deny.
RECOMMENDATIONS: OCWS staff recommends BCC approval to authorize the Chairman
to execute Task Order 3 with CH2M HILL Engineers, Inc. for a not-to-exceed amount of
$82,500.00.
RECOMMENDED BY:
APPROVED BY:
John Hofstad, County Administrator
Okaloosa County Board of County Commissioners. “Okaloosa County BOCC — March 17, 2015 — CH2M HILL Task Order 3 — agenda request.” March 17, 2015. Action Item Printout. Crypt of Echoes evidence ID LED-2026-c4293e65263147e99a555a6043ce005b. http://127.0.0.1:58097/evidence/LED-2026-c4293e65263147e99a555a6043ce005b. Accessed [date].
Catalogue citation: Okaloosa County Board of County Commissioners, CH2M HILL Task Order 3 — agenda request, meeting materials for March 17, 2015. https://okaloosacountyfl.iqm2.com/Citizens/FileOpen.aspx?Type=30&ID=13115&MeetingID=1251
Preserved county public-record source. Third-party attachments may retain their original rights.