Okaloosa County BOCC — April 15, 2014 — NOTICE OF PUBLIC HEARING - East County Force Main and Repump Station — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 117-NOTICE OF PUBLIC HEARING - East County Force Main and Repump Station.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
NOTICE OF PUBLIC HEARING
NOTICE IS HEREBY GIVEN that the Board of County
Commissioners of Okaloosa County, Florida, on May 20, 2014 at 9:00 A.M., or
soon thereafter, at the County Commissioners meeting room, Water & Sewer
Annex, 1804 Lewis Turner Blvd., 3rd Floor, Ft. Walton Beach, Florida will hold a
hearing to discuss the County’s proposal to construct the East County Force Main
and Repump Station Project using Okaloosa County Water and Sewer Department
(OCWS) staff and equipment. The public hearing shall constitute the public
meeting as required by section 225.20, Fla. Stat. The purpose of the public meeting
is to consider whether it is in the public’s best interest to perform the project using
the local government’s own services, employees, and equipment. The scope of
work generally consists of the construction of a new 20 inch diameter sewer force
main (totaling approximately 6.7 miles in length) and a new 4.2 million gallon per
day sewer repump station. The estimated cost of the design-build project using
OCWS staff is $4,169,312.14.
ALL INTERESTED PERSONS ARE INVITED TO ATTEND AND BE HEARD
REGARDING THE PUBLIC HEARING.
The proposal and cost estimate breakdown may be inspected by the public at
Okaloosa County Water & Sewer, 1804 Lewis Turner Blvd., 3rd floor, Engineering Office,
850-651-7504.
If any person decides to appeal any decision made with respect to any matter
considered at these hearings, such person will need a record of the proceeding and may
need to ensure that a verbatim record of the proceeding is made which record includes
the testimony and evidence upon which the appeal is to be based.
Okaloosa County adheres to the American Disabilities Act and will make
reasonable modifications for access to these hearings upon request. Requests may be
made to the Water & Sewer offices described above and must be made at least 48
hours in advance of the hearings in order to provide the requested service.
Board of County Commissioners
Okaloosa County, Florida
By: Don. W. Howard
Clerk of Circuit Court
4/9/2014
Preliminary Cost Estimate
OCWS East County Force Main (From College Blvd./SR-85 to Eglin Repump Station
Line No. Line Item Quantity Unit Unit Price Total
1 20" PVC C-905 DR18 28,805 LF $ 30.00 $ 864,150.00
2 24" HDPE DR-11 Directional Bores (Gator Boring) 6,474 LF $ 201.60 $ 1,305,158.40
3 24"/20" bore transition fittings (Gator Boring) 9 pair $ 3,600.00 $ 32,400.00
4 36" Jack and Bore with Carrier Pipe (Gator Boring) 140 LF $ 350.00 $ 49,000.00
5 20" plug valves w/ box & megalug kit 16 EA $ 8,000.00 $ 128,000.00
6 air release/vacuum valve w/ MH, GV, valve box 23 EA $ 4,500.00 $ 103,500.00
7 20" Megalug Kits 116 EA $ 200.00 $ 23,200.00
8 Tapping saddle and appurtenances for testing/filling 30 EA $ 300.00 $ 9,000.00
9 DI Fittings 1 LS $ 20,000.00 $ 20,000.00
10 14" Line Stops (EA Tapping Services) 2 EA $ 6,000.00 $ 12,000.00
11 Seeding & Mulching 20 AC $ 200.00 $ 4,000.00
12 Erosion Control: Silt Fence 3,000 LF $ 0.19 $ 570.00
13 Concrete Flume/Sidewalk Replacement 1,100 SF $ 3.00 $ 3,300.00
14 Marker Posts 40 EA $ 14.87 $ 594.80
15 OCWS in-house labor (500 LF/day) 58 days $ 3,000.00 $ 174,000.00
16 OCWS in-house equipment (500 LF/day) 58 days $ 1,000.00 $ 58,000.00
TOTAL GATOR BORING (Contract C14-2094-WS) $ 1,386,558.40
TOTAL EA TAPPING SERVICES (Contract C14-2128-WS) $ 12,000.00
TOTAL OCWS MATERIALS $ 1,156,314.80
TOTAL OCWS LABOR + EQUIP $ 232,000.00
SUBTOTAL CONSTRUCTION (Includes Contracted Services) $ 2,786,873.20
18 15% contingency on materials $ 173,447.22
19 15% admin/overhead fee on labor/mat'l (not equip or contracted) $ 199,547.22
TOTAL CONSTRUCTION $ 3,159,867.64
Okaloosa County Water & Sewer
East County RePump Project- Contract Estimates
Contract 1 Contract 2 Contract 3 Contract 4 Contract 5
Pre-
Engineered
Building Pumps Generator MCC/Controls Site Work Piping OCWS
Material $
Cost $ 96,000.00 130,000.00 $328,000.00 $13,797.44 $196,680.00
Labor Cost $ 87,400.00
Contract
Cost $ 157,567.06
CONTRACT 1 COST (Pre-Engineered
Building) $157,567.06
CONTRACT 2 COST (3- 100hp Centrifugal Pumps) $ 96,000.00
CONTRACT 3 COST (550 kW Generator) $130,000.00
CONTRACT 4 COST (Motor Control & Control Panel) $328,000.00
CONTRACT 5 COST (OCWS Labor, Site Work & Mech
Piping) $297,877.44
TOTAL COMBINED CONTRACTS COST $ 1,009,444.50