Okaloosa County BOCC — February 18, 2014 — Underground Electric Manhole — reading text
Part 8 of 47. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 97-Underground Electric Manhole.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
“proper,” “satisfactory,” or adjectives of like effect or
import are used to describe an action or determination
of ENGINEER as to the Work, it is intended that such
exercise of professional judgement, action or
determination will be solely to evaluate, in general,
the completed Work for compliance with the require-
ments of and information in the Contract Documents
and conformance with the design concept of the com-
pleted Project as a functioning whole as shown or
indicated in the Contract Documents (unless there is a
specific statement indicating otherwise). The use of
any such term or adjective shall not be effective to
assign to ENGINEER any duty or authority to
supervise or direct the performance of the Work or
any duty or authority to undertake responsibility
contrary to the provisions of paragraph 9.10 or any
other provision of the Contract Documents.
B. Day
1. The word “day” shall constitute a calendar
day of 24 hours measured from midnight to the next
midnight.
C. Defective
1. The word “defective,” when modifying the
word “Work,” refers to Work that is unsatisfactory,
faulty, or deficient in that it does not conform to the
Contract Documents or does not meet the
requirements of any inspection, reference standard,
test, or approval referred to in the Contract
Documents, or has been damaged prior to
Russell Stephenson — Electrical Manhole Rehabilitation
ENGINEER’s recommendation of final payment @
(unless responsibility for the protection thereof has
been assumed by OWNER at Substantial Completion
in accordance with paragraph 14.04 or 14.05).
D. Furnish, Install, Perform, Provide
1. The word “furnish,” when used in connec-
tion with services, materials, or equipment, shall
mean to supply and deliver said services, materials, or
equipment to the Site (or some other specified
location) ready for use or installation and in usable or
operable condition.
2. The word “install,” when used in connection
with services, materials, or equipment, shall mean to
put into use or place in final position said services,
materials, or equipment complete and ready for
intended use.
3. The words “perform” or “provide,” when
used in connection with services, materials, or
equipment, shail mean to furnish and install said
services, materials, or equipment complete and ready
for intended use.
4. When “furnish,” “install,” “perform,” or ©
“provide” is not used in connection with services,
materials, or equipment in a context clearly requiring
an obligation of CONTRACTOR, “provide” is
implied.
E. Unless stated otherwise in the Contract Documents,
words or phrases which have a well-known technical or
construction industry or trade meaning are used in the
Contract Documents in accordance with such recognized
meaning.
ARTICLE 2 - PRELIMINARY MATTERS
2.01 Delivery of Bonds
A. When CONTRACTOR delivers the executed
Agreements to OWNER, CONTRACTOR shall also
deliver to OWNER such Bonds as CONTRACTOR may
be required to furnish.
2.02 Copies of Documents
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-10
SECTION 00700
GENERAL CONDITIONS
A. OWNER shall furnish to CONTRACTOR up to
ten copies of the Contract Documents. Additional copies
will be furnished upon request at the cost ofreproduction.
2.03 Commencement of Contract Times; Notice to
Proceed
A. The Contract Times will commence to run on the
thirtieth day after the Effective Date of the Agreement or,
ifa Notice to Proceed is given, on the day indicated in the
Notice to Proceed. A Notice to Proceed may be given at
any time within 30 days after the Effective Date of the
Agreement. In no event will the Contract Times com-
mence to run later than the sixtieth day after the day of
Bid opening or the thirtieth day after the Effective Date of
the Agreement, whichever date is earlier.
2.04 Starting the Work
A. CONTRACTOR shall start to perform the Work
on the date when the Contract Times commence to run.
No Work shall be done at the Site prior to the date on
which the Contract Times commence to run.
2.05 Before Starting Construction
A. CONTRACTOR’s Review of Contract Docu-
ments: Before undertaking each part of the Work,
CONTRACTOR shall carefully study and compare the
Contract Documents and check and verify pertinent
figures therein and all applicable field measurements.
CONTRACTOR shall promptly report in writing to
ENGINEER any conflict, error, ambiguity, or
discrepancy which CONTRACTOR may discover and
shall obtain a written interpretation or clarification from
ENGINEER before proceeding with any Work affected
thereby; however, CONTRACTOR shall not be liable to
OWNER or ENGINEER for failure to report any conflict,
error, ambiguity, or discrepancy in the Contract
Documents unless CONTRACTOR knew or reasonably
should have known thereof.
B. Preliminary Schedules: Within ten days after the
Effective Date ofthe Agreement (unless otherwise speci-
fied in the General Requirements), CONTRACTOR shall
submit to ENGINEER for its timely review:
1. a preliminary progress schedule indicating
the times (numbers of days or dates) for starting and
completing the various stages of the Work, including
any Milestones specified in the Contract Documents;
2. apreliminary schedule of Shop Drawing and
Sample submittals which will list each required sub-
Russell Stephenson — Electrical Manhole Rehabilitation
mittal and the times for submitting, reviewing, and
processing such submittal; and
3. apreliminary schedule of values for all ofthe
Work which includes quantities and prices of items
which when added together equal the Contract Price
and subdivides the Work into component parts in
sufficient detail to serve as the basis for progress
payments during performance of the Work. Such
prices will include an appropriate amount ofoverhead
and profit applicable to each item of Work.
