About this source
Okaloosa Admin Building - GMP Proposal - 9-16-2014 from the Okaloosa County BOCC meeting of October 21, 2014 (IQM2 meeting #1236). Original portal label: Okaloosa Admin Building - GMP Proposal - 9-16-2014. Preserved as a historical public record; part of the meeting linked as a related source.
- Original publication
- Okaloosa Admin Building - GMP Proposal - 9-16-2014
- Date
- October 21, 2014
- Reference collection
- Okaloosa County Board of County Commissioners (IQM2 public portal)
HOW FAR THIS HAS BEEN CHECKED
- File / copy authenticity
- Preserved files carry a SHA-256 fingerprint fixed at ingest; whether those bytes match the original capture is not independently verified.
- Transcription / extraction
- Machine produced / unreviewed — machine-extracted, not yet human-corrected
- Claim corroboration
- Not independently verified
View reference catalogue / source ↗
Download this source
Machine-extracted text — 77-Okaloosa Admin Building - GMP Proposal - 9-16-2014.pdf
Text extracted on 2026-10-31 from 77-Okaloosa Admin Building - GMP Proposal - 9-16-2014.pdf using the PDF text layer (pdftotext). Not human-corrected; may contain recognition errors. Read alongside the source images.
Text · 33.2 KB
Download ↓Okaloosa Admin Building - GMP Proposal - 9-16-2014 (PDF)
Original PDF as published on the Okaloosa County IQM2 meeting portal.
PDF · 4.1 MB
Download ↓
Full text
Machine-extracted from the source by optical character recognition. Not yet human-corrected — it may contain recognition errors. Read it alongside the images above.
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
Okaloosa County
C Administration Building Preliminary Schedule 295 01-Aug-14 01-Oct-15 0
Milestone S
Schedule 427 01-Aug-14 01-Oct-15 0
M1000 Site Ready for Construction 0 01-Aug-14 47 Site Ready for Construction
M1010 Start Vertical Construction Building A 0 17-Oct-14 350 Start Vertical Construction Building A
M1100 Steel Erection 92 17-Oct-14 16-Jan-15 48 Erection 16-Jan-15
M1030 Start Roughin Building A 0 13-Dec-14 293 Start Roughin Building A
M1020 Start Vertical Construction Building B 0 25-Dec-14 281 Start Vertical Construction Building B
M1040 Start Roughin Building B 0 27-Jan-15 248 Start Roughin Building B
M1050 Dried In - Building A 0 07-Feb-15 237 Dried In - Building A
M1060 Dried In - Building B 0 25-Feb-15 219 Dried In - Building B
M1070 Moving Air - Building A/B 0 09-Jun-15 115 Moving Air - Bu
M1080 Substantial Complete - Building A - 1st & 2nd Floor 0 14-Aug-15* 0 Subst
M1110 Substantial Complete - Building A - 3rd Floor 0 01-Sep-15* 0 Sub
M1120 Substantial Complete - Building B 0 01-Oct-15* 0
