Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 9 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Regulation).
3.04 Amending and Supplementing Contract
Documents
A. The Contract Documents may be amended to
provide for additions, deletions, and revisions in the
Work or to modify the terms and conditions thereofin one
or more of the following ways: (i) a Written Amendment;
B. The requirements of the Contract Documents
may be supplemented, and minor variations and
deviations in the Work may be authorized, by one or
more of the following ways: (i) a Field Order; (ii)
ENGINEER’s approval ofa Shop Drawing or Sample; or
(iii) ENGINEER’ written interpretation or clarification.
3.05 Reuse of Documents
A. CONTRACTOR and any Subcontractor or
Supplier or other individual or entity performing or
furnishing any of the Work under a direct or indirect
contract with OWNER: (i) shall not have or acquire any
title to or ownership rights in any of the Drawings,
Specifications, or other documents (or copies of any
thereof) prepared by or bearing the seal of ENGINEER
or ENGINEER’s Consultant, including electronic media
editions; and (ii) shall not reuse any of such Drawings,
Specifications, other documents, or copies thereof on
extensions of the Project or any other project without
written consent of OWNER and ENGINEER and specific
written verification or adaption by ENGINEER. This
prohibition will survive final payment, completion, and
acceptance of the Work, or termination or completion of
the Contract. Nothing herein shall preclude
CONTRACTOR from retaining copies of the Contract
Documents for record purposes.
ARTICLE 4 - AVAILABILITY OF LANDS;
SUBSURFACE AND PHYSICAL CONDITIONS;
REFERENCE POINTS
4.01 Availability of Lands
A. OWNER shail furnish the Site. OWNER shail
notify CONTRACTOR of any encumbrances or
restrictions not of general application but specifically
Russell Stephenson — Electrical Manhole Rehabilitation
related to use of the Site with which CONTRACTOR
must comply in performing the Work. OWNER will
obtain in a timely manner and pay for easements for
permanent structures or permanent changes in existing
facilities. I CONTRACTOR and OWNER are unable to
agree on entitlement to or on the amount or extent, ifany,
of any adjustment in the Contract Price or Contract
Times, or both, as a result of any delay in OWNER’s
furnishing the Site, CONTRACTOR may make a Claim
therefor as provided in paragraph 10.05.
B. CONTRACTOR shail provide for all additional
lands and access thereto that may be required for
temporary construction facilities or storage of materials
and equipment.
4.02. Subsurface and Physical Conditions
A. Reports and Drawings: The Supplementary
Conditions identify:
1. those reports of explorations and tests of
subsurface conditions at or contiguous to the Site that
ENGINEER has used in preparing the Contract
Documents; and
2. those drawings of physical conditions in or
relating to existing surface or subsurface structures at
or contiguous to the Site (except Underground
Facilities) that ENGINEER has used in preparing the
Contract Documents.
B. Limited Reliance by CONTRACTOR on
Technical Data Authorized) CONTRACTOR may rely
upon the general accuracy of the “technical data”
contained in such reports and drawings, but such reports
and drawings are not Contract Documents. Such “techni-
cal data” is identified in the Supplementary Conditions.
Except for such reliance on such “technical data,”
CONTRACTOR may not rely upon or make any Claim
against OWNER, ENGINEER, or any of ENGINEER’s
Consultants with respect to:
1. the completeness of such reports and
drawings for CONTRACTOR’s purposes, including,
but not limited to, any aspects of the means, methods,
techniques, sequences, and procedures of
construction to be employed by CONTRACTOR, and
safety precautions and programs incident thereto; or
2. other data, interpretations, opinions, and
information contained in such reports or shown or
indicated in such drawings; or
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-13
SECTION 00700
GENERAL CONDITIONS
3. any CONTRACTOR interpretation of or
conclusion drawn from any "technical data" or any
such other data, interpretations, opinions, or infor-
mation.
4.03 Differing Subsurface or Physical Conditions
A. Notice: If CONTRACTOR believes that any
subsurface or physical condition at or contiguous to the
Site that is uncovered or revealed either:
1. is of such a nature as to establish that any
“technical data” on which CONTRACTOR is entitled
to rely as provided in paragraph 4.02 is materially
inaccurate; or
2. is of such a nature as to require a change in
the Contract Documents; or
3. differs materially from that shown or
indicated in the Contract Documents; or
4. is ofan unusual nature, and differs materially
from conditions ordinarily encountered and generally
recognized as inherent in work of the character
provided for in the Contract Documents;
then CONTRACTOR shall, promptly after becoming
aware thereof and before further disturbing the
subsurface or physical conditions or performing any
Work in connection therewith (except in an emergency as
required by paragraph 6.16.A), notify OWNER and
ENGINEER in writing about such condition.
CONTRACTOR shall not further disturb such condition
or perform any Work in connection therewith (except as
aforesaid) until receipt of written order to do so.
B. ENGINEER's Review: After receipt of written
notice as required by paragraph 4.03.A, ENGINEER will
promptly review the pertinent condition, determine the
necessity of OWNER's obtaining additional exploration
or tests with respect thereto, and advise OWNER in
writing (with a copy to CONTRACTOR) of
ENGINEER’s findings and conclusions.