C. Evidence of Insurance: Before any Work at the
Site is started, CONTRACTOR and OWNER shall each
deliver to the other, with copies to each additional insured
identified in the Supplementary Conditions, certificates of
insurance (and other evidence of insurance which either
of them or any additional insured may reasonably request)
which CONTRACTOR and OWNER respectively are
required to purchase and maintain in accordance with
Article 5.
2.06 Preconstruction Conference
A. Within 20 days after the Contract Times start to
run, but before any Work at the Site is started, a
conference attended by CONTRACTOR, ENGINEER,
and others as appropriate will be held to establish a
working understanding among the parties as to the Work
and to discuss the schedules referred to in paragraph
2.05.B, procedures for handling Shop Drawings and
other submittals, processing Applications for Payment,
and maintaining required records.
2.07 Initial Acceptance of Schedules
A. Unless otherwise provided in the Contract Docu-
ments, at least ten days before submission of the first
Application for Payment a conference attended by
CONTRACTOR, ENGINEER, and others as appropriate
will be held to review for acceptability to ENGINEER, as
provided below, the schedules submitted in accordance
with paragraph 2.05.B. CONTRACTOR shall have an
additional ten days to make corrections and adjustments
and to complete and resubmit the schedules. No progress
payment shall be made to CONTRACTOR until
acceptable schedules are submitted to ENGINEER.
1. The progress schedule will be acceptable to
ENGINEER if it provides an orderly progression of
the Work to completion within any specified
Milestones and the Contract Times. Such acceptance
will not impose on ENGINEER responsibility for the
progress schedule, for sequencing, scheduling, or
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-11
SECTION 00700
GENERAL CONDITIONS
progress of the Work nor interfere with or relieve
CONTRACTOR from CONTRACTOR’s | full
responsibility therefor.
2. CONTRACTOR’s schedule of Shop
Drawing and Sample submittals will be acceptable to
ENGINEER if it provides a workable arrangement
for reviewing and processing the required submittals.
3. CONTRACTOR’s schedule of values will
be acceptable to ENGINEER as to form and
substance if it provides a reasonable allocation of the
Contract Price to component parts of the Work.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT,
AMENDING, REUSE
3.01 Intent
A. The Contract Documents are complementary;
what is called for by one is as binding as if called for by
all.
B. It is the intent of the Contract Documents to
describe a functionally complete Project (or part thereof)
to be constructed in accordance with the Contract
Documents. Any labor, documentation, services,
materials, or equipment that may reasonably be inferred
from the Contract Documents or from prevailing custom
or trade usage as being required to produce the intended
result will be provided whether or not specifically called
for at no additional cost to OWNER.
C. Clarifications and interpretations of the Contract
Documents shall be issued by ENGINEER as provided in
Article 9.
3.02 Reference Standards
A. Standards, Specifications, Codes, Laws, and
Regulations
1. Reference to standards, specifications,
manuals, or codes of any technical society,
organization, or association, or to Laws or
Regulations, whether such reference be specific or by
implication, shall mean the standard, specification,
manual, code, or Laws or Regulations in effect at the
time of opening of Bids (or on the Effective Date of
the Agreement if there were no Bids), except as may
be otherwise specifically stated in the Contract
Documents.
Russell Stephenson — Electrical Manhole Rehabilitation
2. No provision of any such standard,
specification, manual or code, or any instruction of a
Supplier shall be effective to change the duties or
responsibilities of OWNER, CONTRACTOR, or
ENGINEER, or any of their subcontractors,
consultants, agents, or employees from those set forth
in the Contract Documents, nor shall any such
provision or instruction be effective to assign to
OWNER, ENGINEER, or any of ENGINEER’s
Consultants, agents, or employees any duty or author-
ity to supervise or direct the performance of the Work
or any duty or authority to undertake responsibility
inconsistent with the provisions of the Contract
Documents.
3.03 Reporting and Resolving Discrepancies
A. Reporting Discrepancies
1. If, during the performance of the Work,
CONTRACTOR discovers any conflict, error, ambi-
guity, or discrepancy within the Contract Documents
or between the Contract Documents and any provi-
sion of any Law or Regulation applicable to the
performance of the Work or of any — standard,
specification, manual or code, or of any instruction of
any Supplier, CONTRACTOR shall report it to
ENGINEER in writing at once. CONTRACTOR
shall not proceed with the Work affected thereby
(except in an emergency as required by paragraph
6.16.A) until an amendment or supplement to the
Contract Documents has been issued by one of the
methods indicated in paragraph 3.04; provided,
however, that CONTRACTOR shall not be liable to
OWNER or ENGINEER for failure to report any
such conflict, error, ambiguity, or discrepancy unless
CONTRACTOR knew or reasonably should have
known thereof.
B. Resolving Discrepancies
l. Except as may be otherwise specifically
stated in the Contract Documents, the provisions of
the Contract Documents shail take precedence in
resolving any conflict, error, ambiguity, or discrepan-
cy between the provisions of the Contract Documents
and:
a. the provisions of any standard,
specification, manual, code, or instruction
(whether or not specifically incorporated by
reference in the Contract Documents); or
GENERAL CONDITIONS
OKALOOSA COUNTY WATER AND SEWER
DATE: 5/13/2012
00700-12
SECTION 00700
GENERAL CONDITIONS
b. the provisions of any Laws or
Regulations applicable to the performance of the
Work (unless such an interpretation of the provi-
sions of the Contract Documents would result in
violation of such Law or