READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — December 18, 2012 — Request for Bids — reading text
Part 8 of 154. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 101-Request for Bids.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Sea Oats Planting Unit 145,744 $ $
11 Panic Grass Planting Unit 18,780 $ $
12 Diversity Species Planting Unit 23,278 $ $
Total Cost Bid Items 7-12 $
Total Cost Bid Items 7-12 (Written)
BID SCHEDULE
Bid Alternative 3 – Okaloosa Island Option 1 (2” containers)
Bid Item Description Units Quantity Unit Cost Bid Item Cost
13 Sand Fence Linear Feet 10,230 $ $
14 Post & Rope Linear Feet 3,587 $ $
15 Signage Sign & Post 248 $ $
16 Sea Oats Planting Unit 490,548 $ $
17 Panic Grass Planting Unit 63,519 $ $
18 Diversity Species Planting Unit 81,123 $ $
Total Cost Bid Items 13-18 $
Total Cost Bid Items 13-18 (Written)
BID SCHEDULE
Bid Alternative 4 – Okaloosa Island Option 2 (4” containers)
Bid Item Description Units Quantity Unit Cost Bid Item Cost
19 Sand Fence Linear Feet 10,230 $ $
20 Post & Rope Linear Feet 3,587 $ $
21 Signage Sign & Post 248 $ $
22 Sea Oats Planting Unit 218,021 $ $
23 Panic Grass Planting Unit 28,231 $ $
24 Diversity Species Planting Unit 36,055 $ $
Total Cost Bid Items 19-24 $
Total Cost Bid Items 19-24 (Written)
Bidder shall sign below that they have read and understood all addenda, if any, related to this project.
Failure to acknowledge any addendum issued shall disqualify the Bidder.
Addendum # : Date of Receipt:
Last Revised – 01/09/2013 Page 38
Addendum # : Date of Receipt:
Addendum # : Date of Receipt:
Notice to All Bidders:
1. The Owner reserves the right to waive any informality in any bid, to reject any and all
bids, and to delete any part of any of the above items.
2. Bid prices for the various work items are intended to establish a total price for completing
the project in its entirety. The contractor shall include in the Bid, any item for which a
separate pay item has not been established in the Bid Schedule (under any related pay
item), to reflect the total price for completing the project in its entirety.
3. Quantities shown are estimated. Actual quantities may vary. The Owner reserves the
right to adjust the final Contract Price by the actual quantities installed (+ or -) and it shall
be the successful bidder’s responsibility to provide accurate documentation of the
actual quantities installed.
PART III Certifications:
In accordance with your request for Bids, instructions and specifications, attached hereto, and
subject to all conditions thereof, I (we), the undersigned, hereby propose and agree if this Bid is
accepted, to contract with Okaloosa County, Florida to construct any items or furnish any
service requested herein and deliver same without additional cost to Okaloosa County at the
specified location for the quotations listed above.
The undersigned further declares that he/she has carefully examined the specifications
referenced on this Bid Form and is thoroughly familiar with them and their provision(s). The
undersigned further declares that no other person than the Bidder herein named has any
interest in this Bid or in the contract to be executed, and that it is made without any connection
with any other person(s) making Bid for the same articles, and it is in all respects fair and without
collusion and fraud.
SIGNATURE & CERTIFICATION:
Name & Title of Authorized Representative:
(Print or Type)
Signature:
Date of Bid:
Note: See RFB Section III, Bid Requirements, and attach all required information to Bid form.
Okaloosa County reserves the right to reject any and all bids or portions thereof, to waive minor
defects in the process and to accept the Bid or any combination of Bid items or take any other
actions deemed by Okaloosa County to be in the County’s best interest. Okaloosa County also
reserves the right to assign additional work to the successful Bidder based upon their Bid
proposal or negotiation as may be necessary to meet grant funding or completion
requirements.
