READ ALONGSIDE THE SOURCE
Fort Walton Beach Resolution — 2010-21 - Wright Parkway Sidewalk, LAP — reading text
Part 7 of 7. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — fwb-23676-original.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
PROJECT DESCRIPTION
Name: Wriqht Parkway sidewalks Length: n/ a
Termini: From S. R. 30 ( U. S. 98) to S. R. 393 ( Mary Esther Blvd).
FUNDING
1)( 2) ( 3)
TOTAL AGENCY STATE &
TYPE OF WORK By Fiscal Year PROJECT FUNDS FUNDS FEDERAL FUNDS
Planning 2006- 2007
2007 -2008
2008- 2009
Total Planning Cost
Project Development & Environment ( PD& E)
2006- 2007
2007- 2008
2008- 2009
Total PD& E Cost
Design 2010- 2011 $ 16369
Total Design Cost $ 16, 369
Right- of-Way 2006- 2007
2007 -2008
2008- 2009
Total RiQht- of-Way Cost
Construction and Construction Engineering and Inspection( CEI)
2012- 2013 $ 163691
Total Construction and CEI Costs $ 163, 691
TOTAL COST OF THE PROJECT $ 180, 060
The Department's fiscal year begins on July 1. For this project, funds are not projected to be available until after the 1 st of July of
each fiscal year. The Department will notify the Agency, in writing, when funds are available.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525- 010- 40
PROJECT MANAGEMENT OFFICE
LOCAL AGENCY PROGRAM AGREEMENT 07/ 09
Page16
EXHIBIT " C"
RESTRICTION ON CONSULTANT'S ELIGIBILITY TO COMPETE FOR
DEPARTMENT ASSISTED CONTRACTS
FPN: 428097- 1- 38- 01 & 428097- 1- 58- 01
This exhibit forms an integral part of the Agreement between the State of Florida, Department of Transportation and the
City of Fort Walton Beach.
EXISTING CONSULTANT CONTRACTS:
Existing consultant or professional services contracts shall not be used in the development and delivery of this project,
doing sow ill federalize t he ex isting contract. A II consultant an d pr ofessional services contracts as sociated with this
project s hall be ad vertised and s elected in a ccordance with the Consultants Competitive Negotiations A ct ( CCNA).
Consult the District LAP Administrator for the appropriate federal language that must appear in each consultant contract.
CONSULTANT CEI CONTRACTS:
A consultant firm or its affiliate that was the engineer of record ( EOR) on a project shall not be considered for construction
engineering and inspection ( CEI) services, as a prime, on the same project.
A consultant firm or its af filiate w howas the E OR on a pr oject m ay on Iy be considered for C EI services as as ub
consultant to the prime CEI firm with the approval of the Department prior to submittal of letters of response.
A consultant firmor its affiliate who was the sub to the EOR on a project may only be considered for CEI services, as
prime, on the same project, with the approval of the Department prior to submittal of letters of response.
The Department's approval shall be bas ed 0 n t he ex tent of the firm' s involvement in t he des ign of the pr oject or C EI
services, as the case may be, and the potential of hindrance I of any objective decision making.
A consultant or its affiliate who performed geotechnical services for the EOR shall not be considered as a sub to the firm
providing CEI services on the same project, in any capacity.
DESIGN- BUILD CONTRACTS:
The contractor or design professional cannot team, as a prime, with other firms to submit more than one bid per project.
The secondary member ( i.e., designer or contractor) of the design- build team cannot change, after a ward, without the
written approval of the Department.
A professional firm shall not be considered for CEI services, either as a prime or a sub, for a Design- Build contract for
which the same firm or its affiliate is the EOR or is sub to the EOR.
A consultant firm, its affiliate, or sub consultant that is under contract with t he Local A gency to de velop the R FP f or a
Design- Build contract cannot be part of a Design- Build Team proposing on that contract as a prime or a sub consultant. A
consultant firm, its affiliate, or sub consultant that is under contract with the Local Agency to provide CEI services on the
Design- Build contract cannot be part of a Design- Build Team proposing on that contract as a prime or sub consultant.
A consultant or its affiliate, whowas t he prime E OR on a D esign- Bid- Build pr oject, where the pr oject is switched to
Design- Build, may participate on a Design- Build contract with t he approval of the Department. T he Department shall
consider level of design (% completed) by the EOR, the number of component design plans by different EOR' s, etc.
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION 525- 010- 40
PROJECT MANAGEMENT OFFICE
LOCAL AGENCY PROGRAM AGREEMENT 08/ 06
Page 17
EXHIBIT " 1"
SINGLE AUDIT ACT
Federal Resources Awarded to the Recipient Pursuant to This Agreement Consist of the Following:
Federal Agency: Federal Highway Administration
CFDA #: 20. 205 Highway Planning and Construction
Amount: FPID 428097- 1- 38- 01 & 428097- 1- 58- 01................. ............................................. ............ .$ 180, 060
Compliance Requirement:
Allowable Activities: To be eligible, most projects must be located on public roads that are not functionally classified as
local. The major exceptions are the Highway Bridge Replacement and Rehabilitation Program, which provides assistance
for bridges on and off the federal- aid highways, highway safety activities, bicycle and pedestrian projects, transportation
enhancement ac tivities, t he recreational t rails program, and pi anning, research, development, and technology transfer.
Proposed projects meeting these and other planning, design, environmental, safety, etc., requirements can be approved
on the basis of state and local priorities within the limit of the funds apportioned or allocated to each state.
Allowable Costs: Eligible ac tivities a nd allowable costs will be determined in ac cordance with Title 23 an d Title 49
C. F. R. and the OMB cost principles applicable to the recipient/sub- recipient.
Eligibility: By law, the federal- aid highway program is a federally assisted state program that requires each state to have
a suitably e quipped an d organized transportation de partment. Therefore, most projects are ad ministered by or through
State Departments of Transportation ( State DOTs). Projects to be funded under the federal- aid highway program ar e
generally s elected by state DOTs or Metropolitan Planning 0 rganizations ( MPOs), in cooperation with ap propriate local
officials, as specified in 23 U . S. C. and implementing regulations. Territorial hi ghway pr ojects ar e funded in the same
manner as other federal- aid highway projects, with the territorial transportation agency functioning in a manner similar to a
state DOT. Most Florida Land Highway Program ( FLHP) projects are administered by the Federal Highway Administration
FHWA) Office of Federal La nds Highway a nd its Divisions or by the various Florida Lan d Man agement Agencies
FLMAs). Under the FLHP, projects in the Indian Reservation Road ( IRR) Program are selected by Tribal Governments
and are approved by the Bureau of I ndian Affairs ( BIA) and the FHWA. Due to recent legislation, Tribal Governments
meeting certain requirements may now administer various IRR projects on behalf of the BIA and FHWA. The Fish and
Wildlife Service ( FWS) an d the National Park Service ( NPS) select projects in the Refuge Road an d P ark Roads and
Parkways Programs, respectively. For the Forest Highway Program, the Forest Service, the States and the FHWA jointly
select projects.
Compliance Requirements Applicable to the Federal Resources Awarded Pursuant to This Agreement Are As
Follows: The recipient of Local Agency Program ( LAP) funding must comply with the statutory requirements in Sections
112. 061, 215.422, 339. 12, and 339. 135, Florida Statutes, and Title 23 and Title 49, C. F. R.