bridge would serve
as backup). This project is partially funded by a state appropriation administered by a FDEP Grant
Agreement.
Diversion of East County wastewater from the Niceville-Valparaiso Regional Sewer Board (NVRSB) Plant
to the Arbennie Pritchett Water Reclamation Facility (APWRF) (construction) – construct a new force main
to divert OCWS sewer flow from NVRSB to the Arbennie Pritchett WRF. This will consolidate flows and
reduce overall wastewater treatment cost for the flows from our East County service area.
Garniers Area Sanitary Sewer Rehab (construction) – install cured-in-place liners on vitrified clay sewer
mains and brick manholes to reduce the inflow and infiltration, which is currently inundating the collection
system. This project is partially funded by a state appropriation administered by a FDEP Grant Agreement.
GIS/Mapping – database to be improved and upgraded, by merging multiple datasets. Additional
subsurface utility engineering to be completed as needed to accomplish the merger.
Hwy 90 West Water Main Replacement (design & construction) – install a water transmission main to
replace the aging pipeline that is regularly failing.
Lake Pippin Area Sewer (design) – install public sewer to approximately 125 lots adjacent to
Choctawhatchee Bay and Lake Pippin. This project is funded by a state appropriation administered by a
FDEP Grant Agreement.
Marlowe Area Water System Improvements (construction) – provide new, larger water mains to the area
and fire hydrants to provide increased fire protection and ensure the reliability of the system.
Meigs-Seminole Lift Station & Associated Force Mains (construction) – replace the aging and undersized
Meigs-Seminole Lift Station, which currently pumps all the wastewater from Bluewater Bay to the NVRSB
facility.
Mid County Tank #4 & Connecting Water Main (construction) – a second elevated water tank near the Bob
Sikes Industrial Park would provide for increased storage, reliability, and redundancy for the potable water
and fire suppression systems. This project is partially funded by a Northwest Florida Water Management
District grant.
Newport/Essex Area Water System Improvements (design & construction) – provide new, larger water
mains to the area and fire hydrants to provide increased fire protection and ensure the reliability of the
system.
PJ Adams Pkwy Water Main Relocation (construction) – install a water transmission main to replace the
existing main that is in conflict with the roadway 4-laning project. Project to occur in four phases from
Hwy 85 to Interstate 10.
Packet Pg. 107
Reclaimed Water to City of Niceville and Eglin AFB (design & construction) – provide for facility upgrades
at the APWRF to provide up to 4 MGD of reclaimed water capability and install approximately 11 miles of
reclaimed water transmission mains to the City and Eglin AFB. This project has a rough-order-of-
magnitude cost of $8M, and is currently funded at $3M, via a state appropriation administered by a FDEP
Grant Agreement. This grant will fund the entire design and environmental work, the construction of the
APWRF upgrades, and a portion of the pipeline.
Taxiway H Water Main Extension (construction) – in partnership with County Airports and Eglin AFB,
install a water main that will support the Aircraft Rescue & Fire Fighting Station and Eglin AFB’s water
system. This project is funded by an FAA grant and payment in kind for the APWRF lease with Eglin AFB.
PERFORMANCE MEASURES:
Actual Approved Proposed
Performance Measures
FY14/15 FY15/16 FY16/17
Miles of Sewer main / Maintenance Personnel 552/7 534/7 540/7
Miles of Water main / Maintenance Personnel 774/10 746/10 750/10
Input
Number of new sewer taps 154 160 170
Number of new water taps 179 200 210
Output Efficiency
Dollar value - new sewer taps $489,135 $520,000 $600,000
Dollar value - new water taps $167,253 $190,000 $250,000
Feet/Miles of sewer lines cleaned 111,635/21.1 177,424/33.6 180,000/34.1
Number of main breaks repaired - Water 833 681 700
Effectiveness
Number of main breaks repaired - Sewer 363 338 360
Valves maintained 162 300 1,650
Number of work orders (excludes taps & projects) 3,520 3,577 3,600
Man hours per work order 3.89 7.5 6.5
Packet Pg. 108
BOARD OF COUNTY COMMISSIONERS
OKALOOSA COUNTY, FLORIDA
SERVICE AREA: PHYSICAL ENVIRONMENT
DEPARTMENT/PROGRAM: WATER & SEWER ENTERPRISE FUND/LABORATORY
PROGRAM DESCRIPTION: This program is responsible for testing various water and wastewater samples
to assure compliance with Federal and State regulatory requirements. These samples come from 3 wastewater
treatment facilities, 39 monitoring wells, and various points throughout the water distribution system.