Submittals/Procurement
Submittals/P 1 15-Oct-14 16-Oct-14 32 16-Oct-14, Submittals/Procurement
P1000 Deliver Steel 1 15-Oct-14 16-Oct-14 32ver Steel 16-Oct-14
Site Work 241 01-Aug-14 16-Jul-15 54 16-Jul-15,
Preparation 21 01-Aug-14 29-Aug-14 224 29-Aug-14, Preparation
S1000 Fill and Compact Site 6 01-Aug-14 08-Aug-14 57 08-Aug-14
S1020 Rough-in U/G Drainage 10 01-Aug-14 14-Aug-14 235 14-Aug-14
S1030 Run Firemain to Building 5 01-Aug-14 07-Aug-14 240 07-Aug-14
S1010 Place Building Pad 15 11-Aug-14 29-Aug-14 57 29-Aug-14
Finishing 53 30-Apr-15 16-Jul-15 54 16-Jul-15,
S2000 Rough Grade Settling Ponds 5 30-Apr-15 07-May-15 57 Rough Grade Settling Ponds 07-May-15
S2160 Install Ground Rods/Tie In to Building 5 30-Apr-15 07-May-15 97 stall Ground Rods/Tie In to Building 07-May-15
S2010 Build Shadow box Enclosure 5 05-May-15 12-May-15 54 Build Shadow box Enclosure 12-May-15
S2020 Build Storm Structures 10 07-May-15 21-May-15 57 Build Storm Structures 21-May-15
S2070 Rough-in Irrigation Sprinklers 5 07-May-15 14-May-15 62 Rough-in Irrigation Sprinklers 14-May-15
S2030 Grade/Compact Parking Areas/Drives 5 12-May-15 19-May-15 54Grade/Compact Parking Areas/Drives 19-May-15
S2040 Rock and Roll Parking Areas/Drives 5 19-May-15 27-May-15 54 Rock and Roll Parking Areas/Drives 27-May-15
S2050 Place Curbs 5 27-May-15 03-Jun-15 54 Place Curbs 03-Jun-15
Remaining Level of Effort Milestone Page 1 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
S2080 Place Asphalt 5 27-May-15 03-Jun-15 79 Place Asphalt 03-Jun-15
S2060 F/P Sidewalks 10 03-Jun-15 17-Jun-15 54 F/P Sidewalks 17-Jun-15
S2100 Trim Out Drainage/Tie In Gutters 5 03-Jun-15 10-Jun-15 69 Trim Out Drainage/Tie In Gutters 10-Jun-15
S2150 Stripe / Place Signage at Parking Areas/Drives 5 03-Jun-15 10-Jun-15 79 / Place Signage at Parking Areas/Drives 10-Jun-15
S2090 Fine Grade Landscaped Areas 10 17-Jun-15 01-Jul-15 54 Fine Grade Landscaped Areas 01-Jul-15
S2110 Plant Trees/Bedding Areas 5 01-Jul-15 09-Jul-15 54 Plant Trees/Bedding Areas 09-Jul-15
S2130 Trim Out / Test Sprinklers 5 01-Jul-15 09-Jul-15 54 Trim Out / Test Sprinklers 09-Jul-15
S2140 Place Planters 5 01-Jul-15 09-Jul-15 54 Place Planters 09-Jul-15
S2120 Sod Grass Areas 5 09-Jul-15 16-Jul-15 54 Sod Grass Areas 16-Jul-15
Structure and
an Shell 182 02-Sep-14 21-May-15 92 21-May-15, Struct
Building A (Multi-Floor)
( 182 02-Sep-14 21-May-15 92 21-May-15, Buildin
SH1000 F/R/P Spread / Continuous Footings 15 02-Sep-14 22-Sep-14 57 gs 22-Sep-14
SH1010 F/R/P Elevator Pit 5 02-Sep-14 08-Sep-14 244 Pit 08-Sep-14
SH1020 F/R/P Stair Tower / RR Towers 10 02-Sep-14 15-Sep-14 244 rs 15-Sep-14