Last Revised – 01/09/2013 Page 39
ATTACHMENT “A”
WESTERN DESTIN DUNE VEGETATION PROJECT
CONSTRUCTION DRAWINGS, SPECIFICATIONS, and
REGULATORY AUTHORIZATIONS
TECHNICAL SPECIFICATIONS FOR THE
WESTERN DESTIN DUNE VEGETATION PROJECT
PART 1 – GENERAL
1.1 SUMMARY
A. These specifications include requirements for the furnishing of labor,
materials, equipment and performing all operations in connection with
dune vegetation, sand fencing, signage, and post and rope installation as
indicated on the Construction Drawings (Drawings) and specified herein.
1.2 DEFINITIONS
A. Nomenclature: The scientific and common names of plants herein
specified conform to the approved names given in Hortus Third (1976) by
Liberty Hyde Bailey Hortorium.
B. Planting Unit: For the purpose of this project, the term “planting unit” refers
to vegetative material of any individual, viable, nursery-grown plant
installed within a single hole created on the beach or dune system.
Planting unit species and size vary in accordance with these
Specifications & Contract Documents.
C. Engineer: - The Owner’s representative responsible for construction
observations.
1.3 SUBMITTALS – The following shall be submitted for Owner & Engineer approval:
A. Work Plan: As part of the bid package, the contractor shall submit to the
engineer a detailed work plan for the dune vegetation, sand fence,
signage, and post and rope installation. The plan shall include the
construction schedule (including plant propagation through installation.),
propagation method, types of hydrating gel and fertilizer to be used
(including the required manufacturers information), proposed materials,
staging areas and access requirements, work force & equipment, and the
qualifications of supervisor(s). The contractor shall provide with the work
plan documentation as to the source of the planting units to be installed,
including collection permits and any other required permits or
documentation.
B. Watering Plan: As part of the bid package, the contractor shall furnish to
the Engineer a plan for watering the plants and an itemized list of
equipment that will be used during watering operations. The watering
Last Revised – 01/09/2013 Page 40
plan shall detail the proposed number of irrigation events, irrigation
methodology, equipment, water source, labor, required time,
notifications, and the physical condition(s) of the planting units that signal
the need for maintenance irrigation. The plan shall also include details
regarding the hydrating gel requirements and any additional soil
amendments (fertilizer) that may be included during the irrigation.
C. Certificates of Compliance: Before delivery of planting materials, the
contractor shall submit to the Engineer certificates of compliance and/or
documentation certifying that the planting materials meet all of the
requirements (plant source, plant size, plant age, plant grade, etc.) for this
specification.
D. Notice of Commencement: The contractor shall notify the Engineer at
least 3 days before initiating the work, including mobilization, staging,
and/or field work.
E. Notice for Inspection: The contractor shall notify the Engineer at least 10
days before the scheduled 180-day inspection that the vegetation is
ready for inspection. The contractor shall meet and accompany the
Engineer onsite during the inspection.
F. Soil Amendments: The contractor shall submit the required
manufacturer’s information certifying that soil amendments meet the
specifications.
PART 2 – EXECUTION
2.1 GENERAL
A. Schedule – The contractor shall complete all construction activity (plant,
sand fence, signage, and post and rope installation) and remove all
equipment from the beach and work areas prior to marine turtle nesting
season (May 1 – October 31). The contractor shall not commence work
until receiving a written Notice to Proceed from the Owner or Engineer.
Work is permitted seven (7) days a week during daylight hours only (sunrise
to 1 hour after sunset).
B. NOTIFICATION – The contractor shall notify the Engineer at least 3 days
prior to project mobilization, commencement of installation, project
completion, inspections, and demobilization. The contractor shall notify
the Engineer at least 10 days before the scheduled 180-day vegetation
inspection. The contractor shall notify the Engineer at least 48 hours prior
to the suspension of work. The contractor shall notify the Engineer
immediately for any work stoppages resulting from environmental impacts
(turtle nest impacts, fuel spills, etc.), permit violations, property owner
disputes, safety violations, etc.
C. WORK – The contractor shall install the dune vegetation, sand