MAJOR ACCOMPLISHMENTS LAST YEAR:
Performed a total of over 4,000 wastewater sample tests.
Tested in excess of 936 water samples from monitoring wells.
Completed in excess of 2,097 tests in both Bacteriology and Quality on County drinking water samples.
Provided all required reports to DEP, EPA, and NW Florida Water Management District.
Performed numerous testing on an as needed basis (outsourced, leachate, sand and grit).
PROGRAM GOAL: Through the timely testing and reporting of water quality, ensure the public has a safe
supply. Make certain that all treated wastewater meets all required standards prior to discharge from the plant.
Provide the public with an annual report on the quality of the drinking water and how samples are tested and
monitored.
KEY OBJECTIVES:
1. Ensure budgetary, personnel, customer service and purchasing functions comply with County policies and
procedures.
2. Maintain and extend the useful life and utility of County facilities.
3. Ensure the preservation and safe operation of all work related equipment.
4. Carry out required State and Federal laboratory testing to assure water and wastewater meet proper
standards.
5. Perform all tests required by law, regulation and design standards, or contract with a laboratory capable of
such tests at a cost efficient manner as needed.
The following projects are planned for FY2017:
Perform all mandated wastewater sample tests.
Test all required water samples from monitoring wells.
Complete both Bacteriology and Quality tests on County drinking water samples.
Provide all required reports to DEP, EPA, and NW Florida Water Management District.
Prepare and distribute annual Consumer Confidence Report (CCR; water quality analysis) to the public.
PERFORMANCE MEASURES:
Actual Approved Proposed
Performance Measures
FY14/15 FY15/16 FY16/17
Efficiency
Annual lab tests performed / Lab personnel 4,430/5 >4,000/5 >4,000/5
Annual lab tests performed / monitoring wells 726/34 456/39 456/39
Number of lab tests on drinking water 2,173 >2,000 >2,000
Packet Pg. 109
HISTORICAL STAFFING SUMMARY:
Category FY14 FY15 FY16 FY17
Full-time Administrative & Support 32 32 34 35
Full-time Management & Professional 15 15 15 15
Full Time Operations & Trades 75 75 77 79
Part Time 0 2 2 2
Total 122 124 128 131
EXPENDITURES:
Expenditures Budget
FY14 FY15 FY16 FY17 FY16/FY17 Increase/
Category Actual Actual Approved Proposed +/- Decrease
Personnel Services $5,863,852 $6,223,669 $7,627,261 $7,857,425 $230,164 3.0%
Operating Expenses $15,318,889 $16,643,661 $10,116,763 $10,724,306 $607,543 6.0%
Capital Outlay $4,601,298 $3,509,773 $21,568,500 $24,391,000 $2,822,500 13.1%
Debt Service $181,367 $3,226,317 $5,687,533 $6,606,525 $918,992 16.2%
Other Uses $0 $0 $20,277,145 $22,884,285 $2,607,140 12.9%
Total $25,965,405 $29,603,420 $65,277,202 $72,463,541 $7,186,339 11.0%
Packet Pg. 110
ACCOUNTS:
FY15 FY16 FY17 FY16/FY17 Increase/
Code Category Approved Approved Proposed +/- Decrease
10 Salaries & Wages 5,306,741 5,467,038 5,689,280 222,242 4.1%
Funds two additional operational staff and a Contracts and Lease Coordinator.
20 Benefits 1,960,415 2,160,223 2,168,145 7,922 0.4%
31 Professional Services 414,000 425,500 400,000 (25,500) -6.0%
Reduction in consulting expenses.
32 Accounting & Auditing $27,500 $27,500 $77,500 $50,000 181.8%
Includes $50,000 for Risk Assessment Audit.
34 Contract Services $3,325,867 $3,402,623 $3,428,494 $25,871 0.8%
40 Travel & Per Diem $7,200 $9,200 $9,200 $0 0.0%
41 Communications Services $70,000 $80,000 $110,000 $30,000 37.5%
Increase due to conversion from black box analog to cable modems (SCADA)
42 Freight & Postage $5,500 $5,500