SH1060 Build CMU Towers 20 16-Sep-14 14-Oct-14 244wers 14-Oct-14
SH1070 Erect Structural Steel CL A to D 10 16-Oct-14 30-Oct-14 32 L A to D 30-Oct-14
SH1180 Erect Structural Steel CL D to G 15 30-Oct-14 20-Nov-14 32 CL D to G 20-Nov-14
SH1200 Rough-in U/G MEP 10 13-Nov-14 28-Nov-14 59 -in U/G MEP 28-Nov-14
SH1100 F/P 2nd Floor Concrete Deck CL A to D 5 20-Nov-14 28-Nov-14 38eck CL A to D 28-Nov-14
SH2240 Hang Third Floor Joist CL D to G 5 20-Nov-14 28-Nov-14 32oist CL D to G 28-Nov-14
SH1110 F/P 3rd Floor Concrete Deck CL A to D 5 28-Nov-14 05-Dec-14 38Deck CL A to D 05-Dec-14
SH1220 F/P SOG 10 28-Nov-14 12-Dec-14 59 F/P SOG 12-Dec-14
SH2260 Deck Second Floor CL D to G 3 28-Nov-14 03-Dec-14 32Floor CL D to G 03-Dec-14
SH2230 Deck Third Floor CL D to G 3 03-Dec-14 08-Dec-14 32 Floor CL D to G 08-Dec-14
SH2130 Frame Exterior Walls 20 05-Dec-14 06-Jan-15 38 e Exterior Walls 06-Jan-15
SH2250 F/P 2nd Floor Lt.Wgt. Concrete Deck CL D to G 5 08-Dec-14 15-Dec-14 110 Deck CL D to G 15-Dec-14
SH2220 F/P 3rd Floor Lt.Wgt. Concrete Deck CL D to G 5 09-Dec-14 16-Dec-14 32 Deck CL D to G 16-Dec-14
SH1170 Frame Roof 10 16-Dec-14 31-Dec-14 32 Frame Roof 31-Dec-14
SH1160 Deck Roof 5 31-Dec-14 08-Jan-15 56 Deck Roof 08-Jan-15
SH1270 Lay Up Brick Veneer 80 06-Jan-15 30-Apr-15 54Lay Up Brick Veneer 30-Apr-15
SH1150 Install Roofing System 20 08-Jan-15 06-Feb-15 150 stall Roofing System 06-Feb-15
Remaining Level of Effort Milestone Page 2 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
SH1370 Trim Out Soffit/Flashing 5 06-Feb-15 13-Feb-15 150 Trim Out Soffit/Flashing 13-Feb-15
SH1260 Install Exterior Windows 10 30-Apr-15 14-May-15 56 Install Exterior Windows 14-May-15
SH1290 Install Exterior Doors 8 30-Apr-15 12-May-15 58 Install Exterior Doors 12-May-15
SH1390 Install Building Signage 5 30-Apr-15 07-May-15 97 Install Building Signage 07-May-15
SH1380 Punchout Exterior 5 14-May-15 21-May-15 92 Punchout Exterior 21-May-15
Building B ( Single Floor) 145 23-Sep-14 21-Apr-15 114 21-Apr-15, Building B
SH2000 F/R/P Spread/Continuous Footings 20 23-Sep-14 21-Oct-14 57otings 21-Oct-14
SH2020 Rough-in U/G MEP 10 22-Oct-14 04-Nov-14 57 U/G MEP 04-Nov-14
SH2050 Backfill / Compact 10 05-Nov-14 18-Nov-14 57 l / Compact 18-Nov-14
SH2060 Erect Structural Steel 5 24-Dec-14 02-Jan-15 32ect Structural Steel 02-Jan-15
SH2080 Frame Roof 10 02-Jan-15 16-Jan-15 32 Frame Roof 16-Jan-15
SH2090 Deck roof 5 16-Jan-15 26-Jan-15 32 Deck roof 26-Jan-15
SH2200 Frame Exterior Walls 10 26-Jan-15 09-Feb-15 32 Frame Exterior Walls 09-Feb-15
SH2180 Sheath Exterior Walls 10 09-Feb-15 24-Feb-15 32 Sheath Exterior Walls 24-Feb-15
SH2160 Lay Up Brick Veneer 20 24-Feb-15 24-Mar-15 32 Lay Up Brick Veneer 24-Mar-15