C. Possible Price and Times Adjustments
1. The Contract Price or the Contract Times,
or both, will be equitably adjusted to the extent that
the existence of such differing subsurface or physical
condition causes an increase or decrease in
CONTRACTOR’s cost of, or time required for,
performance of the Work; subject, however, to the
following:
a. such condition must meet any one or
more of the categories described in paragraph
4.03.A; and
b. with respect to Work that is paid for on
a Unit Price Basis, any adjustment in Contract
Price will be subject to the provisions of para-
graphs 9.08 and 11.03.
2. CONTRACTOR shall not be entitled to any
adjustment in the Contract Price or Contract Times iff
a. CONTRACTOR knew of the existence
of such conditions at the time CONTRACTOR
made a final commitment to OWNER in respect
of Contract Price and Contract Times by the
submission of a Bid or becoming bound under a
negotiated contract; or
b. the existence of such condition could
reasonably have been discovered or revealed as a
result of any examination, investigation, explo-
ration, test, or study of the Site and contiguous
areas required by the Bidding Requirements or
Contract Documents to be conducted by or for
CONTRACTOR prior to CONTRACTOR's
making such final commitment; or
c. CONTRACTOR failed to give the
written notice within the time and as required by
paragraph 4.03.A.
3. IfOWNER and CONTRACTOR are unable
to agree on entitlement to or on the amount or extent,
if any, of any adjustment in the Contract Price or
Contract Times, or both, a Claim may be made
therefor as provided in paragraph 10.05. However,
OWNER, ENGINEER, and ENGINEER’s
Consultants shall not be liable to CONTRACTOR for
any claims, costs, losses, or damages (including but
not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs)
sustained by CONTRACTOR on or in connection
with any other project or anticipated project.
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
00700-14
DATE: 5/13/2012
Russell Stephenson — Electrical Manhole Rehabilitation
SECTION 00700
GENERAL CONDITIONS
4.04 Underground Facilities
A. Shown or Indicated: The information and data
shown or indicated in the Contract Documents with
respect to existing Underground Facilities at or
contiguous to the Site is based on information and data
furnished to OWNER or ENGINEER by the owners of
such Underground Facilities, including OWNER, or by
others. Unless it is otherwise expressly provided in the
Supplementary Conditions:
1. OWNER and ENGINEER shall not be
responsible for the accuracy or completeness of any
such information or data; and
2. the cost of all of the following will be
included in the Contract Price, and CONTRACTOR
shall have full responsibility for:
a. reviewing and checking all such
information and data,
b. locating all Underground Facilities
shown or indicated in the Contract Documents,
c. coordination of the Work with the
owners of such Underground Facilities, including
OWNER, during construction, and
d. the safety and protection of all such
Underground Facilities and repairing any
damage thereto resulting from the Work.
B. Not Shewn or Indicated
1. Ifan Underground Facility is uncovered or
revealed at or contiguous to the Site which was not
shown or indicated or not shown or indicated with
reasonable accuracy in the Contract Documents,
CONTRACTOR shall, promptly after becoming
aware thereof and before further disturbing conditions
affected thereby or performing any Work in
connection therewith (except in an emergency as
required by paragraph 6.16.A), identify the owner of
such Underground Facility and give written notice to
that owner and to OWNER and ENGINEER.
ENGINEER will promptly review the Underground
Facility and determine the extent, if any, to which a
change is required in the Contract Documents to
reflect and document the consequences of the
existence or location of the Underground Facility.
During such time, CONTRACTOR shall be
responsible for the safety and protection of the
underground facility.
Russell Stephenson — Electrical Manhole Rehabilitation
2. If ENGINEER concludes that a change in
the Contract Documents is required, a Work Change
Directive or a Change Order will be issued to reflect
and document such consequences. An equitable
adjustment shall be made in the Contract Price or
Contract Times, or both, to the extent that they are
attributable to the existence or location of any
Underground Facility that was not shown or indicated
or not shown with reasonable accuracy in the
Contract Documents and that CONTRACTOR did
not know of and could not reasonably have been
expected to be aware of or to have anticipated. If
OWNER and CONTRACTOR are unable to agree on
entitlement to or on the amount or extent, if any, of
any such adjustment in Contract Price or Contract
Times, OWNER or CONTRACTOR may make a
Claim therefor as provided in paragraph 10.05.
4.05 Reference Points
A. OWNER shall provide engineering surveys to
establish reference points for construction which in
ENGINEER’s judgment are necessary to enable
CONTRACTOR to proceed with the Work.
CONTRACTOR shall be responsible for laying out the
Work, shall protect and preserve the established
reference points and property monuments, and shall make
no changes or relocations without the prior written
approval of OWNER. CONTRACTOR shall report to
ENGINEER whenever any reference point or property
monument is lost or destroyed or requires relocation
because of necessary changes in grades or locations, and
shall be responsible for the accurate replacement or
relocation of such reference points or property
monuments by professionally qualified personnel.
4.06 Hazardous Environmental Condition at Site
A. Reports and Drawings: Reference is made to the
Supplementary Conditions for the identification of those
reports and drawings relating to a Hazardous
Environmental Condition identified at the Site, ifany, that
have been utilized by the ENGINEER in the preparation
of the Contract Documents.
B. Limited Reliance by CONTRACTOR on
Technical Data Authorized: CONTRACTOR may rely
upon the general accuracy of the "technical data"
contained in such reports and drawings, but such reports
and drawings