SH2150 Lay Pre-cast 5 17-Mar-15 24-Mar-15 32 Lay Pre-cast 24-Mar-15
SH2210 Install Breezeway Store Fronts 20 24-Mar-15 21-Apr-15 114 Install Breezeway Store Fronts 21-Apr-15
SH2170 Install Exterior Windows 10 24-Mar-15 07-Apr-15 32 Install Exterior Windows 07-Apr-15
SH2190 Install Exterior Doors 5 24-Mar-15 31-Mar-15 129 Install Exterior Doors 31-Mar-15
Interior Build
Build-out - Building A 143 12-Dec-14 09-Jul-15 59 09-Jul-15,
1st Floor 136 12-Dec-14 29-Jun-15 66 29-Jun-15, 1
Working Area
A 110 12-Dec-14 21-May-15 92 21-May-15, Work
BA1000 Rough-in MEP 40 12-Dec-14 11-Feb-15 59 Rough-in MEP 11-Feb-15
BA1020 Frame Interior Partitions 15 29-Dec-14 21-Jan-15 177 e Interior Partitions 21-Jan-15
BA1050 Hang/Finish Drywall 20 11-Feb-15 12-Mar-15 59 Hang/Finish Drywall 12-Mar-15
BA1070 Prime/1st Coat Paint 5 12-Mar-15 19-Mar-15 59 Prime/1st Coat Paint 19-Mar-15
BA1180 Trimout / Finishes 40 19-Mar-15 14-May-15 59 Trimout / Finishes 14-May-15
A1030 Punchout 1st Floor 5 14-May-15 21-May-15 59 Punchout 1st Floor 21-May-15
Rest Rooms
Roo 53 15-Dec-14 04-Mar-15 110 04-Mar-15, Rest Rooms
BA1240 Block Filland Prime 5 15-Dec-14 22-Dec-14 110ock Filland Prime 22-Dec-14
BA1110 Rough-in Plumbing 10 22-Dec-14 07-Jan-15 110Rough-in Plumbing 07-Jan-15
Remaining Level of Effort Milestone Page 3 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
BA1100 Hang / Finish Drywall 10 07-Jan-15 22-Jan-15 110Hang / Finish Drywall 22-Jan-15
BA1340 Prime/1st Coat 3 22-Jan-15 27-Jan-15 110 Prime/1st Coat 27-Jan-15
BA1350 Trimout / Finishes 25 27-Jan-15 04-Mar-15 110 Trimout / Finishes 04-Mar-15
Elevator Equipment
E 0 0
Mech/Elec Rooms 135 15-Dec-14 29-Jun-15 66 29-Jun-15, M
BA1250 Block Fill and Prime 5 15-Dec-14 22-Dec-14 125 ck Fill and Prime 22-Dec-14
BA1200 Rough-in MEP 25 22-Dec-14 29-Jan-15 125 Rough-in MEP 29-Jan-15
BA1490 Commission Fire Pumps/Sprinklers 5 29-Jan-15 05-Feb-15 128 Fire Pumps/Sprinklers 05-Feb-15
BA1500 Install Lighting 5 29-Jan-15 05-Feb-15 125 Install Lighting 05-Feb-15
BA1630 Pull Main Feed to Transformer (Rm 107) 5 29-Jan-15 05-Feb-15 161 Transformer (Rm 107) 05-Feb-15
BA1510 Trim Out Lights 3 05-Feb-15 10-Feb-15 125 Trim Out Lights 10-Feb-15
BA1590 Mount AHU-4 5 19-Mar-15 26-Mar-15 91 Mount AHU-4 26-Mar-15
BA1600 Pipe AHU-4 5 26-Mar-15 02-Apr-15 91 Pipe AHU-4 02-Apr-15
BA1530 Mount Chiller (Exterior) 3 30-Apr-15 05-May-15 54 Mount Chiller (Exterior) 05-May-15
BA4000 Land Chillers 5 30-Apr-15 07-May-15 61 Land Chillers 07-May-15
BA1550 Tie-in HVAC Piping 10 05-May-15 19-May-15 94 Tie-in HVAC Piping 19-May-15
BA1640 Pull distribution to Main Feed (Rm 107) 5 07-May-15 14-May-15 97ull distribution to Main Feed (Rm 107) 14-May-15
BA4010 Pipe Chillers To Mechanical Room 5 07-May-15 14-May-15 61 Pipe Chillers To Mechanical Room 14-May-15
BA1660 Energize Building 5 14-May-15 21-May-15 56 Energize Building 21-May-15
BA1570 Commission HVAC Units 10 08-Jun-15 22-Jun-15 45 Commission HVAC Units 22-Jun-15
BA1580 Test and Balance Ventillation 5 22-Jun-15 29-Jun-15 45 Test and Balance Ventillation 29-Jun-15
Stairwells 0 0
2nd Floor 113 06-Jan-15 17-Jun-15 74 17-Jun-15, 2n
Working Area
A 113 06-Jan-15 17-Jun-15 74 17-Jun-15, W
BA1850 Rough-in MEP 45 06-Jan-15 12-Mar-15 41 Rough-in MEP 12-Mar-15
BA1830 Frame Interior Partitions 15 21-Jan-15 11-Feb-15 162 ame Interior Partitions 11-Feb-15
BA1800 Hang / Finish Drywall 25 12-Mar-15 16-Apr-15 41 Hang / Finish Drywall 16-Apr-15
BA1780 Prime/1st Coat Paint 8 16-Apr-15 28-Apr-15 41 Prime/1st Coat Paint 28-Apr-15
BA1740 Trmiout / Finishes 30 28-Apr-15 10-Jun-15 41 Trmiout / Finishes 10-Jun-15
BA2570 Punchout 2nd Floor 5 10-Jun-15 17-Jun-15 41 Punchout 2nd Floor 17-Jun-15
Rest Rooms
Roo 53 06-Jan-15 24-Mar-15 96 24-Mar-15, Rest Rooms
Remaining Level of Effort Milestone Page 4 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
BA2000 Block Filland Prime 5 06-Jan-15 13-Jan-15 38 Block Filland Prime 13-Jan-15
BA2070 Rough-in MEP 15 13-Jan-15 04-Feb-15 38 Rough-in MEP 04-Feb-15
BA2020 Hang Finish Drywall 10 04-Feb-15 19-Feb-15 96 Hang Finish Drywall 19-Feb-15
BA1940 Prime/1st Coat 3 19-Feb-15 24-Feb-15 96 Prime/1st Coat 24-Feb-15
BA1990 Trimout / Finishes 20 24-Feb-15 24-Mar-15 96 Trimout / Finishes 24-Mar-15
Mech Roo
Room 8 28-Apr-15 08-May-15 65 08-May-15, Mech R
BA2090 Mount AHU-5 5 28-Apr-15 05-May-15 65 Mount AHU-5 05-May-15
BA2100 Mount Power/Light Panels 4 28-Apr-15 04-May-15 66 Mount Power/Light Panels 04-May-15
BA2110 Provide Power to AHU-5 3 05-May-15 08-May-15 65 Provide Power to AHU-5 08-May-15
3rd Floor 126 08-Jan-15 09-Jul-15 38 09-Jul-15,
Working Area
A 108 04-Feb-15 09-Jul-15 38 09-Jul-15,
BA2300 Rough-in MEP 45 04-Feb-15 09-Apr-15 38 Rough-in MEP 09-Apr-15
BA2250 Hang Drywall 25 09-Apr-15 14-May-15 38 Hang Drywall 14-May-15
BA2230 Prime/1st Coat Paint 8 14-May-15 27-May-15 38 Prime/1st Coat Paint 27-May-15
BA2190 Trmiout /Finishes 25 27-May-15 01-Jul-15 38 Trmiout /Finishes 01-Jul-15
BA2600 Punchout 3rd Floor 5 01-Jul-15 09-Jul-15 38 Punchout 3rd Floor 09-Jul-15
Rest Rooms
Roo 52 08-Jan-15 25-Mar-15 107 25-Mar-15, Rest Rooms
BA2450 Block Filland Prime 5 08-Jan-15 15-Jan-15 107 Block Filland Prime 15-Jan-15
BA2520 Rough-in MEP 15 15-Jan-15 06-Feb-15 107 Rough-in MEP 06-Feb-15
BA2470 Hang Drywall 3 06-Feb-15 11-Feb-15 107 Hang Drywall 11-Feb-15
BA2460 Finish Drywall 6 11-Feb-15 20-Feb-15 107 Finish Drywall 20-Feb-15
BA2390 Prime/1st Coat 3 20-Feb-15 25-Feb-15 107 Prime/1st Coat 25-Feb-15
BA2440 Trimout / Finishes 20 25-Feb-15 25-Mar-15 107 Trimout / Finishes 25-Mar-15
Mech Roo
Room/Computer Room 8 27-May-15 08-Jun-15 45 08-Jun-15, Mec
BA2550 Mount AHU-5 5 27-May-15 03-Jun-15 45 Mount AHU-5 03-Jun-15
BA2540 Mount Power/Light Panels 4 27-May-15 02-Jun-15 46 Mount Power/Light Panels 02-Jun-15
BA2530 Provide Power to AHU-6 3 03-Jun-15 08-Jun-15 45 Provide Power to AHU-6 08-Jun-15
Interior Build
Build-out - Building B 142 26-Jan-15 17-Aug-15 32 17-Au
Office Areas
Area 142 26-Jan-15 17-Aug-15 32 17-Au
BA2790 Rough-in MEP 35 26-Jan-15 17-Mar-15 139 Rough-in MEP 17-Mar-15
BA2740 Hang Drywall 20 07-Apr-15 05-May-15 32 Hang Drywall 05-May-15
Remaining Level of Effort Milestone Page 5 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work
© Oracle Corporation
Critical Remaining Work
Okaloosa County Administration Building Preliminary Schedule Lord and Son - Preliminary 08-Sep-14 16:58
Activity ID Activity Name Original Start Finish Total Float r 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015 5
Duration
A S O N D J F M A M J Jul A S ct
BA2720 Prime/1st Coat Paint 5 05-May-15 12-May-15 32 Prime/1st Coat Paint 12-May-15
BA2680 Trimout / Finishes 41 12-May-15 10-Jul-15 32 Trimout / Finishes 10-Jul-15
B3000 Punchout 1st Floor 26 10-Jul-15 17-Aug-15 32 Punchout 1st Floor 17-Au
Mechanical Areas
Mechanica 12 05-May-15 21-May-15 66 21-May-15, Mech
BA2930 Prime/1st Coat Rm 244 2 05-May-15 07-May-15 58 Prime/1st Coat Rm 244 07-May-15
BA2920 Mount AHU-1 & AHU-2 5 07-May-15 14-May-15 58 Mount AHU-1 & AHU-2 14-May-15
BA2910 Mount Power/Light Panels 4 07-May-15 13-May-15 59 Mount Power/Light Panels 13-May-15
BA2900 Provide Power to AHU-1 & AHU-2 3 14-May-15 19-May-15 58 Provide Power to AHU-1 & AHU-2 19-May-15
BA2890 Final Paint Rm 244 5 14-May-15 21-May-15 66 Final Paint Rm 244 21-May-15
Entry Hall / Meeting Chamber 70 05-May-15 13-Aug-15 34 13-Au
BA2880 Rough-in Fire Sprinklers 20 05-May-15 03-Jun-15 34 Rough-in Fire Sprinklers 03-Jun-15
BA2850 Hang Drywall 15 03-Jun-15 24-Jun-15 34 Hang Drywall 24-Jun-15
BA2830 Prime/1st Coat Paint 5 24-Jun-15 01-Jul-15 34 Prime/1st Coat Paint 01-Jul-15
BA2990 Build Dais and Ramp 10 01-Jul-15 16-Jul-15 54 Build Dais and Ramp 16-Jul-15
BA4200 Trimout / Finishes 25 01-Jul-15 06-Aug-15 34 Trimout / Finishes 06-Aug
BA3030 Punchout Meeting Chamber 5 06-Aug-15 13-Aug-15 34 Punchout Meeting Chamber 13-Au
Breezeway 0 0
Remaining Level of Effort Milestone Page 6 of 6
Actual Level of Effort Summary
Actual Work
Remaining Work